Resolved
RESOLVED – That the Council’s annual Internal Audit Plan for 2022/23 be APPROVED .
Audit & Accounts Committee approved this item on Friday 17 June 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – That the Council’s annual Internal Audit Plan for 2022/23 be APPROVED .
2.1That the committee approve the Council’s annual Internal Audit Plan for 2022/23.
3.1The Public Sector Internal Audit Standards state that the Audit Plan must be based on a documented risk assessment undertaken at least annually and it needs to be flexible in response to changes in the Council’s business, risks, operations, programs, systems and controls. Furthermore, the Standard states that the Audit Manager must communicate the internal audit activity’s plans and resource requirements to senior management and the Audit Committee for review and approval. The Audit Manager must also communicate the impact of resource limitations. This report seeks to address these requirements. 3.2 Considerable audit resource was diverted throughout 2021/22 to support the corporate response to the administration of the various Government business grants support schemes and audit resources were further reduced due to a staff secondment. As a direct consequence of this, work has continued into April and May 2022 to complete last years planned audits. The staff secondment has since been extended for a further 3 months. As a result the Audit Plan for 2022/23 will therefore be reduced accordingly and based on a full complement of staff from September onwards and will aim to cover the Council’s key risks and systems.
3.3The annual audit plan for 2022/23 has been created and is attached as Appendix 1. This involved a review of the risk scores in accordance with the Audit Service’s established risk assessment methodology to ensure that the most recent changes affecting risk are taken into account. The Internal Audit Plan is a joint Alliance plan designed to make the best use of Alliance resources and to reflect the nature of Council services.
3.4Should any amendments to the audit plan be necessary during the year, these will be reported to Councillors at future Audit & Accounts Committee meetings.
4. How this report links to Corporate Priorities
4.1The assurance provided by the work of Internal Audit informs the Annual Governance Statement and therefore helps to confirm effective use of financial and other resources to ensure value for money.
5.1Approve the 2022/23 Audit Plan (Recommended). The Council will have an achievable risk based internal audit plan which is designed to provide assurance that the control environment is effective in achieving the Council’s objectives and is in accordance with Public Sector Internal Audit Standards, and therefore the Accounts and Audit Regulations 2015.
5.2Do not approve the 2022/23 Audit Plan (Not Recommended). The Council will not be complying with the Accounts and Audit Regulations 2015 requirement to “undertake an effective internal audit to evaluate the effectiveness of its risk management, control and governance processes, taking into account public sector internal auditing standards or guidance”.
ANDREW P STOKES Chief Executive
Web Links and Contact details Background Papers None John Leak Head of Audit [email protected] 6. Detail
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
1 for Internal Audit: Annual Audit PlanAppendix A | 113 KB | Download |
PDF |
Internal Audit: Annual Audit Plan 2022/2023Report | 226 KB | DownloadRead as text |
Follow Audit & Accounts Committee at High Peak and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 5 Jun 2026 | Minutes of the previous meetingThat the minutes of the meeting of the Audit and Accounts Committee held on 13 February 2026 be approved as a correct... | Approved | Open |
| 5 Jun 2026 | External Audit Plan - Grant Thornton. (TOR: External Audit 4)That the update be received. | Decided | Open |
| 5 Jun 2026 | Audit Committee Update - Grant Thornton. (TOR: External Audit 2)That the update be received. | Decided | Open |
| 5 Jun 2026 | Internal Audit Progress Report (TOR: Internal Audit 7)That the report be received. | Decided | Open |
| 5 Jun 2026 | Internal Audit Charter (TOR: Internal Audit 1)That the Internal Audit Charter be approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.