CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
High Peak Borough Council
The Executive, Thursday 8 December 2022 at 6.00pm

Second Quarter Financial, Procurement and Performance Review 2022/23

Noted Executive 4 papers

The Executive noted this item on Thursday 8 December 2022. Below is the council's own wording, with the papers it was decided on.

Item23/39

Resolved

That the Second Quarter 2022/23 financial, procurement and performance position detailed in Appendices A, B and C and summarised at 3.3 of the covering report be noted.
Word for word from the decision High Peak published for this meeting. Source: democracy.highpeak.gov.uk

Follow this further

Built from High Peak's papers

What the report saysPro

Report to The Executive

Recommendations

2.1It is recommended that the Executive:

 Note the Second Quarter 2022/23 financial, procurement and performance position detailed in Appendices A, B and C and summarised at 3.3 of this covering report; and  Approve the write-offs set out in Appendix D.

Executive summary

3.1This report summarises the Council’s performance and financial position after considering service activity up to the end of the Second Quarter (i.e. 30th September 2022).

3.2Detailed analysis is provided in Appendix A (Finance), Appendix B (Procurement) & Appendix C (Performance).

1 3.3 The position can be summarised as follows: Subject Headline Reference Finance The Finance headlines for the Second Quarter are: Appendix A Performance against Budget  At the Second Quarter stage, the General Fund outturn for 2022/23 is projected to be £35,610 overspent. Efficiency Programme  The current Efficiency Programme was delivered in full in 2021/22. No new savings are programmed to be delivered in 2022/23. Housing Revenue Account  The Housing Revenue Account is predicted to be in deficit (against budget) by £1.05million at the Quarter Two stage. Capital Programme  The General Fund Capital Programme budget for 2022/23 as revised is £19.5 million. The projected outturn is forecast to be £2.25 million underspent compared to budget at the Quarter Two stage.  The HRA Programme for 2022/23 as revised is £6.88 million. The projected outturn is forecast to be £6.43 million, an underspend of £0.45 million compared to budget. Treasury Management  Cash investments held at 30 September 2022 totalled £37.5 million.  Council borrowing at 30 September 2022 totalled £63 million.  The Council’s net interest costs are forecast to be £521,210 under budget on the general fund and £203,200 over budget on the HRA. Revenue Collection  55.11% of Council Tax was collected by 30 September 2022, compared to 56.04% for the same period last year.  59.69% of Business Rates was collected by 30 September 2022 compared with 55.95% for the same period last.  At the end of Quarter Two, the value of sundry debt over 60 days old was £131,610 which compares to £233,390 at 30 September 2021. Procurement The Procurement headlines for the Second Quarter are: Appendix B  29 procurement activities were completed.  The Procurement forward plan includes 27 procurement activities for completion/start in 2022/23 (either HPBC only or joint).  At the 30 September 2022, 44% of procurement activity undertaken was on the forward plan.

Performance The Performance headlines for the Second Quarter are: Appendix C  64% of the key performance indicators on track, with 39% performing better than at this point in the previous year.  The Council closed 54 complaints and received 268 comments and 37 compliments in the Second Quarter.

4. How this Report Links to Corporate Priorities

4.1The successful delivery of all corporate priorities is dependent upon the effective management of performance and financial resources, which is the subject of this report.

2 5. Options and Analysis

5.1Detailed Analysis is contained within the appendices.

6. Implications

6.1Community Safety - (Crime and Disorder Act 1998) None

6.2Workforce None

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
/39Appendix A 832 KB Download
PDF
/39Appendix B 293 KB Download
PDF
/39Appendix C 1.4 MB Download
PDF
Second Quarter Financial, Procurement and Performance Review 2022/23Report 424 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

3 of 16 attended
AM
Councillor Anthony McKeownChair, present
DG
Councillor Damien GreenhalghVice-Chair, present
AB
Councillor Alan BarrowCommittee Member, present
FS
Councillor Fiona SlomanCommittee Member, apologies
JT
Councillor Jean ToddCommittee Member, apologies
AS
Andrew StokesOfficer, expected
NR
Neil RodgersOfficer, expected
SH
Sally HamptonOfficer, expected
MT
Mark TrilloOfficer, expected
LV
Linden VernonOfficer, expected
MD
Member Diary HPBCOfficer, expected
MO
Martin OwenOfficer, expected

All 16 on the meeting page

On this subject at High Peak

Search all
  1. Second Quarter Financial, Procurement and Performance Review 2022/23This decision
  2. Second Quarter Finance, Procurement & Performance ReportsDecided
  3. Second Quarter Finance Performance and Procurement ReportNoted
  4. Second quarter Finance, Performance and Procurement ReportNoted
  5. Second Quarter - Finance, Procurement & PerformanceNoted
  6. Second Quarter - Finance, Procurement & Performance ReportNoted

More from High Peak The Executive

All decisions
MeetingDecisionOutcome
27 Aug 2026 To resolve that the public and press be excluded from the meeting for the following items because there may be disclosure to them of exempt information as defined in Part 1 of Schedule 12A of the Local Government Act 1972.That the public and press be excluded from the meeting for the following items because there may be disclosure to the... Decided Open
6 Aug 2026 To approve the minutes of the previous meetingThat the minutes of the meeting held on 11 June 2026 be approved as a correct record. Approved Open
6 Aug 2026 Forward PlanThat, subject to the above, the be noted. Noted Open
6 Aug 2026 Fourth Quarter Finance, Performance and Procurement UpdateThat the Fourth Quarter 2025/26 financial, procurement and performance position detailed in Appendices A, B and C and... Noted Open
6 Aug 2026 Anti-social Behaviour, Hate and Neighbourhood Management PoliciesThat the Anti-Social Behaviour Policy, Hate Policy and Neighbourhood Management Policy, be approved. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies