That the application be approved as set out in the report; 2. That in the event of any changes being needed to the wording of the Committee’s decision (such as to delete, vary or add conditions/ informatives /planning obligations or reasons for approval/refusal) prior to the decision being issued, the Head of Development Services be delegated authority to do so in consultation with the Chair of the Committee, provided that the changes do not exceed the substantive nature of the Committee’s decision.
Word for word from the decision High Peak published for this meeting.Source: democracy.highpeak.gov.uk
HIGH PEAK BOROUGH COUNCIL DEVELOPMENT CONTROL COMMITTEE
Date 22nd January 2023
Application No: HPK/2023/0235 Location Glossop Fire Station, Whitfield Park, Glossop, SK13 8LG Proposal Demolition of existing Fire Station and Outbuildings and construction of new Fire Station, Smoke House and Tower with associated outbuildings and external works. Work to include a temporary structure to house the fire appliances during construction Applicant Rob Wood, Derbyshire Fire and Rescue Service Agent Graham Normington, James Totty Partnership Parish/ward Whitfield Date registered 15th August 2023 If you have a question about this report please contact: James Stannard, Tel. 01298 28400 extension 4298, [email protected]
1. SUMMARY OF RECOMMENDATION
Approve with Conditions
1. REASON FOR COMMITTEE DETERMINATION
1.1This application has been brought before the Development Control Committee because the application constitutes Major Development.
2. DESCRIPTION OF THE SITE AND ITS SURROUNDINGS
2.1The application relates to Glossop Fire Station, located at the south- eastern fringes of Glossop in the Whitfield area, immediately adjacent to the A624 on its eastern side.
2.2The site is operated by Derbyshire Fire and Rescue Service, and consists of the main Fire Station building, a Tower, and large area of hard standing.
2.3It is understood that the Fire Station dates from the early 1970’s and is nearing the end of its operational and functional life, being spatially inefficient and not being fit for purpose to meet modern operational needs and a modern diverse workforce.
2.4The main Fire Station building comprises a single storey garage which accommodates the Fire Engine vehicles characterised by four sets of red roller shutter doors on its front elevation, with a covered car wash to the rear, which together spans an approximate depth and width of approximately 20m, and a flat roof having a height of 4.2m.
1 2.5 Alongside the vehicle garage and covered wash area to the south is a two storey pre-fabricated structure which contains staffing changing and toilet facilities, office space, and a boiler room. This structure has a height of 5.9m and spans a similar depth to the engine shed and a width of approximately 11m.
2.6To the rear of these buildings is a large yard area accessed via the north of the engine shed. At the far eastern end of this yard is a single storey building which is home to a garage and gym, which stands alongside a large pre-fabricated tower which stands at an approximate height of 15m.
2.7The site benefits from direct access from the public highway and is surrounded on three sides by a large area of mature woodland.
2.8A row of four terraced properties stand immediately to the north-east which are understood to have previously housed crew that were stationed at Glossop. These buildings were subject to a separate (approved) application under HPK/2022/0028 for the following:
“the temporary works and temporary change of use in association with the proposed redevelopment of the Fire Station in Glossop. Work to include a temporary structure to house the two fire appliances and fire kit and the use of 4 no former Fire Crew houses for welfare and administration during the construction period of the new fire station”
2.9For the purposes of the Local Development Plan, the site lies within the built-up area boundary of Glossop and adjacent to the Whitfield Conservation Area boundary on its eastern side.
3. DESCRIPTION OF THE PROPOSAL
3.1The application follows positive pre-application advice and seeks full planning permission for development described as the demolition of the existing Fire Station and associated Outbuildings and the construction of a new modern Fire Station, Smoke House and Tower with associated outbuilding and external works.
3.2The need and justification for the development is set out under Section 2.0 of the accompanying Design and Access Statement, and is summarised as follows:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.