CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
High Peak Borough Council
Cabinet, Tuesday 3 December 2019 at 2.00pm

Leisure Centre Options

Noted Executive 1 paper

Cabinet noted this item on Tuesday 3 December 2019. Below is the council's own wording, with the papers it was decided on.

Item41

Resolved

DECISION: That plans to recruit external consultancy support in order to assist the Council in progressing plans for future investment and management options for leisure centres be noted.
Word for word from the decision High Peak published for this meeting. Source: democracy.highpeak.gov.uk

Follow this further

Built from High Peak's papers

What the report saysPro

Report to Cabinet

Recommendation

2.1It is recommended that the Cabinet:

 Note plans to recruit external consultancy support in order to assist the Council in progressing plans for future investment and management options for leisure centres.

Executive summary

3.1Asset condition surveys were completed during 2016, the outcomes from which were considered by Cabinet in September 2016. The findings highlighted that significant capital investment is required in our leisure assets over the next 30 years in order that they remain fit for purpose.

3.2In August 2017 Cabinet adopted a new Strategy for Physical Activity and Sport. The strategy provides for opportunities for participation be developed and maintained for a widest possible range of the Staffordshire Moorlands community and establishes priorities that will target particular groups of people and communities where inactivity and poor health is more prevalent.

3.3At a similar time, the Council also commissioned FMG Consulting to review its leisure centre provision in the context of its sports facility needs focusing on sports halls, swimming pools and other indoor provision. The purpose of undertaking this review was to inform the Council on options for future provision of council leisure centres and other sports facility based services from 2018 and beyond.

3.4The outcome of this review, in effect sets out a position statement on the suggested facility hierarchy and approach, along with recommendations for phasing of future facility developments and rationalisation. The aim is to ensure that the Council can develop a more sustainable solution in relation to meeting customer needs, affordability and partner aspirations, whilst supporting the overall vision of the Council’s Physical Activity & Sport strategy.

3.5The conclusion of the review was that the Council should consider the following investment requirements:

 Replacement of South Moorlands Leisure Centre with smaller community pool and fitness offer, ideally co-located with other public sector services or alternative options if co-location with health is not deliverable  Refurbishment and essential works at Biddulph Valley Leisure Centre  Replacement pool at Brough Park Leisure Centre  Investment in 3G pitch provision at strategic sites referenced in Local Football Facilities Plan (LFFP) and Playing Pitch Strategy (PPS)

3.6Parkwood Leisure has managed the Council’s leisure centres since March 2006 and in December 2018 Cabinet approved the extension the current contract arrangements with them for the period from 1st March 2019 to 31st March 2024.

3.7Whilst approving the contract extension for Parkwood, the Council committed to commence a process to consider longer-term future management options for the leisure centres in further detail.

3.8There are a number of different delivery options available for the Council to consider for the future management arrangements for leisure centres once the contract with Parkwood comes to an end in March 2024. Recommendations for further consideration, taken from the FMG report are as follows:

 A new outsourced single contract (i.e. an evolution of the current arrangements with Parkwood or other external provider); or  Set up a local delivery vehicle – either a wholly owned subsidiary of the Council or a new trust.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Leisure Centre OptionsReport 918 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 14 attended
MD
Member Diary SMDCOfficer, present
SR
Councillor Sybil Ralphs MBEChair, present
MA
Councillor Mark A DeavilleVice-Chair, apologies
MB
Councillor Michael BowenCommittee Member, present
TD
Councillor Tony D HallCommittee Member, present
JP
Councillor Joe PorterCommittee Member, present
SS
Councillor Sav ScaliseCommittee Member, apologies
EW
Councillor Edwin WainCommittee Member, apologies
SB
Simon BakerOfficer, expected
MT
Mark TrilloOfficer, expected
AS
Andrew StokesOfficer, expected
DL
Dai LarnerOfficer, expected

All 14 on the meeting page

On this subject at High Peak

Search all
  1. Leisure Centre OptionsThis decision
  2. New Mills Leisure Centre UpdateNoted
  3. New Mills Leisure Centre UpdateNoted
  4. HPK/2025/0032 - New Mills Leisure Centre, Hyde Bank Road, New Mills, Derbyshire SK22 4BPApproved
  5. DET/2024/2024 - Biddulph Valley Leisure Centre, Thames Drive, BiddulphApproved
  6. SMD/2024/0176 - Brough Park Leisure Centre, Ball Haye Road, LeekNoted

More from High Peak Cabinet

All decisions
MeetingDecisionOutcome
11 Aug 2026 Forward PlanDECISION: That the be approved for publication. Approved Open
11 Aug 2026 Climate and Nature Delivery Plan Update - Performance Report October 25 to April 26DECISION: That Cabinet approved the performance report set out in Appendix A. Approved Open
11 Aug 2026 Fourth Quarter - Finance, Procurement & Performance ReportsDECISION: 1. That the Fourth Quarter 2025/26 financial, procurement and performance position detailed in Appendices A... Noted Open
11 Aug 2026 Partial Review Staffordshire Moorlands Local PlanDECISION: 1. That the Staffordshire Moorlands Local Plan Partial Review be approved (attached at Appendix A) for a 6-... Approved Open
11 Aug 2026 Adoption of Market Guidance (Development Management)DECISION: That the Guidance attached at Appendix 1 of the report be approved for use by the Council’s Development Man... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies