London Borough of Haringey
Cabinet Member Signing, Friday 27 March 2026 at 9.30am

Award of contract for the acquisition of Fixtures, Fittings and Equipment (FF&E) for the Civic Centre

Approved Executive 1 paper

AI summaryCabinet Member awards two Fixtures, Fittings and Equipment contracts for Haringey's new Civic Centre, Lot 1 to Bidder J at £519,530.51 and Lot 2 to Bidder G at £256,815.50, both running for five years from 15 April 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedLot 1 to Bidder J; Lot 2 to Bidder G
Money£519,530.51 and £256,815.50Lot 1 and Lot 2 contract sums
What happens nextContracts start 15 April 2026Five year term with one year extension option
Who it affectsCivic Centre redevelopmentNew Haringey Council headquarters from 2027

What was decided

Award Lot 1 (New Furniture, Supply, Delivery and Installation) to Bidder J for £519,530.51, with Bidder K as backup if Bidder J cannot accept. Report P20

Award Lot 2 (FF&E Refurbishment, Relocation and Installation) to Bidder G for £256,815.50, with Bidder H as backup if Bidder G cannot accept. Report P22

Approve a five year contract from 15 April 2026 to 15 April 2031, with an option to extend for up to one year, and Letters of Intent for each Lot up to 10 per cent of contract value to enable early mobilisation.

Why

The Civic Centre becomes the Council's main headquarters from 2027 and needs FF&E to operate; without it, occupation is not possible and other fit out contractors and services would be disrupted. Report 4.1, 4.2, P6, P7

The two-lot approach secures high-quality new furniture where reuse is not appropriate while maximising refurbishment and reuse of existing furniture, supporting value for money and sustainability. Report 4.3, 4.4

Both lots were awarded to the highest-scoring bidders under the open tender, with social value (local employment, sustainability, community engagement) included in the quality evaluation. Report 6.3, 6.6, P25, P42

What happens next

Issue Letters of Intent for each Lot up to 10 per cent of contract value to allow early mobilisation.

Install FF&E within a 12 week period following Practical Completion of the building. Report P16

If the preferred bidder is unavailable, fall back to Bidder K (Lot 1) or Bidder H (Lot 2), being the next highest-scoring bidders. Report 6.3

The money

  • £519,530.51 Lot 1 contract sum awarded to Bidder J (New Furniture, Supply, Delivery and Installation)
  • £256,815.50 Lot 2 contract sum awarded to Bidder G (FF&E Refurbishment, Relocation and Installation)
  • £394,530.51 Base price for Lot 1 to Bidder J, with additional contingency set out in Part B Report P39
  • £156,815.00 Base price for Lot 2 to Bidder G, with additional contingency set out in Part B Report P39
  • £1.35m Capital budget provision for client fit-out items for the Civic Centre, approved by Cabinet on 12 November 2024 (capital scheme 330) Report P27, P38
  • £15,000 Approximately spent to date on client fit-out items, as reported by Finance Report P38
  • £1.35m Remaining uncommitted balance on the client fit-out budget, as reported by Finance Report P38

Options considered

  • Rejected: Do nothing (do not procure FF&E). Would prevent occupation of the Civic Centre and cause operational risks, delay to other fit out contractors, and disruption to services. Report 5.1, P6, P7
  • Chosen: Award Lot 1 to Bidder J. Highest-scoring bidder with total score 88.72 in evaluation. Report P20
  • Chosen: Award Lot 2 to Bidder G. Highest-scoring bidder with total score 89.11 in evaluation. Report P22
  • Rejected: Award Lot 1 to Bidder K as fallback. Held as backup in case Bidder J cannot accept the contract.
  • Rejected: Award Lot 2 to Bidder H as fallback. Held as backup in case Bidder G cannot accept the contract.

Implications

  • Financial: Lot 1 base price is £394,530.51 plus contingency, and Lot 2 base price is £156,815.00 plus contingency; the Finance section states the proposed contract awards can be contained within the remaining approved budget provision. Report P38, P39
  • Legal: Award is made under Contract Standing Orders 0.08 and 2.01(c) following a compliant open tender under the Procurement Act 2023 published on Find a Tender; the Director for Legal and Governance sees no legal reasons preventing approval. Report 9.2, P41, P42, P43, 9.3, P45
  • Equalities: Inclusive design with accessibility and neurodiversity considerations, including accessible furniture for circa 95% of staff, a model office for staff trials, engagement with the Disability Action Group and trade unions, and post-occupancy surveys. Report 9.4, P53, P55, P59, P61, P62, P63
  • Climate: FF&E strategy prioritises reuse, refurbishment and relocation to reduce embodied carbon, with sustainability forming part of the procurement evaluation and alignment to the Civic Centre's BREEAM Outstanding ambition. Report 8.1, 8.2, 8.3, 8.5, P36
  • Risk: Failure to procure would delay fit out contractors, occupation and service operations and undermine objectives approved by Cabinet. Report P6, P7
  • Other: Social value commitments are part of the quality evaluation, covering local employment and skills, sustainability and carbon reduction, and community engagement and reuse of furniture. Report 6.6, P24, P25

Who and where

  • Haringey Council staff relocating to the new Civic Centre headquarters Report P53, P59
  • Visitors and community users of the Civic Centre, including users of civic, democratic and community spaces Report 4.2
  • Suppliers who tendered for the FF&E lots (11 for Lot 1, 7 for Lot 2)
  • Local artists and young people involved through the Enliven Project social value commitments Report P57

