Audit & Regulatory Committee, Wednesday 11 February 2026 at 6.30pm

Risk Management Strategy

Approved Licensing 2 papers

AI summaryAudit & Regulatory Committee approves High Peak's revised Risk Management Strategy, the tenth version since 2010, with new quarterly reporting on council-owned company risks.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedRevised Risk Management Strategy 2025 adopted
MoneyNot stated
What happens nextStrategy now in forceCouncil-owned company risks reported quarterly
Who it affectsAll council services and companiesEmbeds risk management across the Alliance

What was decided

The Audit & Regulatory Committee approved the revised Risk Management Strategy as set out in Appendix 1. Report 2.1

The current risk tolerance threshold was confirmed as remaining appropriate for the Alliance's financial context and reserves. Report 8.7

Oversight of council-owned companies was strengthened, with all above-tolerance risks to be reported quarterly to the Risk Management Group. Report 8.3

Why

The strategy is reviewed every two years and this is the tenth iteration, first adopted in December 2010. Report 3.1, P23

The review considered the evolving risk environment, including Local Government Reorganisation, financial pressures, cyber security, climate impacts, and council-owned company governance. Report 8.1, 8.4, P27

Officers drew on a Zurich Resilience Solutions horizon-scanning session in November 2024 and the World Economic Forum's Global Risks Report 2025. Report 8.5, 8.9, P21

What happens next

Above-tolerance risks in council-owned companies will be reported quarterly to the Risk Management Group, escalating to the Audit and Regulatory Committee where necessary. Report 8.3

Local Government Reorganisation risks will continue to be tracked through a dedicated register covering governance, financial, service delivery, workforce and statutory risks. Report 8.4

Heads of Service will continue to be consulted on risk tolerance thresholds through the Risk Management Group. Report 6.8

Options considered

  • Chosen: Approve the Risk Management Strategy 2025 as presented. Recommended by the Chief Executive as the outcome of the 2025 review Report P9, 2.1
  • Rejected: Recommend amendments prior to approval Report P9

Implications

  • Financial: Effective risk management is said to contribute to the Council's financial objectives and is linked to the Medium-Term Financial Plan. Report 6.4
  • Risk: Establishing the Council's risk tolerance is described as central to delivering a successful Risk Management Strategy.
  • Climate: Compliance with environmental regulatory frameworks is included as a risk on the Council's risk register. Report 6.6
  • Equalities: The report was prepared in accordance with the Council's Diversity and Equalities policies. Report 6.3
  • Staffing: Employee wellbeing sits within the strategic risk register and continues to be monitored.
  • Legal: No legal implications arise directly from the report. Report 6.5
  • Community safety: No direct community safety, safeguarding or prevent implications identified. Report 6.1, P12

Who and where

  • All council service areas, as risk management is embedded across them Report 4.1
  • Council-owned companies, now subject to quarterly risk reporting Report 8.3
  • The Risk Management Group, with strengthened oversight duties Report 8.2, 8.3
  • Heads of Service, consulted on risk tolerance thresholds Report 6.8

Timeline

  • December 2010: Joint Risk Management Strategy first adopted Report P23
  • November 2024: Zurich Resilience Solutions commissioned to lead a future-risks discussion Report 8.5
  • 2025: Tenth iteration review undertaken, informed by Global Risks Report 2025 Report 8.1, 8.9
  • 2026-02-11: Audit & Regulatory Committee approved the revised strategy

Plain English for the jargon

  • Alliance: The working arrangement between High Peak Borough Council and Staffordshire Moorlands District Council, referenced throughout the strategy.
  • LGR: Local Government Reorganisation, identified as a significant area of uncertainty with its own risk register.
  • Risk tolerance: The level of risk the Alliance is prepared to accept, reviewed as part of this strategy.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item26/40

Resolved

That the revised , be approved.
Word for word from the decision High Peak published for this meeting. Source: democracy.highpeak.gov.uk

Follow this further

Built from High Peak's papers

What the report saysPro

Report to Audit & Regulatory Committee

Recommendation

2.1That members approve the revised Risk Management Strategy as detailed at Appendix 1.

Executive summary

3.1The Alliance Risk Management Strategy is reviewed every two years to ensure the Council’s approach reflects changing circumstances.

3.2This strategy sets out a clear, Alliance-wide framework for managing risk and opportunity, embedding enterprise risk management into governance, planning, decision-making, and day-to-day service delivery.

