RESOLVED THAT: (a) additional capital resources of £440,333, be allocated to the scheme bringing together Ross on Wye Library and Info Services on one site; (b) capital resources of £2.92m be allocated to the Masters House scheme in Ledbury (c) additional capital resources of £751,000 be allocated to the Hereford City Centre refurbishment; and (d) the balance of the additional funding be held pending greater certainty about funding of other major projects.
Word for word from the decision Herefordshire published for this meeting.Source: councillors.herefordshire.gov.uk
Wards Affected Ross-on-Wye, Ledbury and Hereford wards.
Purpose To put forward further capital programme proposals following Council’s decision on 7 March 2008 to allocate additional resources to fund prudential borrowing in 2008/09 and 2009/10.
Key Decision This is a Key Decision because it is likely to result in the Council incurring expenditure above agreed budgets for the service or function (shown as a line in the budget book) to which the decision relates but allowing for virements between budget heads and savings within budget heads of up to £500,000.
It was not included in the Forward Plan, however inclusion in the agenda gives the required notice in accordance with Section 15 of the Local Authorities (Executive Arrangements) (Access to Information) Regulations 2000.
Recommendation(s) THAT (a) additional capital resources of £440,333 be allocated to the scheme bringing together Ross-on-Wye Library and Info Services on one site;
(b) capital resources of £2.92m be allocated to the Masters House scheme in Ledbury;
(c) additional capital resources of £751,000 be allocated to the Hereford City Centre refurbishment; and
(d) the balance of the additional funding be held pending greater certainty about funding of other major projects.
Reasons 1 To bring the Council’s capital spending plans up to date following Council’s decision on 7 March 20008 to allocate additional resources. This is in addition to the £1m of capital funding already allocated as part of the 2008/09 budget.
Considerations OVERALL
2 The 2008/09 budget and Medium Term Financial Strategy 2008-2011 allows for additional prudential borrowing of £4.188m in 2008/09 and £4.635m in 2009/10. The
Further information on the subject of this report is available from David Powell, Head of Financial Services on (01432) 383173
Cab Draft Capital Prog 0809 overall total of £8.823m has been earmarked for significant projects. Following Council’s decision on 7 March to agree the budget and financial strategy, three significant projects were submitted for consideration as additional capital expenditure.
3 The Council faces a number of uncertainties around future capital projects with the precise likely financial commitment being unknown. These areas include office accommodation, Edgar Street Grid and the Livestock Market. It is for this reason that the Council needs to exercise caution when releasing funding for the capital programme.
CAPITAL BIDS
The Ross-on-Wye Scheme 4 The project for Ross-on-Wye was initiated to bring Library and Info services together and offer services from a single site. Any relocation of the Info Service that is currently based at Swan House (a non-council property) will produce savings as the property is rented. In 2008/09 the anticipated rent is £52,000 per annum.
5 The original capital budget of £800,000 for the refurbishment of Ross-on-Wye Library was estimated in 2004 and covered the projected building costs only as a starting point for the scheme. It did not take account of relocating the Tourist Information Centre (TIC), providing an alternative library service, refit costs for the library service resulting from the “re-organisation” of the internals of the site or the ICT costs.
6 During the construction phase of the refurbishment of Ross-on-Wye Library alternative service provision will be required for 9-12 months. This has not been provided for within the original projected budget. The preferred option is to maintain a front and back office library service on site during the period of refurbishment. Although this will present some management challenges it presents the best option balancing cost with value of service.
7 There is currently an allocation from the Corporate Capital Programme of £800,000 for the scheme. However, as shown from the cost estimate below there is a shortfall of £440,333:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.