Timeline

  • 12 November 2024: Cabinet approved capital budget provision of £1.35m for Civic Centre client fit-out items (capital scheme 330). Report P27, P38
  • 12 January 2026: Tender notice published on the Find a Tender service under the Procurement Act 2023. Report P19, P41
  • February 2026: Tender closed; 11 suppliers responded to Lot 1 and 7 to Lot 2 via the HPCS portal.
  • 15 April 2026: Contracts commence.
  • Within 12 weeks after Practical Completion of the building: FF&E installation is planned. Report P16
  • 15 April 2031: Contracts end (subject to up to one year extension).
  • From 2027: Civic Centre becomes the Council's main headquarters. Report 4.1

Plain English for the jargon

  • FF&E: Fixtures, Fittings and Equipment.
  • CSO: Contract Standing Orders of the Council.
  • PA23: Procurement Act 2023.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6

Resolved

RESOLVED 1. That pursuant to Contract Standing Orders 0.08 and 2.01.c) to approve the following: award of contract for Lot 1 – New Furniture (Supply, Delivery and Installation) to Bidder J for the sum of £519,530.51. 2. To approve the award of contract for Lot 2 – FF&E Refurbishment, Relocation and Installation to Bidder G for the sum of £2 56,815.50 3. To approve that the contract is for a period of 5 years commencing 15th of April 2026 to 15 th April 2031, with an option to extend for a further period(s) of up to 1 year. 4. To approve the issuance of Letters of Intent for each Lot for up to 10% of the respective contract values to enable early mobilisation 5. In the event of the Council being unable to award the contract for Lot 1 to Bidder J to agree the award of the contract to Bidder K (named in paragraph 6.1.1 of the Exempt portion of the report (Part B)) who submitted the next highest scored bid. 6. In the event of the Council being unable to award the contract for Lot 2 to Bidder G to agree the award of the contract to Bidder H (named in paragraph 6.1.2 of the Exempt portion of the report (Part B)) who submitted the next highest scored bid. Reasons for decision The Civic Centre will become the Council’s main headquarters from 2027 and is designed to support flexible, inclusive and sustainable ways of working. The FF&E procurement supports the delivery of modern office accommodation, civic and democratic functions, public-facing spaces and areas for community use within a flagship Grade II Listed building and new-build annexe. The two-Lot procurement approach enables the Council to: Secure high-quality new furniture where ... view the full minutes text for item 6.
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet Member Signing

Reasons for decision

4.1The Civic Centre will become the Council’s main headquarters from 2027 and is designed to support flexible, inclusive and sustainable ways of working.

4.2The FF&E procurement supports the delivery of modern office accommodation, civic and democratic functions, public-facing spaces and areas for community use within a flagship Grade II Listed building and new-build annexe.

4.3The two-Lot procurement approach enables the Council to:  Secure high-quality new furniture where reuse is not appropriate.  Maximise reuse, refurbishment and adaptation of existing furniture.  Support value for money and sustainability objectives.  Accommodate specialist requirements, including the Council Chamber.

4.4The proposed contracts enable the Council to deliver a fully functional client fit out within the approved programme and budget.

Alternative options considered

5.1Do Nothing 5.1.1 This option is not recommended as the Council would be unable to occupy the Civic Centre without the necessary FF&E.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Award of contract for the acquisition of Fixtures, Fittings and Equipment (FF&E) for the Civic CentreMinutes 444 KB DownloadRead as text

At this meeting

Whole meeting
6Award of contract for the acquisition of Fixtures, Fittings and Equipment (FF&E) for the Civic CentreThis decision
7Exclusion of the Press and PublicDecided

Who was there

1 of 1 attended
RG
Councillor Ruth GordonCommittee Member, present

On this subject at Haringey

Search all
  1. Award of contract for the acquisition of Fixtures, Fittings and Equipment (FF&E) for the Civic CentreThis decision
  2. Contract Award - Procurement of Enforcement Agency Services via the YPO Framework to collect PCN related debt for the AuthorityDecided
  3. Direct Award and of Residential and Nursing Care Block Contracts with OurrisDecided
  4. Selby Urban Village - award of contracts for heat supply arrangementsNoted
  5. Woodridings Court N22 Award of Construction ContractApproved
  6. Approval to Award Contract, Kings Road Car Park, N17Approved

More from Haringey Cabinet Member Signing

All decisions
MeetingDecisionOutcome
2 Nov 2026 Deaf Outreach Services ContractDECLARATIONS FOR THIS ITEM: NONE Decided Open
28 Oct 2026 Administrative amendment to Merchant Acquirer Re-ProcurementRESOLVED 1. To note the administrative error in the original report referring to Global Pay and Global Payments; 2. T... Noted Open
20 Oct 2026 Approval of Additional Expenditure and Final Payment to Accora Limited reportDECLARATIONS FOR THIS ITEM: NONE RESOLVED The Cabinet Member for Adults and Health: 1. Approved the variation of cont... Approved Open
16 Oct 2026 Approve Funding from Arts Council England to Haringey Music Service for the North London Music HubDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
13 Oct 2026 Filming at meetingsThe notice of filming at meetings was noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies