Resolved
That the position be noted.
Strategic Monitoring Committee noted this item on Monday 8 December 2003. Below is the council's own wording, with the papers it was decided on.
Resolved
That the position be noted.
STRATEGIC MONITORING COMMITTEE 8TH DECEMBER 2003
CAPITAL PROGRAMME MONITORING 2003/04 TO 30 SEPTEMBER 2003 Report By: County Treasurer
Wards Affected Countywide
Purpose 1. To report on the Capital Programme forecast for 2003/2004.
Financial Implications 2. The report has no direct financial implications at this stage. The availability and use of conditional resources will be an issue towards the end of the year.
Overview 3. This is the second round of the 2003/04 capital monitoring process. The purpose of this monitoring exercise is to update the original budget position as at 30th September in order to highlight and manage any slippages or overspends.
4. The revised forecast for 2003/04 as at 30th September totals £34,732,000 (excluding LSVT costs). This is an increase of £2,598,000 from the last round of capital monitoring in July, mainly owing to the external funding available to the Herefordshire Strategic Regeneration Package – Rotherwas Match Funding capital project. This programme is funded as detailed in Appendix 1.
5. Actual spend in the first six months at £9,517,000 was 27% of the revised forecast. This excludes unposted commitments of £5,838,000 which would increase committed spend to 44% of the revised forecast. A summary of the programme expenditure for each area is set out on Appendix 2. For comparison, spend to the end of September 2002 was 36% of the 2002/03 Capital Programme.
6. Set out in Appendix 4 is a list of all capital schemes with a budget in excess of £500,000.
Further information on the subject of this report is available from Josie Smith, Accountant – Capital and VAT Services, on 01432 261867 Capital Programme Areas 7. Education
The following budget changes have been identified mainly owing to confirmation of funding sources. Other budget changes may occur during the year as and when the DfES approve capital schemes and additional grant funding is identified.
Change in Budget £’000
• There have been budget increases in capital schemes falling under the Sure Start Initiative. This is owing to confirmation of grant funding by the DfES in relation to early years and childcare provisions. 267
• Other Budget changes of less than £100,000 50
Increase in Education capital budget 317
Actual spend has been low in the first half of the year, at 36% of the total budget. New schemes may be brought on line before the year-end in order to ensure no conditional funding is lost. This will be reflected in future rounds of capital monitoring.
8. Social Care
The budgeted capital expenditure on Social Care has increased by £15,000, owing to an additional IT Grant becoming receivable. Actual spend in the first half of the year is very low. However, committed spend reflects 49% of the total budget.
9. Property
The only budget change relates to the Hillside Capital works. The budget has been increased by £583,000 to reflect equipment, planning costs and fees not included in the original budget. This is being funded through a capital grant from the Primary Care Trust.
10. Policy and Finance
The CCTV capital project is expected to spend £40,000 more than the funding available for the scheme. The reducing crime initiative has also overspent by £5,000. These are being temporarily funded from corporate reserves until new sources of funding are identified.
Actual spend is low at 26%. However, with commitments this increases to 86% of the budget.
Further information on the subject of this report is available from Josie Smith, Accountant – Capital and VAT Services, on 01432 261867 11. eModernisation Programme
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
CAPITAL PROGRAMME MONITORING 2003/04 TO 30TH SEPTEMBER, 2003Report | 116 KB | DownloadRead as text |
Follow Strategic Monitoring Committee at Herefordshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Dec 2009 | MINUTESThat the Minutes of the meeting held on 2 December 2009 be confirmed as a correct record and signed by the Chairman. | Decided | Open |
| 2 Dec 2009 | Accommodation strategyThat: the development of the Joint Accommodation Strategy be endorsed, whilst highlighting the importance of close wo... | Decided | Open |
| 2 Dec 2009 | Integrated corporate performance reportThat (a) the report and points raised by the Committee be noted; and (b) performance against a range of education att... | Noted | Open |
| 2 Dec 2009 | Budget monitoring report 2009It was agreed that a briefing note would be provided. · The number of debts written off was questioned. The Director ... | Agreed | Open |
| 2 Dec 2009 | Scrutiny of external communicationThat (a) the scoping statement for the review as appended to the report be approved as the basis for the review, subj... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.