High Peak Borough Council
Moorlands Partnership Board, Thursday 28 November 2024 at 2.00pm

Summary of Projects

Noted Committee 1 paper

Moorlands Partnership Board noted this item on Thursday 28 November 2024. Below is the council's own wording, with the papers it was decided on.

Item22

Resolved

· That the update report be noted. · That the recommendation to reallocate the underspend on the Foxlowe conservatory roof to the Foxlowe outhouse roof be approved.
Word for word from the decision High Peak published for this meeting. Source: democracy.highpeak.gov.uk

Follow this further

Built from High Peak's papers

What the report saysPro

Report to Moorlands Partnership Board

Recommendation

2.1That the update report is noted.

Executive summary

3.1This report deals with progress to date on those projects awaiting commencement, on site, or completed since the last meeting of the Moorlands Partnership Board.

3.2This report is for information only but does offer members an opportunity to comment on progress. The report will be presented with an accompanying power point presentation which displays images of each project.

4. How this report links to Corporate Priorities

4.1This report concerns publicly funding the restoration and repair of historic properties or places that are either listed or an identified heritage asset. This in turn, is related to the Council’s corporate aim:

• Help create a strong economy by supporting further regeneration of towns and villages. 5. Alternative Options

5.1There are no alternative options as this an update report on progress only.

6. Implications

6.1Community Safety No implications at this stage.

6.2Workforce The Moorlands Partnership Scheme is administered by an officer within the Regeneration Team with assistance when required from the Council’s Conservation Officer.

6.3Equality and Diversity / Equality Impact Assessment No implications at this stage.

6.4Financial Considerations There are allocations within the capital programme for the Moorlands Partnership grant scheme. The projects outlined in this report have been met from approved budgets from previous years. The budget for this year 2024-2025 is £60,000.

6.5Legal Local authorities are empowered to give grants towards improvements in conservation areas under Section 57 of the Planning (Listed Buildings and Conservation Areas) Act 1990.

6.6Climate Change No Implications at this stage.

6.7Consultation Grant offers are made in consultation with and approved by the Moorlands Partnership Board. Where required, projects that require planning permission and listed building consent are subject to the normally statutory consultations.

ANDREW P STOKES Chief Executive

Web Links and Contact details Background Papers Joanne Brooks Regeneration Of f icer

joanne.brooks@staf f smoorlands.gov.uk 7. Project Updates and Progress

2016/17 OFFERS:

Biddulph Town Council Projects

The Trough – The new stone pieces have been completed. The County Council have confirmed that the town council can have temporary traffic signals on Thursday 7th November. Work should be completed by the date of the meeting.

2020/2021 OFFERS:

St Edwards Summerhouse – Repair of Grade II listed summer house within site

All the joinery work to the summer house has now been completed including the roof structure and new timber soffits all around the building. Large areas of timber panelling have been reinstated inside on a like for like basis. Just waiting for the zinc roof to be reinstated.

2021/2022 OFFERS:

Christ Church, Biddulph Moor – Roof repairs Applicant has made contact with Officers. They have had to divert funds towards the repair of the Church Hall roof as more critical.

2022/2023 OFFERS:

Foxlowe Arts Centre – Conservatory Repairs The contractor will be on site imminently.

2023/2024 OFFERS:

Endon Station new gate and sign board, reinstatement of windows and door New gate and signboard installed and repaired and decorated. Works to reinstate windows and doors delayed.

Cheddleton Station Signal Box relocation Signal box relocated and grant paid.

St James Court Clock tower redecoration Due to coming winter months works will now start next spring.

8 King Street Sash Window reinstatement Windows manufactured and waiting to be installed. Delays due to specialist glass supply.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Summary of ProjectsReport 107 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 22 attended
AH
Councillor Andrew HartCommittee Member, apologies
CJ
Councillor Christina JebbChair, present
LM
Councillor Linda MalyonVice-Chair, present
BB
Barry BirchCommittee Member, present
BE
Councillor Ben EmeryCommittee Member, present
EF
Councillor Elsie FallowsCommittee Member, present
KF
Councillor Keith FlunderCommittee Member, present
KH
Councillor Ken HarperCommittee Member, absent
AH
Andrew H HartCommittee Member, expected
MJ
Councillor Mark JohnsonCommittee Member, present
VO
Councillor Vicky O'SheaCommittee Member, present
DP
Councillor Darren PriceCommittee Member, present

All 22 on the meeting page

On this subject at High Peak

Search all
  1. Summary of ProjectsThis decision
  2. Summary of ProjectsDecided
  3. Summary of Projects.Decided
  4. Summary of Projects.Decided
  5. Summary of ProjectsDecided
  6. Summary of ProjectsNoted

More from High Peak Moorlands Partnership Board

All decisions
MeetingDecisionOutcome
16 Mar 2026 To Approve the Minutes from the Previous Meeting.That the minutes of the previous meeting held on 17 th November 2025, be approved as correct record. Approved Open
16 Mar 2026 Summary of ProjectsThat the report be received. Decided Open
16 Mar 2026 Financial Summary and Proposed Grant Awards1) The Board noted the financial summary in 3.2 of the report; 2) Members of the Board are APPROVED a maximum grant o... Noted Open
16 Mar 2026 Any Other Business.That some alternative design options and cost for the plaque be presented at the next meeting. Decided Open
17 Nov 2025 To Approve the Minutes from the Previous Meeting.That the minutes of the previous meeting held on 15 July 2025 be approved. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies