That applications HPK/2024/0299 (FULL) and HPK/2024/0302 (LBC) be approved as set out in the report; 2. That in the event of any changes being needed to the wording of the Committee’s decision (such as to delete, vary or add conditions/ informatives /planning obligations or reasons for approval/refusal) prior to the decision being issued, the Head of Development Services be delegated authority to do so in consultation with the Chair of the Committee, provided that the changes do not exceed the substantive nature of the Committee’s decision.
Word for word from the decision High Peak published for this meeting.Source: democracy.highpeak.gov.uk
HIGH PEAK BOROUGH COUNCIL DEVELOPMENT CONTROL COMMITTEE
Date: 14th July 2025
Application No: HPK/2024/0299 (FULL) and HPK/2024/0302 (LBC) Location Grove Hotel, Grove Parade, Terrace Road, Buxton Proposal HPK/2024/0299: Application for Removal or Variation of Condition 6 in relation to application HPK/2022/0376 HPK/2024/0302: Application for Removal or Variation of Condition 6 in relation to application HPK/2022/0377 Applicant AH2 Buxton Limited Agent Cadant Planning Parish/Ward Buxton Central Date registered: 10/07/2024 If you have a question about this report please contact: Rachael Simpkin [email protected] 01538 395400 extension 4122
REFERRAL
The s.73 variation planning application is categorised as a small-scale major.
1. SUMMARY OF RECOMMENDATION
APPROVE subject to recommended conditions.
2. DESCRIPTION OF THE SITE AND ITS SURROUNDINGS
2.1The proposal relates to the Grade II listed former Grove Hotel, which has been redundant for some time. The building is located within the Buxton Central Conservation Area, which is subject to an Article 4 direction. The building’s listing is described as: “Formerly known as: Grove Coffee House Terrace Road. Includes: Nos.1, 3 and 5 Grove Hotel and Grove Parade Spring Gardens. Hotel with shops. c1770 and late C18 with canopy and shop fronts of 1883 at 1 2 & 3 Grove Hotel & Parade”.
2.2The 4-storey building built c.1770-1802 with associated external space to the rear occupies a prominent corner positioning to the east side of Terrace Road presented with a rendered frontage, sash windows, Welsh slate roof with grouped stone chimney stacks and cast iron glazed canopy over the ground shop frontages and hotel entrance. The rear of the building has been subject to a number of alterations and extensions over time.
2.3The site falls within the Town Centre, Primary Shopping Centre, Regeneration Area (DS22) within the defined built up area boundary of Buxton. Other site constraints include: Flood zones 2 and 3, Buxton Groundwater Source Protection Zone, Nutrient Neutrality: River Wye SSSI (Site Special Scientific Interest) and Peak District Dales Catchment SAC (Special Area of Conservation) and Radon Potential Area Class 5.
3. DESCRIPTION OF THE PROPOSAL
3.1A s.73 variation planning application and listed building consent is sought in relation to the extant approved planning permission ref. HPK/2022/0376 and approved listed building ref. HPK/2022/0377 for a residential development comprising of 17 apartments dated 4th April 2024. The approved schemes comprise of two rear extensions, together with external and internal repair / refurbishment works (including canopy) to create 6 x one-bedroom and 11 x two-bedroom apartments over three floor levels, with storage provision on the ground floor.
3.2In terms of background, the consents for the conversion of the former Grove Hotel to 17 residential apartments first received a resolution of approval at the 22nd May 2023 Development Control (DC) Committee. These approvals were subject to securing recommended planning / listed building conditions, completion of a s106 agreement in relation to identified planning obligations and satisfaction of outstanding flood risk matters as outlined within the officer report and subsequent updates report to committee.
3.3Latterly, an addendum report dealing only with matters relating to heritage (in relation to removal of building fabric without consent), flood risk, ecology (bats), lift provision and other matters which had arisen since the previous report was presented to the 26th February 2024 DC Committee in relation to the pending consents i.e. HPK/2022/0376 and HPK/2022/0377. The proposals received a resolution to approve subject to recommended listed building / planning conditions and a s106 legal agreement. In addition, delegated authority was agreed in relation to building structural stability to ensure the safety of future occupiers during a flood event. Subsequently, the consents were issued on the 4th April 2024.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.