3.3It defines risk tolerance, responsibilities, and reporting arrangements, ensuring strategic, operational, project, partnership, and council-owned company risks are identified, actively managed, and escalated by exception through established governance structures.

3.4The approach supports good governance, service resilience, and business continuity, enabling the Alliance to anticipate change, manage the impacts of Local Government Reorganisation, protect its reputation and assets, and deliver objectives while responsibly enabling innovation and value for money.

1 4. How this report links to Borough Priorities

4.1Risk Management is embedded across all service areas and therefore links to each of the Council’s Borough Plan aims.

Options

5.1The Committee may:

• Approve the Risk Management Strategy 2025 as presented; or • Recommend amendments prior to approval.

6. Implications

6.1Community safety, including safeguarding and prevention of terrorism

None 6.2 Workforce Employee wellbeing has been included within the strategic risk register and continues to be monitored

6.3Equality and Diversity/Equality Impact Assessment This report has been prepared in accordance with Diversity and Equalities policies.

6.4Financial Considerations Effective Risk Management contributes to the Council’s financial objectives

6.5Legal None arising directly from this report.

6.6Climate Change and Sustainability Compliance with environmental regulatory frameworks is included as a risk within the Council’s risk register

6.7Conservation and Enhancement of Biodiversity None

6.8Consultation Heads of Service have been consulted on the current risk tolerance thresholds through the Risk Management Group 6.9 Risk Assessment Establishing the Council’s risk tolerance is central to delivering a successful Risk Management Strategy.

2 ANDREW P STOKES Chief Executive

Background Papers Contact details

Medium Term Financial Plan. Tanya Cooper, Head of Organisational Development and Global Risks Report 2025 – World Economic Forum. Transformation, [email protected] Risk Horizon Scan 2024-25

Zurich Julie Nankivell Information Business Partner, [email protected]

3 7. Background 7.1 The Council’s Joint Risk Management Strategy was first adopted in December 2010. In line with the commitment given in the Strategy to undertake regular reviews, the Strategy is now in its tenth iteration.

8. 2025 Review

8.1The 2025 strategy review has been informed by the areas bulleted below, which are explored in more detail in the following paragraphs:

• Ongoing assurance activity, including internal audit findings and monitoring undertaken by the Risk Management Group

• The evolving risk environment, including Local Government Reorganisation (LGR), financial pressures, and governance of council-owned companies

• Review of the Alliance’s risk tolerance thresholds in the context of the Medium-Term Financial Plan and organisational resilience

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Risk Management Strategy /40Appendix A 311 KB Download
PDF
Risk Management StrategyReport 101 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 25 attended
OC
Councillor Ollie CrossChair, present
MT
Councillor Matt TaylorVice-Chair, present
PB
Councillor Pauline BellCommittee Member, present
AB
Councillor Angela BenhamCommittee Member, present
JC
Councillor Joanna CollinsCommittee Member, present
NG
Councillor Nigel GourlayCommittee Member, apologies, sent representative
MH
Councillor Madeline HallCommittee Member, present
CP
Councillor Chris PayneCommittee Member, present
PR
Councillor Pam ReddyCommittee Member, apologies
JL
John LeakOfficer, expected
EB
Emily BennettsOfficer, expected
MT
Mark TrilloOfficer, expected

All 25 on the meeting page

On this subject at High Peak

Search all
  1. Risk Management StrategyThis decision
  2. Risk Management UpdateDecided
  3. Risk Management StrategyApproved
  4. Risk Management UpdateNoted
  5. Treasury Management Update (TOR: Governance, Risk and Control 12)Noted
  6. Annual Treasury Management Report. (TOR: Governance, risk and control 12)Approved

More from High Peak Audit & Regulatory Committee

All decisions
MeetingDecisionOutcome
2 Jun 2026 To approve the Minutes of the previous meetingThat the minutes of the previous meeting held on 11 February 2026 be approved as a correct record. Approved Open
2 Jun 2026 High Peak Borough Council Audit Plan 2025 - 2026 (External Audit)That the report be noted. Noted Open
2 Jun 2026 Audit Progress and Sector Update Report (External Audit)That the report be noted. Noted Open
2 Jun 2026 Internal Audit Periodic Report February 2026 to May 2026That the Committee notes the progress information within the report. Decided Open
2 Jun 2026 Internal Audit CharterThat the Council’s Internal Audit Charter be approved. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies