Resolved
RESOLVED – · That the Audit Service’s 2020/21 year end performance information be NOTED ; · That the opinion on the overall adequacy and effectiveness of the Council’s internal control environment be NOTED .
Audit & Accounts Committee noted this item on Friday 22 October 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – · That the Audit Service’s 2020/21 year end performance information be NOTED ; · That the opinion on the overall adequacy and effectiveness of the Council’s internal control environment be NOTED .
2.1That the committee note the Audit Service’s 2020/21 year end performance information contained within this report.
2.2That the committee note the opinion on the overall adequacy and effectiveness of the Council’s internal control environment.
3.1The purpose of this report is to summarise year end performance information for financial year 2020/21. This includes a breakdown of audits undertaken and completed to date, the number and classification of recommendations made, agreed and where applicable, implemented by management, external review results, developments in the service and an assessment of the Council’s internal control environment. 3.2 The strategic audit plan covered the period 1st April 2020 to 31st March 2021 and the year end performance information referred to above is outlined in the detailed part of this report. Due to the effects of the Covid-19 pandemic including continued diversion of audit resources to support the corporate response to the administration of the Governments various business grants support schemes, the Audit Plan for 2020/21 took longer than usual to complete.
3.3All audit recommendations have been agreed, and to date 93% of 2020/21 audit recommendations that are due have been implemented. Where deficiencies in internal control have been identified and not corrected, Internal Audit are satisfied that they will be resolved in an appropriate manner and they will continue to monitor such cases.
3.4Internal Audit can provide reasonable assurance that the Council’s governance arrangements including risk management and systems of internal control were operating adequately and effectively.
4. How this report links to Corporate Priorities
4.1The assurance provided by the work of Internal Audit informs the Annual Governance Statement and therefore helps to confirm effective use of financial and other resources to ensure value for money.
5.1There are no options to consider.
ANDREW P STOKES Chief Executive
Web Links and Contact details Background Papers None John Leak Head of Audit [email protected] 6. Detail
6.1Introduction
6.1.1 The purpose of this report is to summarise year-end performance information for the Council’s Internal Audit service for the 2020/21 financial year.
6.1.2 The work of the internal audit service is primarily based upon the annual audit plan, which for the financial year 2020/21 was agreed by this committee on 3rd July 2020. The internal audit service also carry out work outside of the audit plan for which a contingency is built in. This unplanned work consists mainly of consultancy work and special investigations into suspected fraud and irregularity.
6.2Progress against Audit Plan
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
1 for Internal Audit Annual ReportAppendix A | 145 KB | Download |
PDF |
2 for Internal Audit Annual ReportAppendix A | 12 KB | Download |
PDF |
Internal Audit Annual ReportReport | 248 KB | DownloadRead as text |
Follow Audit & Accounts Committee at High Peak and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 5 Jun 2026 | Minutes of the previous meetingThat the minutes of the meeting of the Audit and Accounts Committee held on 13 February 2026 be approved as a correct... | Approved | Open |
| 5 Jun 2026 | External Audit Plan - Grant Thornton. (TOR: External Audit 4)That the update be received. | Decided | Open |
| 5 Jun 2026 | Audit Committee Update - Grant Thornton. (TOR: External Audit 2)That the update be received. | Decided | Open |
| 5 Jun 2026 | Internal Audit Progress Report (TOR: Internal Audit 7)That the report be received. | Decided | Open |
| 5 Jun 2026 | Internal Audit Charter (TOR: Internal Audit 1)That the Internal Audit Charter be approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.