Crowland Primary School - Condition Works - Permission to initiate tender action for a Construction Works Contract

Decided Executive 1 paper

AI summaryHaringey Cabinet Member for Children, Education and Families approved starting a tender for a construction contractor to deliver condition works at Crowland Primary School in South Tottenham, covering fire safety, roofs, heating, electrical and water systems. Project costs are kept in an exempt appendix.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedTo appoint a construction works contractor
MoneyExemptTotal project costs in Part B exempt appendix
What happens nextTender exerciseFollowed by a further report to award the contract
Who it affectsCrowland Primary SchoolSouth Tottenham, five blocks on site

What was decided

Approve the commencement of a tendering process for a construction works contractor to deliver condition works at Crowland Primary School, under Contract Standing Orders 0.08 and 2.01(b). Report 3.1, 3.2

Why

A feasibility study found significant building condition concerns at the school, including fire safety, roofing, windows, heating, electrical, and water systems, that need addressing to meet health, safety and compliance standards. Report 4.2, 4.3, 6.8, 6.9

The project sits in the 2024-25 Children's Capital Programme after an estate-wide review of school condition and compliance was approved by the September 2020 Capital Board. Report 4.1

What happens next

Run a single-stage JCT traditional tender through the London Construction Programme Education Framework or DPS, with soft market engagement to test interest and availability. Report 4.4

Bring a further report back to award the construction works contract to the successful bidder. Report 6.13

Consult planning and building control authorities on regulatory compliance as the project develops. Report 6.11

The money

  • approx. 20.99 tCO2pa Estimated annual carbon reduction from energy efficient measures Report 8.2
  • £500,000 Threshold above which contracts require Cabinet approval under CSO 2.01(b) Report P49, P50

Options considered

  • Chosen: Procure via London Construction Programme Education Framework or DPS, single-stage JCT traditional contract. Compliant with Procurement Act 2023 and CSO 7.02, suitable for the works required Report 4.4, P50
  • Rejected: Do nothing. Would leave the school below current compliance and health and safety standards and risk the Council's statutory duties Report 5.1
  • Rejected: Deliver in-house. No internal resource with the capacity, specialist expertise or qualifications to deliver the work Report 5.3
  • Rejected: Invite open tenders via Contracts Finder. Would lead to a protracted tender period and delay project delivery Report 5.4
  • Rejected: Use an alternative public sector DPS. Would not be compliant with CSO 8.02 given the LCP Framework or DPS is suitable Report 5.5

Implications

  • Legal: Cabinet Member can take a Cabinet-level decision with the Leader's prior agreement under CSO 0.08; no legal reasons prevent approval. Report P51, P52
  • Equalities: Public Sector Equality Duty considered; the works are judged to have a wholly positive impact on health and safety with no negative consequences for protected groups. Report P54, P58, P59
  • Climate: Project is expected to deliver around 20.99 tCO2pa carbon reduction through energy efficient measures and should meet DM21 sustainable design requirements. Report 8.1, 8.2
  • Financial: Estimated total projected costs are recorded in Appendix 1 - Exempt Part B and are not in the public part of the report. Report 6.14, P42
  • Risk: Failure to act would risk the Council's statutory duties and could compromise building safety, with more serious financial and operational implications later. Report 5.1

Who and where

  • Pupils, staff and visitors at Crowland Primary School Report 6.1, P59
  • The wider South Tottenham community served by the school Report 6.1
  • Haringey Council as the responsible body for school estate condition and compliance Report 4.2, 5.1

Timeline

  • September 2020: Capital Board approved the most urgent condition projects after an estate-wide review Report 4.1
  • 2006: Upper floor and roof of Block A were re-constructed after a fire Report 6.2
  • 23rd December 2024: Multi-disciplinary design team appointment approved under delegated authority Report 6.7
  • 2024-25: Project included in the Children's Capital Programme Report 4.1
  • 2026-03-19: Cabinet Member approved commencement of the construction works tender Report 3.2
  • After tender: Further report to be prepared seeking award of the construction works contract Report 6.13

Plain English for the jargon

  • JCT: Joint Contracts Tribunal, a standard form of building contract used in UK construction
  • DPS: Dynamic Purchasing System, a list of pre-qualified suppliers that buyers can use to procure works, goods or services
  • LCP: London Construction Programme, a public sector framework used for education construction works
  • MDDT: Multi-Disciplinary Design Team, including Quantity Surveying services
  • RIBA 1: Royal Institute of British Architects work stage 1, the feasibility/strategic definition stage
  • CSO: Contract Standing Orders, the Council's rules for procuring contracts
  • DM21: Haringey Development Management policy on Sustainable Design, Layout and Construction
  • tCO2pa: Tonnes of carbon dioxide equivalent per annum, a unit of greenhouse gas emissions
  • PSED: Public Sector Equality Duty under the Equalities Act 2010
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8

Resolved

DECLARATIONS OF INTEREST MADE FOR THIS ITEM: None
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet Member Signing

Recommendations

3.1For the Cabinet Member for Children, Education and families, pursuant to Contract Standing Orders 0.08 and 2.01(b) to:

3.2Approve the commencement of a tendering process for a construction works contractor to deliver condition works at Crowland Primary School.

Reasons for decision

4.1An estate-wide review of school condition and compliance resulted in a business case and programme delivery plan submission to the September 2020 Capital Board for approval. A number of programme delivery options were presented for consideration and approval was subsequently granted to proceed with the most urgent projects in advance of a final decision. This project was proposed, as it has been prioritised in the 2024-25 Children’s Capital Programme.

4.2Due to significant concerns to areas of the building’s condition, including fire safety and compliance, Crowlands Primary School have been identified as requiring works to bring its building condition and services infrastructure up to standard.

4.3It is essential to engage a construction works contractor to undertake condition works required to address the health and safety concerns and priority condition issues that were identified within the feasibility report.

4.4It is proposed to procure a contractor on a single-stage, JCT traditional form of contract using the London Construction Programme Education Framework or DPS. Soft market engagement will be undertaken to ascertain interest and availability within the market. 5. Alternative Options Considered

5.1Do nothing: The council could decide not to tender the scheme. This may seem cost- effective in the short term, but it is not a sustainable solution as the school would not meet current compliance and health and safety standards. This approach risks the Council’s ability to fulfil its statutory responsibilities and potentially compromises the safety and integrity of the building, which could have more serious financial and operational implications in the future.

5.3In-house: There is currently no resource within the Council that has the capacity, specialist expertise or qualifications to deliver this service.

5.4Invite open tenders via Contracts Finder: This would result in a protracted tender period and would delay delivery of the project.

5.5Use an alternative public sector DPS: This would not be compliant with CSO 8.02, given the LCP Framework or DPS has been deemed suitable for the requirements being sought.

6. Background Information

6.1Crowland Primary School is located in the South Tottenham area and is made up of five blocks comprising three main teaching buildings, Blocks A, B and E; a building which houses the caretaker, Block C; and a building providing swimming pool facilities, Block D.

6.2Blocks A, B, C and E are assumed to be early 20th century traditional construction, whilst the swimming pool block and Block D, a late 20th century addition to the site. The upper floor and roof of Block A was re-constructed due to a fire in the school in 2006.

6.3The condition works expected to be addressed are listed as below:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Crowland Primary School: Condition Works: Permission to initiate tender action for a Construction Works ContractMinutes 269 KB DownloadRead as text

More from Haringey Cabinet Member Signing

All decisions
MeetingDecisionOutcome
2 Nov 2026 Deaf Outreach Services ContractDECLARATIONS FOR THIS ITEM: NONE Decided Open
28 Oct 2026 Administrative amendment to Merchant Acquirer Re-ProcurementRESOLVED 1. To note the administrative error in the original report referring to Global Pay and Global Payments; 2. T... Noted Open
20 Oct 2026 Approval of Additional Expenditure and Final Payment to Accora Limited reportDECLARATIONS FOR THIS ITEM: NONE RESOLVED The Cabinet Member for Adults and Health: 1. Approved the variation of cont... Approved Open
16 Oct 2026 Approve Funding from Arts Council England to Haringey Music Service for the North London Music HubDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
13 Oct 2026 Filming at meetingsThe notice of filming at meetings was noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies