Cabinet, Tuesday 14 July 2026 at 6.30pm

Enterprise Resource Planning Programme - Phase 2

Decided Executive 2 papers

AI summaryHaringey Cabinet has approved the Full Business Case to replace its ageing SAP ERP system, agreed to run a procurement through the CCS Back Office Software 2 framework, and approved the transformation budget funded from capital receipts.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedIncludes ERP replacement and possible Business Integration procurement
Money10-year value in exempt appendixTransformation costs from Flexible Use of Capital Receipts
What happens nextProcurement and supplier selectionFinal supplier recommendation returns to Cabinet at award
Who it affectsAll wardsFinance, HR, Procurement and Payroll across the council

What was decided

Cabinet approved the Full Business Case for replacing the council's ERP system, which supports finance, procurement, HR and payroll, and approved starting the procurement. Report 3.1, 3.2

Cabinet approved a waiver to set the social value weighting at 5 percent for this procurement, below the usual 10 percent minimum. Report 3.4, 6.21, 6.24

Cabinet approved the transformation budget, funded from Flexible Use of Capital Receipts, subject to full Council approval of the capital receipts allocation. Report 3.5

Why

The current SAP ECC system, installed in 2001, reaches the end of mainstream support in December 2027 and is increasingly difficult to maintain. Report 1.2, 6.2

Finance, HR, procurement and payroll currently rely on manual workarounds and spreadsheets, which increases error risk and weakens controls. Report 4.2, 6.3, P52

A competitive procurement through an established framework is expected to give better value for money than a direct award or doing nothing. Report 4.3, 4.4, 5.3, 5.4, P42

What happens next

A revenue budget increase will be sought for 2028/29 and the Medium Term Financial Strategy to cover ongoing costs once the new system is live. Report 3.6

Implementation is expected to begin in January 2027, with the new system going live in July 2028. Report 3.6, P93

Final contract values and the recommended supplier will return to Cabinet at contract award. Report 3.7, P98

The money

  • £500,000 Threshold above which Cabinet must approve the start of a procurement Report 3.2, P95
  • 5% Reduced social value weighting for this procurement, down from the usual minimum of 10% Report 3.4, 6.24

Options considered

  • Rejected: Do nothing and sustain SAP ECC. Does not provide a sustainable 10-year solution and increases security and compliance risks Report 5.2, P37
  • Rejected: Direct award to existing supplier. Would reduce competitive tension and limit the ability to demonstrate best value Report 5.3, P39
  • Chosen: Competitive ERP procurement via CCS BOS2 framework. Maintains competitive tension and offers the strongest balance of value for money and delivery confidence Report 5.4, P41, P42
  • Rejected: Dual vendor or separate functional systems. Adds integration complexity, fragmented accountability and higher long-term support costs Report 5.5, P44
  • Rejected: Shared service with another council. No viable shared service route identified that meets the council's timescales and governance needs Report 5.6, P46

Implications

  • Financial: Transformation (one-off) costs are planned to be funded from the Flexible Use of Capital Receipts allocation, and a revenue budget increase will be needed from 2028/29. Report 3.5, 3.6, P91
  • Financial: If capital receipts from disposals do not materialise as expected, the General Fund balance may need to be used, to be replenished within three years.
  • Legal: Procurement will follow the Procurement Act 2023, the council's Contract Standing Orders and the CCS BOS2 framework, and legal has no objections to the recommendations. Report 4.4, P104, P108
  • Equalities: A modern system is expected to improve workforce data, support monitoring against the Public Sector Equality Duty and help track reasonable adjustments and training. Report P113, P114, P115
  • Climate: Moving to a cloud-based platform should reduce reliance on ageing hosted infrastructure and paper-based processing. Report 8.1, 8.2, P88
  • Risk: If the system is not replaced before the December 2027 end of support, the council faces growing security, payroll, resilience and audit risk. Report 1.2, 4.9
  • Staffing: Officers may consider delivering the Business Integration work in-house to manage cost; the decision is delegated to the Corporate Director of Finance and Resources. Report 4.6

Who and where

  • All wards in the London Borough of Haringey Report P6
  • Council staff using finance, HR, payroll and procurement processes Report 6.1, P52
  • Council managers and budget holders Report 6.1, 7.2
  • Suppliers dealing with the council Report 6.3, P52
  • Residents using council services Report 2.4

Timeline

  • 14 July 2026: Cabinet decision to approve Full Business Case and procurement Report P1, 3.1
  • January 2027: Implementation expected to commence, subject to procurement standstill Report P93
  • Spring 2027: System implementation and readiness work Report P93
  • December 2027: Current SAP ECC platform reaches end of mainstream support Report 1.2
  • July 2028: New ERP system expected to go live Report 3.6
  • 2028/29: Revenue budget increase bid to be considered as part of the budget and Medium Term Financial Strategy Report 3.6
  • Later date: Final supplier recommendation and contract award return to Cabinet Report 2.3, 3.7

