London Borough of Haringey
Cabinet, Tuesday 14 July 2026 at 6.30pm

Report for approval of the contract for Phase 1(a) of the High Road West Scheme, demolition of 2-32 Whitehall Street, and the management plan for the Love Lane estate.

Decided Executive 5 papers

AI summaryHaringey Cabinet approves contract for 61 new council homes at High Road West Phase 1A, demolition of 2-32 Whitehall Street, and £1.1m Love Lane Estate Management Plan.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedContract, land appropriation, demolition, and management plan
Money£1.1mLove Lane Estate Management Plan budget
What happens nextSite possession July 2026Demolition starts August 2026, completion February 2028
Who it affectsLove Lane Estate residentsRehousing and safety during phased works

What was decided

Cabinet approves the appointment of Contractor A, identified in the exempt part of the report, to demolish Whitehall Lodge and 2-32 Whitehall Street and build 61 new council homes at High Road West Phase 1A. Report 3.1

Cabinet approves appropriation of the Phase 1A site for planning purposes under Section 122 of the Local Government Act 1972, and use of Section 203 of the Housing and Planning Act 2016 to override third-party rights, with later re-appropriation for housing under Section 19 of the Housing Act 1985. Report 3.2, 3.3, 3.4, 3.5

Cabinet approves the Love Lane Estate Management Plan, a £1.1m budget, and delegated authority to commence procurement for site security, decommissioning and demolition of Ermine, Charles and Moselle blocks. Report 3.10, 3.11, 3.13

Why

The recommendations will deliver 61 affordable council homes on council-owned land and allow rehousing of over half of existing Love Lane Estate residents into new permanent homes, in line with the Love Lane Landlord Offer approved by a resident ballot. Report 4.1, 6.16

A hybrid planning application for High Road West was granted in October 2021, with the site now ready to progress to construction, making this the final member decision required for Phase 1A. Report 4.2

The Love Lane Estate has a mix of occupied and vacant homes because of phased rehousing, which has already led to anti-social behaviour, squatting and criminal activity, so a proactive management plan is needed to safeguard remaining residents. Report 4.4, 6.7, 6.8

What happens next

Contract signing and site possession by July 2026, demolition starting on site in August 2026, main works commencing October 2026 and practical completion expected in February 2028, on a 77 week programme. Report 6.19, 6.27

Council will issue a letter of intent for up to 10% of the contract value pending formal contract execution, and a community update letter with in-person engagement is planned for July 2026. Report 3.9, 6.18

Procurement exercises will be commenced for site security, decommissioning and demolition of the Ermine, Charles and Moselle blocks once residents are rehoused and the blocks are fully vacated. Report 3.11, 3.12, 6.38

The money

  • £1.1m Total budget for the Love Lane Estate Management Plan Report 3.13
  • up to 10% of the contract value Letter of intent pending formal contract Report 3.9
  • £500,000 Threshold above which Cabinet or Cabinet Member approval is required for contract award Report 3.12, 9.3, 9.6

Options considered

  • Rejected: Do not develop the site for housing. Does not support the Council's commitment to deliver much needed affordable homes Report 5.1
  • Rejected: Do not appropriate the land for housing purposes upon completion. Could prevent the Council from offering the new homes for occupation Report 5.2
  • Rejected: Retain Whitehall Lodge as temporary accommodation. Land is needed for Phase 1A, building is not fit for purpose, and the partially demolished site is experiencing significant anti-social behaviour Report 5.3
  • Rejected: Do not implement the Love Lane Estate Management Plan or delegated authority for associated procurements. Would undermine ability to safeguard resident wellbeing, secure vacant homes, control anti-social behaviour and manage costs Report 5.4
  • Rejected: Leave 2-32 Whitehall Street in place behind hoarding or bring it back into use as housing. Anti-social behaviour risk, poor environment, no community benefit, and bringing it back into use would not be cost-effective for its remaining lifespan Report 5.5

Implications

  • Financial: Phase 1A new build is in the approved Housing Capital Programme and will be funded by Greater London Authority grant and HRA borrowing; the Love Lane management plan costs are not in the current Housing capital programme but can be contained within HRA capital and revenue budgets. Report 9.22, 9.23, 9.24
  • Legal: Use of Section 203 Housing and Planning Act 2016 powers to override third-party rights is justified given the public benefits of Phase 1A, but any interference with third-party rights will give rise to a right to compensation payable by the Council. Report 3.4, 3.6, 6.31
  • Equalities: The decision is expected to positively advance the public sector equality duty, particularly benefiting people in severe housing need, families needing 3-bed homes, and groups over-represented in temporary accommodation including women, young people, lower socio-economic groups and BAME people. Report 9.29, 9.31, 9.32
  • Climate: The development is designed to a 70% improvement over the 2021 building regulations baseline, with passive design, energy efficient equipment, renewable energy, living roofs with solar PV, low water usage and biodiversity net gain features. Report 8.1, 8.2, 8.5
  • Risk: Building Safety Regulator duties apply to the high-rise blocks, and a proactive management plan is needed to mitigate health and safety risks, anti-social behaviour, squatting and criminal activity on the partly vacant estate. Report 6.7, 6.35, 6.36
  • Staffing: The wider High Road West Scheme is forecast to create 1,214 construction jobs and 1,202 construction supply chain jobs. Report 6.2

