London Borough of Haringey
Cabinet Member Signing, Thursday 19 March 2026 at 11.00am

Mulberry Primary School - Condition Works - Permission to initiate tender action for a Construction Works Contract

Decided Executive 1 paper

AI summaryHaringey Cabinet Member for Children, Education and Families approved starting a tender for condition works at Mulberry Primary School, with Phase 1 estimated at £6.326m and Phase 2 at £2.291m.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedApproved commencement of tendering for construction works
Money£6.326m and £2.291mPhase 1 and Phase 2 estimated costs separately
What happens nextSoft market engagement April 2026Phase 1 procurement from July 2026
Who it affectsMulberry Primary SchoolFive blocks in Tottenham Hale area

What was decided

The Cabinet Member for Children, Education and Families approved the commencement of a tendering process for construction works contractors to deliver Phase 1 and Phase 2 condition works at Mulberry Primary School. Report 3.2

The contractor will be procured on a single-stage JCT traditional form of contract using the London Construction Programme Education Framework or DPS, with two separate tender opportunities offered for Phase 1 and Phase 2. Report 4.4, 4.5

The works have been phased to reflect available capital funding, with Phase 1 focusing on external fabric and mechanical and electrical upgrades, and Phase 2 on internal fabric repairs. Report 4.5, 6.5

Why

An estate-wide review identified significant condition and health and safety concerns at the school, which has been prioritised in the 2024 to 2025 Children's Capital Programme. Report 4.1, 4.2

A feasibility report and RIBA 1 study identified priority condition issues across roof, windows, fabric, heating, electrical, drainage and water systems, as well as fire safety and external grounds. Report 6.8, 6.9

What happens next

Soft market engagement is programmed for April 2026 to ascertain interest and availability within the market. Report 4.4

Phase 1 procurement is projected to commence in July 2026, with Phase 2 tender action scheduled for March 2027. Report 4.5

Upon completion of the tender exercise, a further report will be prepared to request award of the construction works contract to the successful bidder. Report 6.13

The money

  • £6.326m Phase 1 overall cost including estimated construction works, project management fees, contingency and disbursements Report P51
  • £2.291m Phase 2 cost including estimated construction works, project management fees, contingency and disbursements Report P51

Options considered

  • Chosen: Use London Construction Programme Education Framework or DPS. Deemed suitable for the requirements; compliant with Contract Standing Orders Report 4.4, 5.5, P56
  • Rejected: Do nothing. Not sustainable; school would not meet compliance and health and safety standards Report 5.1
  • Rejected: Deliver in-house. No council resource has the capacity, specialist expertise or qualifications to deliver the service Report 5.3
  • Rejected: Invite open tenders via Contracts Finder. Would result in a protracted tender period and delay project delivery Report 5.4
  • Rejected: Use an alternative public sector DPS. Would not be compliant with CSO 8.02 given the LCP Framework or DPS has been deemed suitable Report 5.5

Implications

  • Financial: Phase 1 estimated at £6.326m and Phase 2 at £2.291m, both funded from the approved General Fund capital programme; more accurate cash flows will follow tender returns. Report P51, P52
  • Legal: The recommendation is in line with Contract Standing Orders 0.08 and 2.01(b) and the Director of Legal and Governance sees no legal reasons preventing approval. Report 3.1, P59, P60, P61
  • Equalities: The Public Sector Equality Duty has been considered and the works are expected to have a wholly positive impact, with no negative consequences identified for protected characteristic groups. Report P63, P67, P68
  • Climate: An Energy Audit will identify opportunities to reduce energy consumption and contribute towards net zero, and may inform a future Public Sector Decarbonisation Scheme funding bid; the appointed contractor must meet DM21 sustainable design requirements. Report 6.6, 8.1, 8.2
  • Risk: Not addressing the works would risk the council's ability to fulfil statutory responsibilities and could compromise building safety and integrity, with potentially more serious financial and operational implications. Report 5.1

Who and where

  • Pupils and staff at Mulberry Primary School in Tottenham Hale Report 6.1, 6.3
  • Visitors to the school Report P68
  • The council's schools estate more widely, through the corporate delivery plan alignment Report 7.1, 7.2

Timeline

  • September 2020: Estate-wide review business case and programme delivery plan submitted to Capital Board for approval Report 4.1
  • 5th December 2024: Multi-disciplinary design team and Quantity Surveyor appointment approved under delegated authority Report 6.7
  • April 2026: Soft market engagement programmed Report 4.4
  • July 2026: Phase 1 procurement projected to commence Report 4.5
  • March 2027: Phase 2 tender action scheduled Report 4.5

Plain English for the jargon

  • JCT: Joint Contracts Tribunal, a standard form of building contract used in the UK
  • DPS: Dynamic Purchasing System, a public sector procurement route
  • LCP: London Construction Programme, a public sector construction framework
  • CSO: Contract Standing Orders, the council's procurement rules
  • MDDT: Multi-Disciplinary Design Team, including Quantity Surveying services
  • RIBA: Royal Institute of British Architects, used here to describe the work stages of the feasibility study
  • PSED: Public Sector Equality Duty under the Equality Act 2010
  • DM21: Policy in the Haringey Development Management Plan Document on Sustainable Design, Layout and Construction
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7

Resolved

DECLARATIONS OF INTEREST MADE FOR THIS ITEM: None
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet Member Signing

Recommendations

3.1For the Cabinet Member for Children, Education and families, pursuant to Contract Standing Orders 0.08 and 2.01(b) to:

3.2Approve the commencement of a tendering process for construction works contractors to deliver Phase 1 & 2 condition works at Mulberry Primary School.

Reasons for decision

4.1An estate-wide review of school condition and compliance resulted in a business case and programme delivery plan submission to the September 2020 Capital Board for approval. A number of programme delivery options were presented for consideration, and approval was subsequently granted to proceed with the most urgent projects in advance of a final decision. This project was proposed, as it has been prioritised in the 2024-25 Children’s Capital Programme.

4.2Due to significant concerns to areas of the building’s condition, Mulberry Primary School has been identified as requiring works to bring its building condition and services infrastructure up to standard. 4.3 It is essential to engage a construction works contractor to undertake condition works required to address the health and safety concerns and priority condition issues that were identified within the feasibility report.

4.4It is proposed to procure a contractor on a single-stage, JCT traditional form of contract using the London Construction Programme Education Framework or DPS. Soft market engagement is programmed to be undertaken in April 2026 to ascertain interest and availability within the market.

4.5As set out in 1.2 it is intended to develop the design and offer two separate tender opportunities to the market for the procurement of a construction works contractor. Phase 1 procurement activity is projected to commence in July 2026, Phase 2 works have been scheduled for tender action in March 2027. Works have been phased to reflect available capital funding.

Alternative options considered

5.1Do nothing: The council could decide not to tender the scheme. This may seem cost- effective in the short term, but it is not a sustainable solution as the school would not meet current compliance and health and safety standards. This approach risks the Council’s ability to fulfil its statutory responsibilities and potentially compromises the safety and integrity of the building, which could have more serious financial and operational implications in the future.

5.3In-house: There is currently no resource within the Council that has the capacity, specialist expertise or qualifications to deliver this service.

5.4Invite open tenders via Contracts Finder: This would result in a protracted tender period and would delay delivery of the project.

5.5Use an alternative public sector DPS: This would not be compliant with CSO 8.02, given the LCP Framework or DPS has been deemed suitable for the requirements being sought.

6. Background Information

6.1Mulberry Primary School is located in the Tottenham Hale area with the proposed works impacting 5 blocks of accommodation, the main teaching blocks A B & C, gym block D and nursery block E.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Mulberry Primary School: Condition Works: Permission to initiate tender action for a Construction Works ContractMinutes 262 KB DownloadRead as text

More from Haringey Cabinet Member Signing

All decisions
MeetingDecisionOutcome
2 Nov 2026 Deaf Outreach Services ContractDECLARATIONS FOR THIS ITEM: NONE Decided Open
28 Oct 2026 Administrative amendment to Merchant Acquirer Re-ProcurementRESOLVED 1. To note the administrative error in the original report referring to Global Pay and Global Payments; 2. T... Noted Open
20 Oct 2026 Approval of Additional Expenditure and Final Payment to Accora Limited reportDECLARATIONS FOR THIS ITEM: NONE RESOLVED The Cabinet Member for Adults and Health: 1. Approved the variation of cont... Approved Open
16 Oct 2026 Approve Funding from Arts Council England to Haringey Music Service for the North London Music HubDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
13 Oct 2026 Filming at meetingsThe notice of filming at meetings was noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies