Resolved
RESOLVED – That, subject to the deletion of the duplicated attendance of [name removed], the minutes of the Audit & Accounts Committee held on 3 December 2021 be APPROVED as a correct record and signed by the Chair.
Audit & Accounts Committee approved this item on Friday 11 February 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – That, subject to the deletion of the duplicated attendance of [name removed], the minutes of the Audit & Accounts Committee held on 3 December 2021 be APPROVED as a correct record and signed by the Chair.
STAFFORDSHIRE MOORLANDS DISTRICT COUNCIL AUDIT & ACCOUNTS COMMITTEE MEETING Minutes FRIDAY, 3 DECEMBER 2021 PRESENT: Councillor J Davies (Chair)
Councillors K Flunder, N Hawkins, K J Jackson, [name removed], P Wilkinson and N Yates and [name removed]: J Betts Interim Executive Director J Leak Head of Internal Audit V Higgins Information Business Partner S Hampton Democratic Services Officer P Trafford Democratic Services Officer
APOLOGIES: Councillors T Hall and E Fallows
56 DECLARATIONS OF INTEREST
There were no declarations made.
57 MINUTES OF THE PREVIOUS MEETING
[name removed] noted that in Minute 47 – External Audit, Audit Findings Report – the report had stated that “this was a situation that the Council could be proud of”. This was highly commendable and worthy of further publicity.
RESOLVED – That the minutes of the meeting of the Audit and Accounts Committee held on 22 October 2021 be APPROVED as a correct record and signed by the Chair.
58 INTERNAL AUDIT PROGRESS REPORT
Head of Internal Audit – John Leak presented the report covering audit performance for the period 1 June 2021 to 31 October 2021.
4 Audits had been completed, with 3 given Satisfactory assurance and 1 Limited. All recommendations had been agreed and all those which were due had been implemented. The Audit which was given Limited assurance was on the Housing Agency function within the Environmental Health department. Members were encouraged that the Occupational Therapy element of the service had been formalised and implemented. 7 Audits were shown to be ‘in progress’.
1 Audit & Accounts Committee - 3 December 2021
Audit staff had continued to be involved in the administration of Covid 19-related business grants which was affecting the completion of the Audit Plan, which was 41% complete at 31 October 2021. In addition, 1 member of staff was to be seconded to the Finance section from the week after this meeting which would further affect the Audit Plan but assurance was given that such staffing issues would not affect the ability to give an audit opinion.
RESOLVED – That the report be NOTED.
59 RISK MANAGEMENT UPDATE
Information Business Partner – Vanessa Higgins gave an update of the Council’s Risk Management arrangements in accordance with generally accepted good practice.
The Strategic Risk Register identified 16 Strategic Risks, of which 8 were rated ‘high’ and therefore above the risk tolerance threshold. There had been 4 changes to the strategic risk profile as follows:-
New high rated risk around employee wellbeing, included in response to the pandemic and new ways of working; Downgrading of the external funding risk from high to medium due to levelling up and shared prosperity funding streams coming online; Increased risk rating for environmental regulation to incorporate climate change targets; Downgrading of opportunity risk around trading and commercialism due to project being temporarily put on hold due to the pandemic.
The Operational Risk Registers showed 42 Operational Risks, of which 9 were rated ‘high’ and therefore above the risk tolerance threshold. A number of changes had been made to reflect the new management structures and responsibilities, including:-
Development Services – Building Control risk removed now that the Derbyshire partnership was in place. Arboreal risks added; Communities – new register in place, all rated ‘medium’ including resourcing of Climate Change Action Plan; Revenues & Benefits – rationalisation of Universal Credit risks, supplier failure risk reinstated; Environmental Health – escalation of major incident risk to reflect the ongoing pull on public health resources.
September’s Project Risk Review saw 1 new project added – Developer Contributions Supplementary Planning Document. 2 projects had been closed due to completion – Hybrid Mail & Civica Pay (Phase 1). Existing Project Risk Registers were:-
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Minutes of the previous meetingMinutes | 302 KB | DownloadRead as text |
Follow Audit & Accounts Committee at High Peak and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 5 Jun 2026 | Minutes of the previous meetingThat the minutes of the meeting of the Audit and Accounts Committee held on 13 February 2026 be approved as a correct... | Approved | Open |
| 5 Jun 2026 | External Audit Plan - Grant Thornton. (TOR: External Audit 4)That the update be received. | Decided | Open |
| 5 Jun 2026 | Audit Committee Update - Grant Thornton. (TOR: External Audit 2)That the update be received. | Decided | Open |
| 5 Jun 2026 | Internal Audit Progress Report (TOR: Internal Audit 7)That the report be received. | Decided | Open |
| 5 Jun 2026 | Internal Audit Charter (TOR: Internal Audit 1)That the Internal Audit Charter be approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.