That the financial summary in 3.2 be noted. 2. That a maximum grantof £8,000 towards the cost of eligible works totalling £21,264.61 (VAT excl.) towards the repair of the original cast iron windows at the Alton Castle be approved. The work will be subject to the standard grant scheme conditions and the following technical conditions: · The works to be carried out in accordance with the Architects specification. 3. That a 75% grant of £5,925 towards the cost of eligible works totalling £7,900 (VAT excluded) towards the renewal of the flat roof to the Well building at the former Stockton Brook Pumping Station be approved. The work will be subject to the standard grant scheme conditions. 4. That a 75% grant of £4,736 (excl. VAT) towards the cost of eligible works totalling £6,315 (excl. VAT) towards the roof repair of the porch at St Chad, Longsdon be approved. The work will be subject to the standard grant scheme conditions and the following technical conditions: · Any new materials brought to site to match existing. 5. That the application for a maximum grant of £8,000 towards the costs of repairing and restoring the Garage at School Green, Ipstones of £15,700 (VAT excl.) be deferred pending clarity over any planning decisions on the garage site and the applicant be asked to consider uses that would provide community/public use. 6. That a maximum grant of £8,000 towards the cost of eligible works totalling £15,840 (VAT excl.) for the repair of the historic dam at Belmont Farm, Ipstones be deferred until discussions have taken place with the Biodiversity Officer and Staffordshire Wildlife Trust.
Word for word from the decision High Peak published for this meeting.Source: democracy.highpeak.gov.uk
2.2Approve a maximum grant of £8,000 towards the cost of eligible works totalling £21,264.61 (VAT excl.) towards the repair of the original cast iron windows at the Alton Castle. The work will be subject to the standard grant scheme conditions and the following technical conditions:
• The works to be carried out in accordance with the Architects specification.
2.3Approve a 75% grant of £5,925 towards the cost of eligible works totalling £7,900 (VAT excluded) towards the renewal of the flat roof to the Well building at the former Stockton Brook Pumping Station. The work will be subject to the standard grant scheme conditions.
2.4Approve a 75% grant of £4,736 (VAT incl.) towards the cost of eligible works totalling £6,315 (excl. VAT) towards the roof repair of the porch at St Chad, Longsdon. The work will be subject to the standard grant scheme conditions and the following technical conditions:
• Any new materials brought to site to match existing. 2.5 Approve a maximum grant of £8,000 towards the costs of repairing and restoring the Garage at School Green, Ipstones of £15,700 (VAT excl.). The work will be subject to the standard grant scheme conditions and the following technical conditions:
• Any new materials brought to site must match the existing exactly • Rainwater goods to be in cast iron • New joinery details to match the existing exactly unless otherwise agreed • Colour scheme to be agreed • The applicant to consult with Planning and ensure planning permission is not required.
2.6Approve a maximum grant of £8,000 towards the cost of eligible works totalling £15,840 (VAT excl.) for the repair of the historic dam at Belmont Farm, Ipstones The work will be subject to the standard grant scheme conditions.
Executive summary
3.1This report allows the Board to consider applications for environmental enhancement and heritage grants under the MPB for funding toward suitable projects within the district.
3.2The Board will recall that given the impact of the pandemic unallocated funds from 2020/21 were rolled forward to the subsequent 4 years funding of the MPB. This resulted in an enhanced budget of £60,350 in 2021/22 followed by a further 3 years with a £60,000 budget. It should be noted however that the usual budget rules apply and there is no ability to carry forward any unused allocation. Subject to the approval of all the grant applications in this report then the table below represents the current financial position.
Scheme Budget £60,000
Grant offers to date: St Marks Foxt £8,000 The Plough Endon £8,000 St Giles Cheadle £8,000 £24,000 Grant offers for consideration: Alton Castle £8,000 Stockton Brook Pumping Station £5,925 St Chad Church Longsdon £4,736 Garage School Green Ipstones £8,000 Belmont Farm Dam £8,000 Total of grant offers for approval £34,661
Remaining Allocation for 2024/25 £1,339 4. How this report links to Corporate Priorities
4.1This report concerns publicly funding the enhancement, restoration or repair of historic properties or places that are either listed or an identified heritage asset. This, in turn, is related to the Council’s corporate aim:
• To help create a strong economy by supporting further regeneration of towns and villages.
Alternative options
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.