Cabinet Member Signing, Thursday 8 January 2026 at 1.30pm

Selby Urban Village - Procurement strategy for heat supply arrangements

Approved Executive 1 paper

AI summaryHaringey Cabinet Member approves direct negotiations with Energetik for heat supply at Selby Urban Village, with up to 40 year contracts for connection, supply and maintenance.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedMixed procurement for works, supply and services, 40 years
MoneyNot stated in public papersContract value is in the exempt report
What happens nextNegotiate then return for awardReport to Lead Member, Section 151 and Corporate Director after negotiations
Who it affectsSelby Urban Village schemeNew Selby Centre, 202 Council homes and small commercial unit in N17

What was decided

The Cabinet Member for Placemaking and Local Economy approved starting a mixed procurement and direct talks with Lee Valley Heat Network Operating Company Limited (trading as Energetik) for the Selby Urban Village scheme, covering connection, supply and possible management and maintenance deals lasting 40 years. Report 2.1

The procurement covers both the housing and non-residential parts of the development, and is treated as a mixed procurement of public and utility contracts, with the utility services element being the largest part and exempt from competitive procurement rules. Report 3.5, 3.6, 3.7

Officers concluded that the Procurement Act 2023 exemption at Schedule 2 paragraph 31 applies, so there is no requirement to run a competitive process or publish contract notices, though the council's internal contract standing orders still apply. Report 3.6, 3.7, P53, P54

Why

Planning policy from the London Plan, Haringey, Enfield and the GLA, along with the planning approvals already granted, require new developments like Selby Urban Village to connect to a district energy network, and Energetik is the nearest viable one. Report 3.1, 3.2, 4.1, 5.8

Other heat network suppliers such as those in Stratford or Brent were ruled out because the pipework distances and capital costs (which would fall to Haringey) make them unviable, and the project has already been designed on the basis of an Energetik connection. Report 4.2, 5.6, 5.7

The deal is also being progressed to align with the main works contractor onboarding in March to April 2026, so Energetik can oversee Stage 4 technical design for the heat supply infrastructure. Report 3.8

What happens next

Officers will open direct negotiations with Energetik, aiming to report back to the Lead Member, Section 151 Officer and Corporate Director with negotiated terms, or return to Cabinet for a different approach if those talks do not produce a workable deal. Report 3.10

Risks around the Energetik connection, including the timing of the Energy Recovery Facility replacing gas use, are being managed and are covered in more detail in the exempt report. Report 3.10, 5.10

The mixed procurement process must be completed to align with the main works contractor onboarding in March to April 2026. Report 3.8

The money

  • £500,000 or more Threshold in CSO 2.01(b) that requires Cabinet or Cabinet Member approval for procurement commencement Report 7.4
  • 40 years Standard contract duration offered by Energetik, expected to run 2030 to 2070 for the supply and service agreements Report P37

Options considered

  • Rejected: Progress with a different heating solution instead of a district heat network. Planning policy from the London Plan, Haringey and Enfield requires connection to a district energy network, though the council is still exploring alternatives as a fallback Report 4.1
  • Rejected: Connect to a different district heat network supplier. Pipework distances and capital costs for options such as Stratford or Brent make them unviable Report 4.2
  • Rejected: Procure the connection and the supply separately. Robust commercial reasons for negotiating connection and supply together for the site as a whole Report 4.3
  • Rejected: Procure connection to Energetik but not its service agreement, with Haringey or another party managing the secondary network. Technical advice indicated it is not currently the preferred option due to financial implications, though it will continue to be tested in negotiations Report 4.4
  • Rejected: Run a competitive tender process despite the procurement exemption. Unlikely to attract interest beyond Energetik and would create significant risk to programme and funding Report 4.5

Implications

  • Legal: The Director of Legal and Governance (Monitoring Officer) raised no legal reasons preventing approval, and the recommendation is in line with the Council's Contract Standing Orders, subject to the Lead Member acting with the agreement of the Leader. Report 7.5, 7.6
  • Equalities: The scheme is expected to have a positive impact for people on the housing register, families needing two and three bedroom homes, those in temporary accommodation (where women, young people and ethnic minority residents are over-represented), and the socioeconomically deprived N17 area. Report 7.9
  • Climate: Connecting to Energetik supports Haringey's zero carbon and climate resilient objectives, although the decarbonisation of Energetik's heat source is dependent on the Energy Recovery Facility, whose completion date is not yet known. Report 6.3, 6.4, 5.10
  • Risk: Risks include Energetik's decarbonisation timeline and the outcome of negotiations, with further detail held in the exempt report. Report 3.10, 5.10
  • Financial: Finance comments are contained in the exempt report, and specific contract values are not given in the public papers. Report 5.18, 7.1
  • Other: The heat supply contractor will be obliged to have due regard to the Public Sector Equality Duty under the Equality Act 2010, and contract management will be needed to prevent preventable or disproportionate inequality in delivery. Report 7.10

Who and where

  • Future residents of 202 new Council homes on Phase 2 of Selby Urban Village in N17, Bruce Castle Ward Report 5.2, 5.3
  • Users of the new Selby Centre community building, pavilion, park and sports pitches on Phase 1 Report 5.2, 5.3
  • Lee Valley Heat Network Operating Company Limited (trading as Energetik), owned by Enfield Council Report 5.9
  • London Borough of Haringey as the procuring authority and accountable body for the scheme Report 3.1, 5.1
  • The Selby Trust, the local charitable organisation partnering on the scheme Report 5.1
  • Existing Energetik customers, including around 1700 domestic customers, a hotel, medical centres and community spaces Report 5.9

Timeline

  • 19 September 2023: Cabinet approved the overall design concept and sustainability aims for the Selby Urban Village project Report 3.1
  • 19 June 2024: Cabinet Member Signing Gateway 0 Report for Phase 2 set out the preference for connection to the local District Energy Network Report 3.2, 5.7
  • 15 July 2025: Cabinet report on approval to tender a contract for the delivery of Selby Urban Village Report P67
  • 8 January 2026: Cabinet Member Signing decision to approve the mixed procurement strategy and direct negotiations with Energetik
  • March 2026: Phase 1 works scheduled to commence Report 5.2
  • By 2027: Energetik is anticipated to be regulated by Ofgem under the new heat network authorisation regime Report 5.15
  • March to April 2026: Main works contractor onboarding for Selby Urban Village, which the heat supply procurement must align with Report 3.8
  • September 2027: Phase 2 works expected to begin Report 5.2
  • December 2027: Expected completion of Phase 1 works Report 5.2
  • February 2030: Expected completion of Phase 2 works Report 5.2
  • 2030 to 2070: Proposed 40 year supply and service agreement period for community facilities and new homes Report P37

Plain English for the jargon

  • Energetik: Trading name of Lee Valley Heat Network Operating Company Limited (company number 09763702), a district heat network operator fully owned by Enfield Council
  • Mixed procurement: A procurement covering a combination of works, services and goods, treated under the rules applying to its largest element
  • District Energy Network (DEN): A piped network supplying heating and hot water to multiple buildings from a shared energy source, here the Energetik network running from the Edmonton Eco Park
  • Energy Recovery Facility (ERF): A facility expected to replace around 90% of Energetik's gas use with low carbon heat, completion date not yet confirmed
  • CSO: Council Contract Standing Orders, the internal procurement rules of the London Borough of Haringey
  • Gateway 0: An early stage project approval step in the council's capital project process, used here for Phase 2 of Selby Urban Village
  • Ofgem heat network authorisation regime: Planned regulation of heat networks from 2027 covering supplier of last resort, performance monitoring and price limits for domestic customers
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6

Resolved

DECLARATIONS OF INTEREST FOR THIS ITEM: There were none. RESOLVED It was recommended that the Cabinet Member for Placemaking and Local Economy: Approved the commencement of a mixed procurement strategy (i.e. works, supply and services) and direct negotiations with the district heat network, Lee Valley Heat Network Operating Company Limited (company number: 09763702) concerning the connection, supply and potential management/ maintenance agreements for 40 years for the Selby Urban Village scheme. The potential agreements are as set down in Section 5.14 and 5.15. Reasons for decision Cabinet approved the overall design concept and sustainability aims behind the Selby Urban Village Project on the 19 September 2023 Cabinet Report: ‘Contract award to KCA for design and architectural services for the Selby Urban Village masterplan’. Section 8, ‘Carbon and Climate Change’ of that report sets out that the energy strategy of the detailed Planning Applications would be developed in line with the energy policies of the London Plan, LBH and LBE, to achieve a zero-carbon target, and in accordance with the London Plan’s energy hierarchy. These policies and the project’s planning approvals require connecting to a District Energy Network. In the subsequent Cabinet Member Signing Report ‘Gateway 0 Report - Phase 2, Selby Urban Village, N17 – Bruce Castle Ward’ on 19 June 2024, para 8.12 notes “A communal heating system is the preferred solution, with connection to the local District Energy Network. Further work would be undertaken to establish if this was the best option for the Council and its residents”. Work undertaken since that decision, confirmed that due to the nature of the scheme and policy requirements, the best option remained to connect to the Energetik network operating in LB Enfield. Further detail on this could be seen in para 5.1 and Section 6. Given the strong rationale to approach Energetik , officers had investigated the Procurement, Legal and Other issues and recommended a way forward based upon the overall context. The proposed Procurement Strategy was set out in this paper and required Cabinet Member approval based on CSO 2.01(b). The proposal was for a mixed procurement covering the connection and supply arrangements for both the housing and non-residential elements of the development. A mixed procurement means the procurement is for works/ services/ goods. It was also a mixed procurement made up of public contracts and utility contracts (the housing elements are utility contracts by virtue of the Procurement Act 2023 Schedule 4, Para 1a). Further detail on the mixed procurement approach and rationale is set out in the exempt report. The nature of the mixed procurement means this procurement was exempt from procurement regulations requiring competitive processes. The rule for mixed procurement (where it is not realistic to separate it out) is to apply the rules from the largest element of the procurement to the entire contract. The largest element of this mixed procurement was the utility services element. In reviewing the utility services parts of the contract and considering the exemptions in Schedule 2 of the Procurement Act ...
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet Member Signing