Plain English for the jargon

  • ERP: Enterprise Resource Planning software supporting finance, procurement, HR and payroll
  • SAP ECC: The council's current ERP system, installed in 2001
  • CCS BOS2: Crown Commercial Service Back Office Software 2 framework, the proposed route to market
  • FUCR: Flexible Use of Capital Receipts, the proposed funding source for transformation costs
  • BI: Business Integration services to support organisational change and adoption
  • CSO: Contract Standing Order, the council's procurement rules
  • TCO: Total Cost of Ownership, used in the 10-year financial model
  • MTFS: Medium Term Financial Strategy
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10

Resolved

DECLARATIONS OF INTEREST MADE FOR THIS ITEM: None
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet

Report for: Cabinet – 14 July 2026

Item number: 10

Title: ERP Replacement Programme – Full Business Case and Approval to Procure

Report authorised by : Taryn Eves – Corporate Director of Finance & Resources

Lead Officer: Kevin Bartle – Strategic Adviser and SRO – Haringey ERP Programme (SAP replacement programme)

Ward(s) affected: All

Report for Key/ Non Key Decision: Key Decision

1. Describe the issue under consideration

1.1This report seeks approval of the Full Business Case for the replacement of the Council’s Enterprise Resource Planning (ERP) system, which supports Finance, Procurement, HR and Payroll.

1.2The current SAP ECC platform (our current ERP system) was implemented in 2001 and is now approaching end of mainstream support in December 2027. The system is increasingly difficult to sustain, relies on manual workarounds, and creates growing operational, financial, compliance and audit risk.

1.3The report also seeks approval to proceed to market for a modern, integrated, cloud-based ERP solution and associated implementation and business integration services, should they be required. It also seeks approval of the procurement strategy, the 10-year total contract value, and seeks approval of the budget required to deliver the full programme.

1.4The Business Case has been developed through a structured and evidence- led process, including market engagement, options appraisal, financial modelling, risk assessment, governance design and review of delivery models. This provides the basis for Cabinet to approve the next stage of the programme.

2. Cabinet Member Introduction 2.1 Haringey’s new leadership is dedicated to getting the basics right. 2.2 The Council is currently relying on manual intervention and offline spreadsheets for basic processes in finance, HR and procurement. This isn’t right. If we are going to build first-rate local public services, we need to have the IT systems and infrastructure to support them.

2.3The Council needs a fully functional and modern Enterprise Resource Planning platform. We take the risks of currently having a system that will be obsolete come next year incredibly seriously. Unlike in other local authorities, such as Waltham Forest, who have already implemented new solutions, Haringey has not and now we are behind the curve. The new administration is determined to remedy the situation and so we are today approving a route to market and a funding envelope, with final supplier recommendation and confirmed pricing returning to Cabinet at a later date.

2.4In procuring the new system, we must use fair procurement processes and, above all, we must use Council funds responsibly. The reality of our financial position is such that we must scrutinise our spending closely and hold value for money at the forefront of our minds. But not choosing to update such critical infrastructure would be irresponsible. The decision is not just about internal Council processes, but it is fundamentally about our residents and staff. When our residents use local services, when they want to pay a bill, or make an application, we want the systems provided to be as easy and reliable to use as possible.

2.5We have to do things differently so that we can get the best value for our local communities; centring the principle of public excellence, not inefficiency, in our procurement activities.

3. Recommendations Cabinet is asked to:

3.1Approve the Full Business Case for the replacement of the Council’s Enterprise Resource Planning (ERP) system, including the procurement of an integrated ERP solution, the associated implementation, and potentially business integration and support services.

3.2Approve the commencement of two linked procurement activities, in accordance with Contract Standing Order (CSO) 2.01(b), which requires Cabinet approval to commence procurement activity for contracts with an estimated value of £500,000 or above comprising of:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
ERP Replacement FAQsAppendix C 169 KB Download
PDF
Enterprise Resource Planning Programme: Phase 2Minutes 338 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 19 attended
TE
Taryn EvesCouncil Staff, expected
AD
Andy DonaldOfficer, expected
FA
Fiona AldermanCouncil Staff, expected
AG
Ann GrahamOfficer, expected
BF
Barry FrancisCouncil Staff, expected
JC
Jess CroweOfficer, expected
AS
Ayshe SimsekSecretary, expected
SB
Stephen Bramah-CalvertOfficer, expected
CM
Claire McCarthySecretary, expected
MB
Councillor Mark BlakeChair, present
TH
Councillor Tammy HymasVice-Chair, present
GI
Councillor Gio IozziCommittee Member, present

All 19 on the meeting page

On this subject at Haringey

Search all
  1. Enterprise Resource Planning Programme - Phase 2This decision
  2. Enterprise Resource Planning (ERP) Programme - Phase 1Decided

More from Haringey Cabinet

All decisions
MeetingDecisionOutcome
10 Nov 2026 Corporate Delivery Plan 2026-2028DECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Draft 2027-28 Budget and 2027-2032 Medium Term Financial Strategy ReportDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Regulation 19 consultation on Proposed Submission version of Haringey Local Plan 2027-2042 and submission to Secretary of StateDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Admission to Schools - Proposed Admission Arrangements for 2028/29DECLARATIONS OF INTEREST FOR THIS ITEM: None Decided Open
10 Nov 2026 Approval to extend current Highways and Street Lighting Contracts and approval of the procurement strategy for a future combined Highways and Street Lighting ContractDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies