Audit & Accounts Committee approved this item on Friday 29 November 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
That the minutes of the meeting of the Audit and Accounts Committee held on 2 August 2024 be approved as a correct record.
STAFFORDSHIRE MOORLANDS DISTRICT COUNCIL AUDIT & ACCOUNTS COMMITTEE DECISIONS FRIDAY, 2 AUGUST 2024 PRESENT: Councillor M Spooner (Chair)
Councillors J Cox, K Flunder, D Proudlove and N Yates
IN ATTENDANCE: Councillor(s) C Wood
APOLOGIES: Councillors C Edwards, A Parkes, A Hart and [name removed]
15 DECLARATIONS OF INTEREST
There were no declarations of interest made.
16 MINUTES OF THE PREVIOUS MEETING
RESOLVED:
That the minutes of the meeting of the Audit and Accounts Committee held on 7 June 2024 be approved as a correct record.
17 AUDIT COMMITTEE UPDATE - GRANT THORNTON
A verbal summary of the Audit Findings Reports was delivered to members by representatives from Grant Thornton. Members were reassured that the Audit Backstop was on track and plans would be put into place should there need to be additional meetings scheduled to sign off reports. Members discussed the valuation of assets that had been refurbished against the value for money and the independent process around this. The Chair advised members to use the resources detailed on page 11 of the report.
RESOLVED:
That the report be noted.
18 RISK MANAGEMENT UPDATE
The Council’s Strategic, Operational and Project Risk Registers were reviewed by the Audit and Accounts Committee on an exception basis. This report was based on the Council’s position as at March 2024. The latest analysis of the Strategic Risk Register revealed that the Council had identified and assessed 19 strategic risks, of which 8 (42%) were rated as 'high' and therefore above the Council’s risk tolerance threshold. The eight ‘high’ rated risks are listed in full at Appendix A. The Operational Risk Registers revealed that the Council had identified and assessed 40 operational risks in total, of which 13 (32%) were rated as ‘high’ and, therefore, above the Council’s risk tolerance thresholds. The risks falling within the ‘high’ category are listed in full at Appendix B. The project risk registers cover 7 projects, total risks had increased significantly following the inclusion of the three risk registers for the LUF project. Audit & Accounts Committee - 2 August 2024
Members were advised that the report was a running commentary and it was constantly refreshed and updated.
RESOLVED:
That the Committee noted the Council’s current risk position and the mitigation/ fruition plans summarised within Appendix A (strategic risks), Appendix B (operational risks), Appendix C (project risks) and Appendix D (opportunity risks).
19 TREASURY MANAGEMENT UPDATE REPORT
The report allowed robust scrutiny of the Council’s Treasury Management performance in 2024/25 in compliance with the Chartered Institute of Public Finance and Accountancy (CIPFA) Code of Practice on Treasury Management and generally accepted good practice.
The report was delivered in accordance with the Chartered Institute of Public Finance and Accountancy (CIPFA) Code of Practice for Treasury Management, which recommends that members be updated on treasury management activities regularly (annual, mid-year and quarterly reports).
This report comprised of the following: The latest interest rate forecast The investment portfolio and investment income The capital loan (service investment – housing) Borrowing requirements with associated borrowing costs Compliance against Prudential and Treasury indicators set in the Treasury Management Strategy 2024/25
The Officer provided an overview of the main headlines which were:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Minutes of the previous meetingMinutes | 226 KB | DownloadRead as text |
Follow Audit & Accounts Committee at High Peak and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 5 Jun 2026 | Minutes of the previous meetingThat the minutes of the meeting of the Audit and Accounts Committee held on 13 February 2026 be approved as a correct... | Approved | Open |
| 5 Jun 2026 | External Audit Plan - Grant Thornton. (TOR: External Audit 4)That the update be received. | Decided | Open |
| 5 Jun 2026 | Audit Committee Update - Grant Thornton. (TOR: External Audit 2)That the update be received. | Decided | Open |
| 5 Jun 2026 | Internal Audit Progress Report (TOR: Internal Audit 7)That the report be received. | Decided | Open |
| 5 Jun 2026 | Internal Audit Charter (TOR: Internal Audit 1)That the Internal Audit Charter be approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.