London Borough of Haringey
Cabinet, Tuesday 14 July 2026 at 6.30pm

All Void works Procurement

Decided Executive 1 paper

AI summaryHaringey Cabinet approves procurement of a multi-service call-off contract for void property works across its housing portfolio, with up to four contractors on an initial five year term.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedMulti-service call-off, up to four contractors, 5+1+1 years
MoneyNot stated in non-exempt papersContract values and ceilings are in Exempt Appendix A
What happens nextFurther Cabinet reports for awardAfter compliant procurement, evaluation and financial checks
Who it affectsCouncil tenants and housing applicantsExisting and prospective social housing residents across all tenures

What was decided

Cabinet approved the procurement of a multi-service call-off contract for void refurbishment, compliance and remediation works across the housing portfolio, for an initial five year term with options to extend by up to two further one year periods (5+1+1). Report 3.1

Cabinet noted that a future report will be brought back seeking approval to award the contracts, including contract values, affordability within approved budgets, and financial implications for the Housing Revenue Account and General Fund. Report 3.2

Why

The council has a backlog of about 500 empty homes and significant ongoing demand for void works, and prolonged voids lose rental income and increase costs such as security, utilities and council tax on empty properties. Report 4.1, 6.1, 6.4

Current delivery relies on in-house teams and several separate contractor arrangements, which has produced fragmented commissioning, inconsistent performance management, differing specifications and prices, and limited visibility of overall demand. Report 6.5, 6.6

A call-off model with up to four contractors will add capacity, standardise delivery and reporting, strengthen commercial oversight, and let the council scale work up or down in response to fluctuating demand, with no minimum spend guaranteed. Report 4.4, 6.9, 6.23

What happens next

Run a compliant procurement under Contract Standing Orders 7.02 or 8.01, evaluating tenders on quality and price to identify the Most Advantageous Tender. Report 6.12, P57, P62

Use a Joint Contracts Tribunal Measured Term Contract, with prices set as a percentage uplift or discount against the National Housing Federation Schedule of Rates. Report 6.21, 6.22

Haringey Repairs Service will lead contract management, with monthly performance reviews, quarterly stakeholder review meetings, and KPIs reported to the Housing Board, the Housing, Planning and Development Scrutiny Panel, and the Resident Voice Board. Report 6.27, 6.28, 6.31, 6.32

The money

  • £570 million Asset Management Strategy investment in Council homes over ten years Report 6.15
  • £500,000 Cabinet approval threshold for starting a procurement under CSO 2.01(b) Report P61
  • approximately 500 Empty homes currently in the refurbishment, compliance or remediation backlog Report 6.1
  • approximately 301 Empty homes delivered through outsourced arrangements in 2025/26 Report 6.4
  • 250 properties per year Average voids delivered by Haringey Repairs Service in-house workforce Report 6.4

Options considered

  • Chosen: Procure a multi-service call-off contract with up to four contractors on a 5+1+1 year term. Adds flexible capacity, standardises delivery, strengthens oversight, and supports faster re-letting without a minimum spend commitment. Report 3.1, 4.4, 6.9
  • Rejected: Do nothing and keep the current fragmented mix of in-house and separate contractor arrangements. Would keep commissioning fragmented, lengthen void turnaround, lose rental income, and add holding costs. Report 5.1
  • Rejected: Run a series of short-term procurement arrangements. Would still be fragmented, raise administrative costs, and limit long-term planning and consistent standards. Report 5.2
  • Rejected: Bring all void refurbishment, compliance and remediation works in-house. Demand is too variable, requiring a much larger permanent workforce, so the model would be less flexible and offer poorer value for money than a hybrid approach.

Implications

  • Financial: No new capital or revenue budget is approved by this decision; any spend will be met from existing approved service budgets and call-off orders, with no minimum spend guaranteed. Report 6.23, 6.25
  • Financial: Where works meet the council's capitalisation criteria, costs will be treated as capital in line with the Capital Strategy, Financial Regulations and Housing Revenue Account rules. Report 6.17
  • Legal: The Director of Legal and Governance raises no legal reasons preventing approval, and procurement will be carried out under CSO 7.02 (Framework) or CSO 8.01 (Dynamic Purchasing System), with an alternative route only with Chief Procurement Officer approval. Report P57, P60, P61, P62, P63
  • Equalities: Faster re-letting of voids is expected to benefit groups disproportionately represented in social housing, the housing waiting list and Temporary Accommodation, including Black residents, disabled people, women, larger families, and residents on lower incomes. Report P68, P70, P71
  • Risk: Identified risks include inaccurate demand forecasting, cost pressure from fluctuating volumes, contractor underperformance, and mobilisation risks for the new cross-service model, to be managed through KPIs, call-off payments, and regular monitoring. Report 6.36
  • Staffing: Day-to-day delivery stays with individual commissioning services, while Haringey Repairs Service leads central contract management; the in-house voids service is retained and supplemented by external capacity. Report 6.27, 6.29
  • Climate: Standardised specifications can embed energy efficiency measures, while aggregated scheduling and bulk purchasing are expected to reduce travel and emissions; compliance works will also support adaptation to extreme weather. Report 8.1, 8.3

Who and where

  • Existing council tenants across general needs, sheltered housing, hostels, lodges and temporary accommodation Report 4.1, 6.4
  • Prospective tenants on the housing register, in Temporary Accommodation, and in homelessness and transfer pathways Report P70
  • Residents of Home for Haringey Private Sector Leasing, Council Private Sector Leasing and Housing Choice Based Scheme properties Report 6.4
  • Haringey Repairs Service in-house operatives and management Report 6.4, 6.27
  • Existing external void works contractors Report 6.4
  • Resident Voice Board, which will be consulted on the procurement and re-let standards Report 6.32, 6.35

Timeline

  • 2025/26: About 301 empty homes delivered through outsourced arrangements across the housing portfolio Report 6.4
  • By March 2028: Asset Management Strategy target for all council homes to meet the Decent Homes Standard Report 6.15
  • Next ten years: Asset Management Strategy commits £570 million of investment in council homes Report 6.15
  • Initial five year term with up to two further one year extensions (5+1+1): Proposed length of the multi-service call-off contract Report 3.1, P69
  • Following procurement: Further Cabinet reports will be presented to award the contracts Report 3.2

Plain English for the jargon

  • Void property: A council home that is empty between tenancies and needs works before it can be re-let.
  • Call-off contract: A contract that sets prices and terms so the council can order individual jobs as needed, with no minimum spend guaranteed.
  • JCT Measured Term Contract (MTC): A standard construction contract used to procure packages of work on an as-needed basis over a set period, valued against agreed rates.
  • NHF Schedule of Rates: An industry-standard pricing framework for housing maintenance and refurbishment works, used here with contractor percentage uplifts or discounts.
  • Housing Revenue Account (HRA): The ringfenced account that holds income and spending on council housing.
  • Decent Homes Standard: A government standard setting minimum requirements for housing condition, which the council aims to meet across all homes by March 2028.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item11

Resolved

DECLARATIONS OF INTEREST MADE FOR THIS ITEM: None
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet

Recommendations

It is recommended that Cabinet:

3.1Approves the procurement of a multi-service call-off contract to support the delivery of void (empty property) refurbishment, compliance, and remediation works across the Council’s housing portfolio, as outlined in Section 1, for an initial five-year term with options to extend by up to two further one-year periods (5+1+1).

3.2Notes that Cabinet reports will be presented seeking approval to award the contracts following completion of a compliant procurement process and evaluation of tenders received detailing the outcome of the procurement, the recommended contractors, contract values, affordability within approved budgets, and any associated financial implications for the Housing Revenue Account and General Fund.

Reasons for decision

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
All Void works ProcurementMinutes 446 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 19 attended
TE
Taryn EvesCouncil Staff, expected
AD
Andy DonaldOfficer, expected
FA
Fiona AldermanCouncil Staff, expected
AG
Ann GrahamOfficer, expected
BF
Barry FrancisCouncil Staff, expected
JC
Jess CroweOfficer, expected
AS
Ayshe SimsekSecretary, expected
SB
Stephen Bramah-CalvertOfficer, expected
CM
Claire McCarthySecretary, expected
MB
Councillor Mark BlakeChair, present
TH
Councillor Tammy HymasVice-Chair, present
GI
Councillor Gio IozziCommittee Member, present

All 19 on the meeting page

More from Haringey Cabinet

All decisions
MeetingDecisionOutcome
10 Nov 2026 Corporate Delivery Plan 2026-2028DECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Draft 2027-28 Budget and 2027-2032 Medium Term Financial Strategy ReportDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Regulation 19 consultation on Proposed Submission version of Haringey Local Plan 2027-2042 and submission to Secretary of StateDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Admission to Schools - Proposed Admission Arrangements for 2028/29DECLARATIONS OF INTEREST FOR THIS ITEM: None Decided Open
10 Nov 2026 Approval to extend current Highways and Street Lighting Contracts and approval of the procurement strategy for a future combined Highways and Street Lighting ContractDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies