Treasury Management Update (TOR: Governance, Risk and Control 12)

Noted Finance 2 papers

AI summaryHigh Peak Audit & Accounts Committee notes the Treasury Management position for the quarter ended 30 September 2025, with a £80,000 investment income shortfall forecast and a £34,400 borrowing underspend.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedQuarter ended 30 September 2025 position noted by members
Money£80,000 investment income shortfallAgainst budget of £742,030; £34,400 borrowing underspend
What happens nextNo new actionsReport is a statement of fact, no options
Who it affectsCouncil finances and investments£21.5m portfolio across five institutions, £12.6m external debt forecast

What was decided

Members noted the current Treasury Management position at the quarter ended 30 September 2025, including investment portfolio, income, borrowing and Prudential Indicator compliance. Report 2.1, 3.2

Why

The update is required under the CIPFA Code of Practice for Treasury Management, which recommends regular reporting to members, and the Audit & Accounts Committee's Terms of Reference require scrutiny of all treasury management reports. Report 3.1

Effective Treasury Management safeguards and manages the Council's financial resources, which underpin delivery of the Council's main priorities. Report 4.1, P5

Investment and borrowing decisions follow the formally adopted Treasury Management Strategy, with security of deposits taking precedence over return, supported by external advisers MUFG Corporate Markets.

What happens next

No next steps arise: the report is a statement of fact and there are no options to consider. Report 5.1

The money

  • £21.5million Investment portfolio total at end of the quarter, across five institutions Report 3.3
  • £1.5million Balance held in ESG linked investments with one institution Report 3.3
  • £15.5million Average investment balances to the end of quarter 2 Report 3.3
  • £742,030 Investment income budget for the year Report 3.3
  • £80,000 Forecast shortfall in investment income against budget Report 3.3
  • £307,000 Interest earned during the year on the capital loan (service investment, housing) Report 3.3
  • £12.6million Forecast level of external debt at the end of the year Report 3.3
  • £778,320 Borrowing costs budget for the year Report 3.3
  • £34,400 Forecast underspend against borrowing costs budget Report 3.3

Options considered

  • Rejected: Consider alternative actions on the Treasury Management position. The report is a statement of fact and there are no options to consider. Report 5.1

Implications

  • Financial: A £80,000 shortfall in investment income is forecast against a £742,030 budget, while a £34,400 underspend is forecast against borrowing costs of £778,320; external debt is forecast at £12.6million by year end. Report 3.3
  • Risk: Treasury Management carries inherent financial risks, including potential loss of interest and deposits, mitigated by external advisers MUFG Corporate Markets and the adopted Treasury Management Strategy with security of deposits prioritised over return.
  • Climate: Information on investments with Environmental, Social and Governance (ESG) links is included in the investment portfolio; £1.5million is held in ESG linked investments. Report 3.3
  • Equalities: The report has been prepared in accordance with the Council's Diversity and Equality Policies.
  • Other: No community safety, workforce, legal, biodiversity or consultation implications identified. Report 6.1

Who and where

  • The Council, through the management of its investment portfolio, borrowing position and compliance with Treasury Management Strategy and Prudential Indicators. Report 3.2, 4.1
  • Staffordshire Moorlands District Council, named in the report body as the subject of the Treasury Management position. Report 5.1, P11, P12

Timeline

  • Start of 2025/26: Bank of England base rate stood at 4.50% Report 3.3
  • May 2025: Bank of England base rate decreased to 4.25% Report 3.3
  • August 2025: Bank of England base rate decreased to 4.00% Report 3.3
  • Quarter ended 30 September 2025: Investment portfolio totalled £21.5million across five institutions; average balances to end of quarter 2 were £15.5million Report 3.3
  • End of 2025/26 (forecast): External debt forecast at £12.6million; investment income shortfall of £80,000 and borrowing underspend of £34,400 forecast Report 3.3

Plain English for the jargon

  • CIPFA: Chartered Institute of Public Finance and Accountancy, the professional body whose Code of Practice for Treasury Management guides council treasury activity.
  • ESG: Environmental, Social and Governance, criteria used to identify investments linked to sustainability outcomes.
  • Prudential Indicators: Measures set within the Treasury Management Strategy to demonstrate that capital expenditure, borrowing and treasury activity are affordable, prudent and sustainable.
  • MUFG Corporate Markets: External Treasury Management advisers engaged by the Council to support investment and borrowing decisions.
  • Service investment, housing: A capital loan made by the Council to support housing activity, currently earning £307,000 interest during the year.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item76

Resolved

That Members note the current Treasury Management position at the quarter ended 30 September 2025.
Word for word from the decision High Peak published for this meeting. Source: democracy.highpeak.gov.uk

Follow this further

Built from High Peak's papers

What the report saysPro

Report to Audit & Accounts Committee

Recommendation

2.1That Members note the current Treasury Management position at the quarter ended 30 September 2025.