Recommendations

2 It is recommended that the Cabinet Member for Placemaking and Local Economy:

2.1Approves the commencement of a mixed procurement strategy (i.e. works, supply and services) and direct negotiations with the district heat network, Lee Valley Heat Network Operating Company Limited (company number: 09763702) concerning the connection, supply and potential management/ maintenance agreements for 40 years for the Selby Urban Village scheme. The potential agreements are as set down in Section 5.14 and 5.15.

Reasons for decision

3.1Cabinet approved the overall design concept and sustainability aims behind the Selby Urban Village Project on the 19 September 2023 Cabinet Report: ‘Contract award to KCA for design and architectural services for the Selby Urban Village masterplan’. Section 8, ‘Carbon and Climate Change’ of that report sets out that the energy strategy of the detailed Planning Applications would be developed in line with the energy policies of the London Plan, LBH and LBE, to achieve a zero-carbon target, and in accordance with the London Plan’s energy hierarchy. These policies and the project’s planning approvals require connecting to a District Energy Network.

3.2In the subsequent Cabinet Member Signing Report ‘Gateway 0 Report - Phase 2, Selby Urban Village, N17 – Bruce Castle Ward’ on 19 June 2024, para 8.12 notes “A communal heating system is the preferred solution, with connection to the local District Energy Network. Further work will be undertaken to establish if this is the best option for the Council and its residents”. Work undertaken since that decision, confirmed that due to the nature of the scheme and policy requirements, the best option remains to connect to the Energetik network operating in LB Enfield. Further detail on this can be seen in para 5.1 and Section 6.

3.3Given the strong rationale to approach Energetik, officers have investigated the Procurement, Legal and Other issues and are recommending a way forward based upon the overall context.

3.4The proposed Procurement Strategy is set out in this paper and requires Cabinet Member approval based on CSO 2.01(b).

3.5The proposal is for a mixed procurement covering the connection and supply arrangements for both the housing and non-residential elements of the development. A mixed procurement means the procurement is for works/ services/ goods. It is also a mixed procurement made up of public contracts and utility contracts (the housing elements are utility contracts by virtue of the Procurement Act 2023 Schedule 4, Para 1a). Further detail on the mixed procurement approach and rationale is set out in the exempt report.

3.6The nature of the mixed procurement means this procurement is exempt from procurement regulations requiring competitive processes. The rule for mixed procurement (where it is not realistic to separate it out) is to apply the rules from the largest element of the procurement to the entire contract. The largest element of this mixed procurement is the utility services element. In reviewing the utility services parts of the contract and considering the exemptions in Schedule 2 of the Procurement Act 2023, the utility contracts are covered by exemption 31.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Selby Urban Village: Procurement strategy for heat supply arrangementsMinutes 338 KB DownloadRead as text

At this meeting

Whole meeting
6Selby Urban Village - Procurement strategy for heat supply arrangementsThis decision
7Exclusion of the Press and PublicOn the agenda

Who was there

1 of 1 attended
RG
Councillor Ruth GordonCommittee Member, present

On this subject at Haringey

Search all
  1. Selby Urban Village - Procurement strategy for heat supply arrangementsThis decision
  2. Selby Urban Village - award of contracts for heat supply arrangementsNoted
  3. Selby Urban Village - approval to procure Artificial Grass Pitch works contractorDecided
  4. Award of contract for Employers Agent services for Phase 1 (Selby Centre + Sports Facilities) and Phase 2 (Housing of the Selby Urban Village ProjectApproved
  5. Gateway 0 Report - Phase 2, Selby Urban Village, N17 - Bruce Castle WardNoted
  6. Contract award to KCA for design and architectural services for the Selby Urban Village masterplanApproved

More from Haringey Cabinet Member Signing

All decisions
MeetingDecisionOutcome
2 Nov 2026 Deaf Outreach Services ContractDECLARATIONS FOR THIS ITEM: NONE Decided Open
28 Oct 2026 Administrative amendment to Merchant Acquirer Re-ProcurementRESOLVED 1. To note the administrative error in the original report referring to Global Pay and Global Payments; 2. T... Noted Open
20 Oct 2026 Approval of Additional Expenditure and Final Payment to Accora Limited reportDECLARATIONS FOR THIS ITEM: NONE RESOLVED The Cabinet Member for Adults and Health: 1. Approved the variation of cont... Approved Open
16 Oct 2026 Approve Funding from Arts Council England to Haringey Music Service for the North London Music HubDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open