Resolved
That the update be received. 2. That the Head of Organisational Development and Transformation advise members how they can view the full risk register.
AI summaryAudit Committee receives December 2025 risk update showing 11 of 21 strategic risks rated high, and asks the Head of OD and Transformation to advise on viewing the full register.
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
That the update be received. 2. That the Head of Organisational Development and Transformation advise members how they can view the full risk register.
2.1That the committee notes the Council’s current risk position and the mitigation / fruition plans summarised within Appendix A (strategic risks), Appendix B (operational risks), Appendix C (project risks) and Appendix D (opportunity risks).
3.1The Council’s Strategic, Operational and Project Risk Registers are reviewed by the Audit and Accounts Committee on an exception basis. This report is based upon the Council’s position in December 2025.
3.2The latest analysis of the Strategic Risk Register reveals that the Council has identified and assessed 21 strategic risks, of which 52% are rated as 'high' and therefore above the Council’s risk tolerance threshold. The ten ‘high’ rated risks are listed in full at Appendix A.
3.3The Operational Risk Registers reveal that the Council has identified and assessed 45 operational risks in total, of which 9 are rated as ‘high’ and therefore above the Council’s risk tolerance thresholds. The risks falling within the ‘high’ category are listed in full at Appendix B.
3.4The project risk registers reveal that the Council has identified and assessed 102 project risks in total, of which 8 are rated as ‘high’ and therefore above the Council’s risk tolerance thresholds. The risks falling within the ‘high’ category are listed in full at Appendix C.
3.5A review of the Transformation Programme is underway to assess the impact of LGR on the projects. When this has been completed, a refresh of the project paperwork will be undertaken including the project risk registers.
3.6A new column has been added to every risk register to indicate whether and how the risk may be impacted by Local Government Reorganisation (LGR), and there is a dedicated LGR risk register in place.
4. Evaluation of Options
4.1There are no options to consider
5. How this report links to Corporate Priorities
5.1Risk Management impacts on all service areas and therefore links to each of the Council’s Corporate Plan aims.
6. Implications
6.1Community Safety including safeguarding and prevention of terrorism None
6.2Workforce None
6.3Equality and Diversity/Equality Impact Assessment This report has been prepared in accordance with the Council's Diversity and Equality Policies
6.4Financial Considerations Effective Risk Management contributes to financial objectives
6.5Legal None
6.6Climate Change and Sustainability None
6.7Conservation and Enhancement of Biodiversity None
6.8Consultation None 6.9 Risk Assessment The Council’s Risk Registers are a critical element in the Council’s Risk Management Framework.
ANDREW P STOKES Chief Executive
Background Papers Contact details Risk Registers Dec 2025 Tanya Cooper Head of OD & Transformation [email protected] Julie Nankivell Information Business Partner [email protected] 7. Background and Introduction
7.1The Council ensures that it undertakes a deliberate and systematic identification of the key risks that might prevent, degrade, delay or enhance the achievement of its objectives and priorities. The Council's Risk Management Strategy sets out the process for undertaking this on an ongoing basis.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
for Risk Management UpdateAppendix A | 112 KB | Download |
PDF |
for Risk Management UpdateAppendix B | 88 KB | Download |
PDF |
for Risk Management UpdateAppendix C | 71 KB | Download |
PDF |
for Risk Management UpdateAppendix D | 83 KB | Download |
PDF |
Risk Management UpdateReport | 211 KB | DownloadRead as text |
Follow Audit & Accounts Committee at High Peak and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 5 Jun 2026 | Minutes of the previous meetingThat the minutes of the meeting of the Audit and Accounts Committee held on 13 February 2026 be approved as a correct... | Approved | Open |
| 5 Jun 2026 | External Audit Plan - Grant Thornton. (TOR: External Audit 4)That the update be received. | Decided | Open |
| 5 Jun 2026 | Audit Committee Update - Grant Thornton. (TOR: External Audit 2)That the update be received. | Decided | Open |
| 5 Jun 2026 | Internal Audit Progress Report (TOR: Internal Audit 7)That the report be received. | Decided | Open |
| 5 Jun 2026 | Internal Audit Charter (TOR: Internal Audit 1)That the Internal Audit Charter be approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.