Cabinet Member Signing, Tuesday 29 August 2023 at 10.30am

Award of contract for voids works on recently acquired properties

Approved Executive 3 papers

Cabinet Member Signing approved this item on Tuesday 29 August 2023. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

RESOLVED to: 1. Approve pursuant to the Council’s Contract Standing Orders (CSO) 9.07.01d, and CSP 16.02, the appointment of Bidder A (named in the exempt part of the report)to undertake building works as set out in Appendix 2 to the properties set out in Appendix 1 for a total contract sum as set out in the exempt part of this report and within a three month period following the start of Works. Reasons for decisions The Council requires the Works set out in Appendix 2 to be completed to all of its properties in order that they can be let. Following a formal procurement process, a contractor has been identified to undertake these works. Alternative options considered It would be possible not to appoint a contractor to complete these Works. However, this option was rejected as it does not support the Council’s commitment to deliver affordable Council Homes and would perpetuate the void letting situation that currently persists. This contract was procured via a competitive tender through the LCP major works framework Lot 1.1B and HPCS for mini competition, using a standard, fixed price, JCT Contract with Contractor’s design. This is the recommended route for a contract of this value. An alternative option would have been to do a direct appointment, but this option was rejected due to the estimated contract value of the scheme and to give opportunities for local small to medium size contractors to submit a tender.
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet Member Signing, 5 pages

Report for: Cabinet Member Signing

Title: Award of contract for voids works on recently acquired properties. Report Authorised by: David Joyce, Director of Placemaking and Housing

Lead Officer: Jonathan Kirby, Assistant Director for Capital Projects and Property

Ward(s) affected: N/A

Report for Key/ Non Key Decision: Key Decision

1. Describe the issue under consideration. 1.1. This report seeks the Cabinet Member for Housing Services, Private Renters and Planning’s approval to deliver Voids Works to the properties shown on the List at Appendix 1 to bring these properties up to the approved Specification shown at Appendix 2.

1.2The Cabinet Member for Housing Services, Private Renters and Planning is asked in light of a formal procurement exercise to approve the appointment of contractor A (exempt - further details in exempt report), to deliver these Voids Works to the properties on the List shown at Appendix 1.

2. Cabinet Member Introduction 2.1 This Council remains committed to delivering the new era of Council homes that Haringey’s communities need.

2.2The List at Appendix 1 sets out the properties requiring Voids Works. These Works are necessary to ensure that the properties are immediately available for Letting.

2.3The Specification at Appendix 2 identifies the Works required to each of the properties.

3. Recommendation 3.1. It is recommended that the Cabinet Member for Housing Services, Private Renters and Planning:

3.2Approves pursuant to the Council’s Contract Standing Orders (CSO) 9.07.01d, and CSP 16.02, the appointment of Bidder A (named in the exempt part of the report) to undertake building works as set out in Appendix 2 to the properties set out in Appendix 1 for a total contract sum as set out in the exempt part of this report and within a three month period following the start of Works.

4. Reasons for decisions 4.1. The Council requires the Works set out in Appendix 2 to be completed to all of its properties in order that they can be let.

4.2Following a formal procurement process, a contractor has been identified to undertake these works. 5. Alternative options considered 5.1. It would be possible not to appoint a contractor to complete these Works. However, this option was rejected as it does not support the Council’s commitment to deliver affordable Council Homes and would perpetuate the void letting situation that currently persists.

5.2This contract was procured via a competitive tender through the LCP major works framework Lot 1.1B and HPCS for mini competition, using a standard, fixed price, JCT Contract with Contractor’s design. This is the recommended route for a contract of this value. An alternative option would have been to do a direct appointment, but this option was rejected due to the estimated contract value of the scheme and to give opportunities for local small to medium size contractors to submit a tender.

6. Background information 6.1. The Council has recently acquired the properties shown on the attached List at Appendix 1. Each of these properties requires Voids Works to be completed in order that the properties reach the minimum approved standard for Lettings.

6.2The Specification shown at Appendix 2 has been prepared in consultation with the Head of Acquisitions and Acquisitions Managers and the Haringey Repairs Service to ensure that each of the properties is refurbished to a standard that should enable the properties to require the minimum maintenance for a period of 10 years following completion of the Works.

The Build Contract 6.3. This report is seeking final approval of the JCT construction contract in order to enable the Voids Works to commence.

6.4The selected contractor was asked to respond to a Quality Assessment based on a pre – approved lump sum price. They responded with their proposal on. Full tender analysis based on the cost consultants estimate has been provided in Appendix 2, which is exempt due to the commercially sensitive nature of this information.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Final HCBS Contracts Void List. 21.06.2023Appendix 1 2 pages Download
PDF
HCBS Minimum Property StandardsAppendix 2 12 pages Download
PDF
Award of contract for voids works on recently acquired propertiesMinutes 5 pages DownloadRead as text

At this meeting

Whole meeting
6Award of contract for voids works on recently acquired propertiesThis decision
8EXCLUSION OF THE PRESS AND PUBLICDecided

On this subject at Haringey

Search all
  1. Award of contract for voids works on recently acquired propertiesThis decision
  2. Contract Award - Procurement of Enforcement Agency Services via the YPO Framework to collect PCN related debt for the AuthorityDecided
  3. Direct Award and of Residential and Nursing Care Block Contracts with OurrisDecided
  4. Selby Urban Village - award of contracts for heat supply arrangementsNoted
  5. Woodridings Court N22 Award of Construction ContractApproved
  6. Approval to Award Contract, Kings Road Car Park, N17Approved

More from Haringey Cabinet Member Signing

All decisions
MeetingDecisionOutcome
2 Nov 2026 Deaf Outreach Services ContractDECLARATIONS FOR THIS ITEM: NONE Decided Open
28 Oct 2026 Administrative amendment to Merchant Acquirer Re-ProcurementRESOLVED 1. To note the administrative error in the original report referring to Global Pay and Global Payments; 2. T... Noted Open
20 Oct 2026 Approval of Additional Expenditure and Final Payment to Accora Limited reportDECLARATIONS FOR THIS ITEM: NONE RESOLVED The Cabinet Member for Adults and Health: 1. Approved the variation of cont... Approved Open
16 Oct 2026 Approve Funding from Arts Council England to Haringey Music Service for the North London Music HubDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
13 Oct 2026 Filming at meetingsThe notice of filming at meetings was noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies