Cabinet Member Signing, Thursday 19 March 2026 at 11.00am

Earlsmead Primary School - Condition Works - Permission to initiate tender action for a Construction Works Contract

Decided Executive 1 paper

AI summaryThe Cabinet Member for Children, Education and Families approved starting a tender for condition works at Earlsmead Primary School, with Phase 1 estimated at £2.975m and Phase 2 at £2.539m, funded from the General Fund capital programme.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedFor Phase 1 and 2 condition works at Earlsmead Primary School
Money£2.975m and £2.539mPhase 1 and Phase 2 estimated project costs
What happens nextFurther report for contract awardAfter tender exercise completed
Who it affectsEarlsmead Primary SchoolFour blocks across the school site in South Tottenham

What was decided

The Cabinet Member approved the commencement of a tendering process for construction works contractors to deliver Phase 1 and 2 condition works at Earlsmead Primary School, under Contract Standing Orders 0.08 and 2.01(b). Report 3.1, 3.2

A single-stage JCT traditional form of contract will be used, procured through the London Construction Programme Education Framework or DPS, with the two phases tendered separately. Report 4.5

Why

An estate-wide review of school condition and compliance identified significant concerns with the building, including health and safety risks and outdated mechanical, electrical and water systems, requiring the council to act to meet its statutory responsibilities. Report 4.1, 4.2, 4.3

The council has no in-house resource with the capacity, specialist expertise or qualifications to deliver these works. Report 5.3

Procurement through the LCP Education Framework or DPS is judged compliant with CSO 8.02, unlike an alternative public sector DPS, and avoids the protracted timescales of an open tender via Contracts Finder. Report 5.4, 5.5

What happens next

Soft market engagement is programmed for April 2026 to test interest and availability in the market.

Phase 1 tender activity is projected to commence in July 2026, with Phase 2 tender action scheduled for March 2027, reflecting available capital funding. Report 4.5, 6.5

Following the tender exercise, a further report will be prepared seeking approval to award the construction works contract to the successful bidder. Report 6.13

The money

  • £2.975m Estimated cost of Phase 1, including construction works, project management fees, contingency and disbursements, funded from the General Fund capital programme Report P50
  • £2.539m Estimated cost of Phase 2, including construction works, project management fees, contingency and disbursements, funded from the General Fund capital programme Report P50

Options considered

  • Chosen: Use the London Construction Programme Education Framework or DPS with a single-stage JCT traditional contract, in two phased tenders. Compliant with CSO 8.02 and deemed suitable for the requirements Report 4.5, 5.5
  • Rejected: Do nothing. Not sustainable, would risk compliance and health and safety standards and the council's statutory responsibilities Report 5.1
  • Rejected: Deliver in-house. No in-house resource with the capacity, specialist expertise or qualifications Report 5.3
  • Rejected: Invite open tenders via Contracts Finder. Would result in a protracted tender period and delay delivery Report 5.4
  • Rejected: Use an alternative public sector DPS. Would not be compliant with CSO 8.02, as the LCP Framework or DPS is suitable Report 5.5

Implications

  • Financial: Phase 1 is estimated at £2.975m and Phase 2 at £2.539m, both funded from the approved General Fund capital programme, with more accurate cash flows to follow once tenders are returned. Report P50, P51
  • Legal: The recommendation aligns with Contract Standing Orders 0.08 and 2.01(b); the Director of Legal and Governance sees no legal reasons preventing approval, and the works support the council's statutory responsibilities on school building standards. Report P59, P60, P61
  • Equalities: The Public Sector Equality Duty has been considered; no negative consequences are identified for those sharing protected characteristics, and the works are expected to have a wholly positive impact on health and safety. Report P67, P68
  • Climate: An Energy Audit will identify opportunities to reduce energy consumption and contribute to net zero in the schools' estate, potentially supporting a future Public Sector Decarbonisation Scheme funding bid. Report 6.6, 8.1, 8.2
  • Risk: Failure to act would risk the building's safety and integrity and could lead to more serious financial and operational implications, while phasing and decant accommodation arrangements are intended to minimise disruption to school activities. Report 5.1, 6.3
  • Other: The project contributes to the Corporate Delivery Plan 2024-2026, supporting the Borough Plan outcomes of best start in life for children and young people and strong communities. Report 7.1, 7.2, P42, P43

Who and where

  • Pupils, staff and visitors at Earlsmead Primary School Report 6.1, P68
  • The school community, including the nursery Report 6.1, 6.2, 6.10
  • Prospective construction works contractors in the education construction market

Timeline

  • 5th December 2024: Multi-disciplinary design team, including Quantity Surveying services, appointed under delegated authority to support Phases 1 and 2 Report 6.7
  • April 2026: Soft market engagement planned to ascertain interest and availability within the market
  • July 2026: Phase 1 procurement activity projected to commence Report 4.5
  • March 2027: Phase 2 works scheduled for tender action Report 4.5

Plain English for the jargon

  • CSO: Contract Standing Orders, the council's rules for procurement
  • LCP: London Construction Programme, a public sector construction framework
  • DPS: Dynamic Purchasing System, an electronic list of approved suppliers
  • JCT: Joint Contracts Tribunal, a standard form of building contract used in the UK
  • MDDT: Multi-Disciplinary Design Team, including Quantity Surveying services
  • RIBA: Royal Institute of British Architects, whose work stages define design progression
  • PSED: Public Sector Equality Duty under the Equalities Act 2010
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6

Resolved

DECLARATIONS OF INTEREST MADE FOR THIS ITEM: None
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet Member Signing

Recommendations

3.1For the Cabinet Member for Children, Education and families, pursuant to Contract Standing Orders 0.08 and 2.01(b) to:

3.2Approve the commencement of a tendering process for construction works contractors to deliver Phase 1 & 2 condition works at Earlsmead Primary School.

Reasons for decision

4.1An estate-wide review of school condition and compliance resulted in a business case and programme delivery plan submission to the September 2020 Capital Board for approval. A number of programme delivery options were presented for consideration, and approval was subsequently granted to proceed with the most urgent projects in advance of a final decision. This project was proposed, as it has been prioritised in the 2024-25 Children’s Capital Programme.

4.2Due to significant concerns to areas of the building’s condition, Earlsmead Primary School has been identified as requiring works to bring its building condition and services infrastructure up to standard.

4.3It is essential to engage a construction works contractor to undertake condition works required to address the health and safety concerns and priority condition issues that were identified within the feasibility report. 4.4 It is proposed to procure a contractor on a single-stage, JCT traditional form of contract using the London Construction Programme Education Framework or DPS. Soft market engagement is programmed to be undertaken in April 2026 to ascertain interest and availability within the market.

4.5As set out in 1.2 it is intended to develop the design and offer two separate tender opportunities to the market for the procurement of a construction works contractor. Phase 1 procurement activity is projected to commence in July 2026; Phase 2 works have been scheduled for tender action in March 2027. Works have been phased to reflect available capital funding.

Alternative options considered

5.1Do nothing: The council could decide not to tender the scheme. This may seem cost- effective in the short term, but it is not a sustainable solution as the school would not meet current compliance and health and safety standards. This approach risks the Council’s ability to fulfil its statutory responsibilities and potentially compromises the safety and integrity of the building, which could have more serious financial and operational implications in the future.

5.3In-house: There is currently no resource within the Council that has the capacity, specialist expertise or qualifications to deliver this service.

5.4Invite open tenders via Contracts Finder: This would result in a protracted tender period and would delay delivery of the project.

5.5Use an alternative public sector DPS: This would not be compliant with CSO 8.02, given the LCP Framework or DPS has been deemed suitable for the requirements being sought.

6. Background Information

6.1Earlsmead Primary School is located in the South Tottenham area with the proposed works impacting 4 blocks of accommodation, the main teaching blocks A & B, nursery block C and caretaker block D.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Earlsmead Primary School: Condition Works: Permission to initiate tender action for a Construction Works ContractMinutes 333 KB DownloadRead as text

More from Haringey Cabinet Member Signing

All decisions
MeetingDecisionOutcome
2 Nov 2026 Deaf Outreach Services ContractDECLARATIONS FOR THIS ITEM: NONE Decided Open
28 Oct 2026 Administrative amendment to Merchant Acquirer Re-ProcurementRESOLVED 1. To note the administrative error in the original report referring to Global Pay and Global Payments; 2. T... Noted Open
20 Oct 2026 Approval of Additional Expenditure and Final Payment to Accora Limited reportDECLARATIONS FOR THIS ITEM: NONE RESOLVED The Cabinet Member for Adults and Health: 1. Approved the variation of cont... Approved Open
16 Oct 2026 Approve Funding from Arts Council England to Haringey Music Service for the North London Music HubDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
13 Oct 2026 Filming at meetingsThe notice of filming at meetings was noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies