That the financial summary in 3.2 be noted. 2. That a maximum grant of £8,000 towards the cost of eligible works totalling £15,745 (VAT NA) for the restoration and manufacture of 3 miner’s lamps at Biddulph be approved. The work will be subject to the standard grant scheme conditions. 3. That Members of the Board approve a 75% grant of £6937 towards the cost of eligible works totalling £9,250 (exc VAT) for the timber repairs and redecoration of Endon Village Hall. The work will be subject to the standard grant scheme conditions and the following technical conditions: All new joinery details to match the existing exactly. Decoration to be in the original black and white scheme. 4. That the application for Derby Street be deferred pending the agent making an application for UKSPF. 5. That an additional £173 be spent on the Endon Village Hall project to bring the full spend of the budget in line. 6. A tour of the projects takes place when finished to see where the funding has been spent.
Word for word from the decision High Peak published for this meeting.Source: democracy.highpeak.gov.uk
2.2Members of the Board are recommended to approve a maximum grant of £8,000 towards the cost of eligible works totalling £15,745 (VAT NA) for the restoration and manufacture of 3 miner’s lamps at Biddulph. The work will be subject to the standard grant scheme conditions.
2.3Members of the Board are recommended to approve a 75% grant of £6937 towards the cost of eligible works totalling £9,250 (exc VAT) for the timber repairs and redecoration of Endon Village Hall. The work will be subject to the standard grant scheme conditions and the following technical conditions:
All new joinery details to match the existing exactly. Decoration to be in the original black and white scheme.
2.4Members to discuss the merits of awarding a maximum grant of £8,000 towards roof repairs at 41 and 41a Derby Street as set out in paragraphs 7.5 and 7.6.
Executive summary
3.1This report allows members to consider applications for environmental enhancement and heritage grants under the MPB for funding toward suitable projects within the district.
3.2Members will recall that given the impact of the pandemic unallocated funds from 2020/21 were rolled forward to the subsequent 4 years funding of the MPB. This resulted in an enhanced budget of £60,350 in 2021/22 followed by a further 3 years with a £60,000 budget. Members should note however that the usual budget rules apply and there is no ability to carry forward any unused allocation. If members recommend approval of all the grant applications on this report then the table below represents the current financial position.
Scheme Budget £60,000 Grant offers to date: £44,890 Remaining grants budget 23/24 £15,110 Miners lamps £8,000 Endon Village Hall £6,937 41 and 41a Derby Street £8,000 Total of grant offers £22,937 Remaining Allocation for 2023/24 - £7,827 overspend to be met from 24/25
4. How this report links to Corporate Priorities
4.1This report concerns publicly funding the enhancement, restoration or repair of historic properties or places that are either listed or an identified heritage asset. This, in turn, is related to the Council’s corporate aim 3:
To help create a strong economy by supporting further regeneration of towns and villages.
Alternative options
5.1To not approve environmental and heritage grant awards under the Moorlands Partnership Board and not allocate the capital budget of £60,000 set aside for this grant scheme. As a result, the MPB would not be able to continue to financially assist a number of environmental and heritage projects throughout the district and secure the repair, restoration and enhancement of heritage features, places and buildings. NOT RECOMMENDED
5.2To continue to approve environmental and heritage grant awards to suitable projects throughout the district and to ensure the allocation of the budget of £60,000 this year. As a result, the MPB can financially assist with projects that secure the repair, restoration or enhancement of heritage features, places and buildings and contribute towards the further regeneration of town and villages through Staffordshire Moorlands. RECOMMENDED 6. Implications
6.1Community Safety – No implications at this stage.
6.2Workforce – The Moorlands Partnership Scheme is administered by an officer within the Regeneration Team with assistance when required from the council’s Conservation Officer.
6.3Equality and Diversity/ Equality Impact Assessment - No implications at this stage.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.