Who and where

  • Existing residents of the Love Lane Estate, with over half to be rehoused into new permanent homes Report 4.1, 6.16
  • Residents of the Headcorn and Tenterden Estate neighbouring Phase 1A Report 6.17
  • Households currently in Whitehall Lodge emergency temporary accommodation, which will be vacated before demolition Report 6.10, 6.28
  • People on the housing register, including families needing 3-bed homes and people in temporary accommodation Report 9.29
  • Future tenants of the 61 new council homes to be built on Phase 1A Report 3.1, 4.1
  • Leaseholder of 2-32 Whitehall Street whose interest will vest in the Council under the confirmed CPO Report 4.5
  • Wider community around the Love Lane Estate who may benefit from temporary public spaces created after demolition of larger blocks Report 3.14, 6.38

Timeline

  • 2014: Start of High Road West Masterplan consultation stages Report 6.15
  • 2018 to 2021: Four rounds of consultation on the hybrid planning application including detailed proposals for Phase 1A Report 6.15
  • July 2021: Cabinet agreed the High Road West Local Lettings Policy Report 6.3
  • August and September 2021: Resident ballot on the Love Lane Estate regeneration: 55.7% of participating residents voted in favour Report 6.16
  • October 2021: Hybrid planning application for High Road West granted, reference HGY/2021/3175 Report 4.2
  • August 2022: Outline planning permission for High Road West granted, reference HGY/2021/3175 (as cited in carbon section) Report 8.6
  • November 2022: Cabinet agreed to make the High Road West Phase A Compulsory Purchase Order 2022 Report 6.4
  • July 2023: Non-Material Amendment application approved, reference HGY/2022/3937 Report 4.2
  • 20 March 2024: Confirmed Compulsory Purchase Order publicised by press notice; powers must be used within three years, that is by 20 March 2027 Report 6.4
  • December 2025: Council and Lendlease agreed to remove Phase 1A from the Development Agreement so the Council can direct deliver it Report 6.5
  • July 2026: Planned contract signing, site possession and community update engagement following Cabinet decision Report 6.18, 6.27
  • August 2026: Demolition works planned to start on site Report 6.27
  • October 2026: Main works planned to commence Report 6.27
  • 20 March 2027: Deadline by which Compulsory Purchase Order powers must be used Report 6.4
  • February 2028: Practical completion of Phase 1A new build expected Report 6.27
  • 2028: Earliest anticipated date for Phase 1B land to be leased to Lendlease for delivery Report 4.5

Plain English for the jargon

  • Development Agreement (DA): Agreement between the Council and Lendlease under which the High Road West Scheme is delivered through a phased approach
  • Compulsory Purchase Order (CPO): Legal order used by the Council to acquire land, interests and new rights needed to deliver the Scheme
  • CPOIA: Compulsory Purchase Order Indemnity Agreement under which Lendlease indemnifies the Council for CPO costs
  • HRA: Housing Revenue Account, the ringfenced account that holds income and spending on council housing
  • General Fund: The Council's main fund for non-housing revenue services, holding around 82% of the Phase 1A site
  • LCP DPS: LHC Construction Delivery Partner Dynamic Purchasing System framework used to procure the contractor
  • RIBA Plan of Work 2020: Royal Institute of British Architects' framework setting out design stages; the scheme has been designed to Stage 4
  • JCT Design and Build Contract: Standard form of construction contract where the contractor completes the design and build, used here as a single stage tender
  • Section 122 LGA 1972: Power for a principal council to appropriate land it owns that is no longer needed for its current purpose
  • Section 203 Housing and Planning Act 2016: Power that allows the Council to override third-party rights and easements on land appropriated for planning purposes once planning consent is in place
  • Landlord Offer: Document setting out commitments to Love Lane Estate residents, on which the 2021 resident ballot was held
  • GLA: Greater London Authority, which is providing grant funding towards Phase 1A
  • Building Safety Regulator: Regulator with duties applying to higher-risk residential buildings such as the Love Lane high-rise blocks
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12

Resolved

DECLARATIONS OF INTEREST MADE FOR THIS ITEM: None
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet

Report for: Cabinet - 14 July 2026

Item number: 12

Title: High Road West: Approval of the contract for Phase 1A of the High Road West Scheme, demolition of 2-32 Whitehall Street, and the Estate Management Plan for the Love Lane Estate (Public)

Report Authorised by: Jess Crowe, Corporate Director of Culture, Strategy and Communities

Lead Officer: Abigail Stratford, Director of Placemaking and Community Development

Ward(s) affected: Bruce Castle

Report for Key/ Non Key Decision: Key Decision

1. Describe the issue under consideration

1.1In 2017, following a competitive procurement process, the Council entered into a Development Agreement (“DA”) with Lendlease to deliver the High Road West Scheme (“the Scheme”) in north Tottenham. In recent years the Scheme has progressed through a number of milestones, including the grant of a hybrid planning application for the site, a positive resident ballot on the Love Lane Estate, and confirmation of a compulsory purchase order for Phase A of the Scheme.

1.2Delivery is currently stalled, due to difficult market conditions which have impacted the viability of the scheme. The Council is working with Lendlease to explore ways to find a viable route to unlock delivery. The Council's priority throughout this process has been to build new Council homes for Love Lane Estate residents as quickly as possible and ensure the Estate is effectively and safely managed prior to redevelopment. This report will therefore consider the following:

 Approval of the contract for Phase 1A of the High Road West Scheme. A plan of Phase 1A is at Appendix 1 (“Phase 1A”)  Approval of the contract for the demolition of 2-32 Whitehall Street for the reasons set out in this report. A plan of 2-32 Whitehall Street is at Appendix 2  Approval and implementation of the Love Lane Estate Management Plan and associated costs

1.3In December 2025, the Council and Lendlease agreed to remove Phase 1A from the DA and in turn enabled the Council to directly deliver the site, which comprises the first 61 council homes within the Scheme, as part of its council house-building programme.

1.4On 10th February 2026, Cabinet approved the procurement exercise for the selection of a main contractor to deliver the proposed development on the Council owned site on the land at High Road West, Phase 1A, and the demolition of Whitehall Lodge and 2- 32 Whitehall Street in line with Contract Standing Order (CSO) 2.01 (b). Following a formal tender process, this report now seeks permission to proceed with the appointment of a main contractor to allow the construction of the project, in line with Contract Standing Order (CSO) 2.01 (c) and 0.08.

1.5The Cabinet is asked to approve the appointment of the recommended contractor, identified in the exempt part of the report, to demolish Whitehall Lodge and construct the new build development of 61 Council homes at Phase 1A. The construction of the new homes will comprise 20 x one-bed two-person flats, 4 x two-bed four-person M4(3) ‘wheelchair’ flats, 10 x two-bed four-person flats, 19 x three-bed five-person family flats, 4 x three-bed five-person family maisonettes and 4 x four-bed six-person family maisonettes on Council-owned land at 100 Whitehall Street, Tottenham, N17 8BP. The location of the proposed new homes is shown in the ‘Proposed Phase 1A Site Plan’ included in Appendix 3. All 61 new council homes will be let at Social Rent.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Land Ownership Site PlanAppendix 1 1.5 MB Download
PDF
2-32_Whitehall_Street_Site_PlanAppendix 2 127 KB Download
PDF
Site Plan, Floorplans and 3D Impressions-High Road West Phase 1A_25-12-16Appendix 3 2.5 MB Download
PDF
Love Lane Management PlanAppendix 6 250 KB Download
PDF
Report for approval of the contract for Phase 1(a) of the High Road West Scheme, demolition of 2-32 Whitehall Street, and the management plan for the Love Lane estate.Minutes 472 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 19 attended
TE
Taryn EvesCouncil Staff, expected
AD
Andy DonaldOfficer, expected
FA
Fiona AldermanCouncil Staff, expected
AG
Ann GrahamOfficer, expected
BF
Barry FrancisCouncil Staff, expected
JC
Jess CroweOfficer, expected
AS
Ayshe SimsekSecretary, expected
SB
Stephen Bramah-CalvertOfficer, expected
CM
Claire McCarthySecretary, expected
MB
Councillor Mark BlakeChair, present
TH
Councillor Tammy HymasVice-Chair, present
GI
Councillor Gio IozziCommittee Member, present

All 19 on the meeting page

On this subject at Haringey

Search all
  1. Report for approval of the contract for Phase 1(a) of the High Road West Scheme, demolition of 2-32 Whitehall Street, and the management plan for the Love Lane estate.This decision
  2. Approval to extend current Highways and Street Lighting Contracts and approval of the procurement strategy for a future combined Highways and Street Lighting ContractDecided
  3. Approval to procure Enhanced Environmental Enforcement ContractDecided
  4. Approval to Award Contract, Kings Road Car Park, N17Approved
  5. Selby Urban Village - approval to procure Artificial Grass Pitch works contractorDecided
  6. Approval to deliver Council homes and let construction contract within Tiverton Estate boundary N15 6RRDecided

More from Haringey Cabinet

All decisions
MeetingDecisionOutcome
10 Nov 2026 Corporate Delivery Plan 2026-2028DECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Draft 2027-28 Budget and 2027-2032 Medium Term Financial Strategy ReportDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Regulation 19 consultation on Proposed Submission version of Haringey Local Plan 2027-2042 and submission to Secretary of StateDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Admission to Schools - Proposed Admission Arrangements for 2028/29DECLARATIONS OF INTEREST FOR THIS ITEM: None Decided Open
10 Nov 2026 Approval to extend current Highways and Street Lighting Contracts and approval of the procurement strategy for a future combined Highways and Street Lighting ContractDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies