Development Control Committee noted this item on Monday 22 January 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
That the update sheet be noted.
22nd January 2024
HPBC DEVELOPMENT CONTROL COMMITTEE
UPDATES REPORT
HPK/2023/0061 – Land at Long Lane, Chapel-en-le-Frith
Additional Representations (2)
This planning application is not in keeping with the local area. It will overburden the private access road to the site, which is heavily used by ramblers, dog walkers, and local residents for recreational walking, and this planning application, if approved, will ruin the aesthetic appeal of walking in this area. There is also a lot of birds that feed and nest in the area, including seasonal woodpeckers, that would be disturbed.
I object to this proposal in the strongest terms possible. My family live in this area for its outstanding natural beauty and the local walks to our home. This proposal would tarnish the attraction of this public right of way.
Wildlife will be ruined and the noise will carry to my property. The owners had a test run of the events they are planning to hold and the noise was awful, keeping my children awake.
Applicant Correspondence to LLFA (Lead Local Flood Authority)
13.09.23:
A “copy of the FRA (Flood Risk Assessment) and Drainage Strategy dated May 2021, prepared by Waterco and first submitted in respect of the earlier application for a similar but larger development. The larger scheme can be seen on the drawing at Appendix K in the FRA. The application for this scheme was withdrawn by the applicants.
I also attach a copy of the revised site plan subject of the current application. You will note the revised scheme relates to the same overall site area but is significantly smaller in terms of the numbers of glamping pods (down from 6 to 3), shepherd's huts (down from 7 to 3), yurts (down from 6 to 5), motorcaravan pitches (down from 5 to 0). This has a significant impact on the overall extent of hard surfacing, that being; access into the site and parking, access track for servicing the body of the site, a field storage shelter (for bikes and maintenance equipment etc), and a reception pod by the site entrance.
As before, it intended that all service tracks and the point of access will be constructed out of permeable materials. There will be no made access tracks to and from the pods off the central access track. Access will be provided along mown grass pathways.
You requested additional information on two points;
1. Evidence that all types of SuDS components have been considered. At least 90% of the site will remain permeable. There will be very little surface water to dispose of or "play with". The proposed Drainage Strategy is still as set out in the Waterco drawing in Appendix K of the FRA. Whilst the FRA of May 2021 related to a significantly larger scheme, I am of the opinion that the overall assessment, conclusions and discharge limitations/proposals hold good for exactly the same but much smaller development.
Attenuation ponds discharging into existing water courses are required as filtration is not a suitable solution on this site. The Drainage Strategy proposes two attenuation ponds (to drain the northern and southern parts of the site separately). The southern attenuation pond will pick up the water from the WTP as previously proposed. In both cases storage capacity and outflow limits are proposed. The two ponds will provide habitat (adding to the overall biodiversity) as well as attenuation.
I can see no need for, nor any practicable possibility of providing, any other SuDS components for this particular development.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Update SheetReport | 428 KB | DownloadRead as text |
Follow Development Control Committee at High Peak and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Aug 2026 | Minutes of the previous meetingThat the minutes of the meeting held on 13 July 2026 be approved as a correct record. | Approved | Open |
| 10 Aug 2026 | Update SheetThat the update sheet be noted. | Noted | Open |
| 10 Aug 2026 | Planning ApplicationsThat the report be noted. | Noted | Open |
| 10 Aug 2026 | HPK/2026/0134 - The Natural Baths, The Crescent, BuxtonThat the application be approved as set out in the report, subject to the amended condition from DCC Archaeology as s... | Approved | Open |
| 10 Aug 2026 | HPK/2026/0184 - Buxton Opera House, Water Street, Buxton, DerbyshireThat Listed Building Consent be granted as set out in the report: 2. That in the event of any changes being needed to... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.