Executive summary

3.1This report is delivered in accordance with the Chartered Institute of Public Finance and Accountancy (CIPFA) Code of Practice for Treasury Management, which recommends that members be updated on treasury management activities regularly (annual, mid-year and quarterly reports). The Terms of Reference of the Audit & Accounts Committee, section ‘Governance, risk and control’, point 12 confirms: “To recommend to Council the approval of the Annual Treasury Management Strategy and Annual Treasury Management Report and scrutinise all treasury management reports”.

3.2This report comprises the latest interest rate forecast, the investment portfolio and investment income, the capital loan (service investment – housing), impact of the capital programme, borrowing requirements and associated borrowing costs, and compliance against Prudential and Treasury indicators set in the Treasury Management Strategy 2025/26.

3.3The main headlines are: • The Bank of England base rate has decreased from 4.50% at the start of the year to 4.25% in May and again to 4.00% in August. • At the end of the quarter, the Council’s investment portfolio total was £21.5million spread across five separate institutions; of this balance on specific ESG linked investments there was £1.5million with one institution. Average balances to the end of quarter 2 were £15.5million. • A shortfall of £80,000 in investment income is forecast against a budget of £742,030. • The capital loan (service investment – housing) is earning £307,000 interest during the year. • The Council’s level of external debt is forecast to be £12.6million at the end of the year. An underspend of £34,400 is forecast against the borrowing costs budget of £778,320.

4. How this report links to Corporate Priorities

4.1An effective Treasury Management function is critical in safeguarding and effectively managing the financial resources at the Council’s disposal. Sufficient financial resources are required to deliver and underpin all of the Council’s main priorities.

Alternative options

5.1This report sets out the Treasury Management position for Staffordshire Moorlands District Council for 2025/26 to date and the projected outturn. As such it is a statement of fact and there are no options.

6. Implications

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
1 for Treasury Management UpdateAppendix A 150 KB Download
PDF
Treasury Management Update (TOR: Governance, Risk and Control 12)Report 94 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 26 attended
MS
Councillor Matthew SpoonerChair, present
CE
Councillor Charlotte EdwardsVice-Chair, present
JC
Councillor Jo CoxCommittee Member, present
KF
Councillor Keith FlunderCommittee Member, present
AH
Councillor Andrew HartCommittee Member, apologies
DP
Councillor Dave ProudloveCommittee Member, present
CS
Councillor Charlie SmithCommittee Member, apologies
MW
Councillor Michael WorthingtonCommittee Member, present
NY
Councillor Nigel YatesCommittee Member, present
JB
John BerrisfordAdvisory Member, apologies
MD
Member Diary SMDCOfficer, expected
EB
Emily BennettsOfficer, expected

All 26 on the meeting page

On this subject at High Peak

Search all
  1. Treasury Management Update (TOR: Governance, Risk and Control 12)This decision
  2. Audit and Accounts Committee - Treasury Management UpdateNoted
  3. Audit and Accounts Committee - Treasury Management Strategy Statement (TMSS) 2026/27Approved
  4. Treasury Management UpdateDecided
  5. Treasury Management Strategy Statement (TMSS) 2026/27Approved
  6. Treasury Management UpdateNoted

More from High Peak Audit & Accounts Committee

All decisions
MeetingDecisionOutcome
5 Jun 2026 Minutes of the previous meetingThat the minutes of the meeting of the Audit and Accounts Committee held on 13 February 2026 be approved as a correct... Approved Open
5 Jun 2026 External Audit Plan - Grant Thornton. (TOR: External Audit 4)That the update be received. Decided Open
5 Jun 2026 Audit Committee Update - Grant Thornton. (TOR: External Audit 2)That the update be received. Decided Open
5 Jun 2026 Internal Audit Progress Report (TOR: Internal Audit 7)That the report be received. Decided Open
5 Jun 2026 Internal Audit Charter (TOR: Internal Audit 1)That the Internal Audit Charter be approved. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies