Noted Planning 1 paper

AI summaryHigh Peak Development Control Committee notes update sheet covering five applications, including revised descriptions for two lawful development certificates at Hargate Equestrian Centre.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedProcedural note of changes and clarifications
MoneyNot stated
What happens nextNMA decision neededBefore Milltown Way decision notice can issue
Who it affectsFive planning applicationsAcross Buxton, Glossop, Charlesworth, Milltown

What was decided

The committee noted the update sheet, which contained points of clarification and updates for five applications on the agenda. Report P3, P4, P25, P27, P38, P50

For the Brown Edge Road, Buxton application, the council recorded County Councillor Smith's comments supporting refusal or deferral pending further technical evidence on drainage, ground stability, ecology and infrastructure. Report P4, P9, P24

For the two Hargate Equestrian Centre applications, officers confirmed lawful development certificates would be granted under amended descriptions that reflect the evidence available, rather than the B8 storage use originally applied for. Report P29, P30, P31, P32, P33, P40, P41, P42, P43, P44

Why

On Brown Edge Road, the county councillor argued there is not enough up to date evidence on flood risk, hydraulic modelling, slope stability, ecological impact and Network Rail engagement to determine the application safely. Report P14, P15, P16, P17, P22, P23

On the Hargate Equestrian Centre applications, officers were not satisfied the evidence supported a certificate for the change of use to B8 storage originally applied for, so the recommended certificate covers a narrower description of operational development and storage use the evidence does support. Report P31, P32, P33, P42, P43, P44

What happens next

The decision notice for application HPK/2025/0461 at Milltown Way cannot be issued until the non-material amendment application NMA/2025/0031, which introduces phasing, has been determined. Report P50, P51, P52

The recommendation to grant a lawful development certificate under an amended description at Hargate Equestrian Centre can proceed without the applicant's agreement, although officers note it is advisable to seek it. Report P36, P47

Options considered

  • Rejected: Grant a lawful development certificate for the change of use to B8 storage and hardstanding (as originally applied for) at Hargate Equestrian Centre, application HPK/2025/0337. Officers were not satisfied the available evidence supports a certificate for the development as described Report P29, P30, P31
  • Chosen: Grant a lawful development certificate under the amended description covering hardstanding and modifications to the northern boundary at Hargate Equestrian Centre, application HPK/2025/0337. Reflects what the evidence shows Report P32, P33
  • Rejected: Grant a lawful development certificate for the change of use to B8 storage and hardstanding (as originally applied for) at Hargate Equestrian Centre, application HPK/2025/0339. Officers were not satisfied the available evidence supports a certificate for the development as described Report P40, P41, P42
  • Chosen: Grant a lawful development certificate under the amended description covering storage of caravans, motor homes and horse trailers and hardstanding at Hargate Equestrian Centre, application HPK/2025/0339. Reflects what the evidence shows Report P43, P44

Implications

  • Legal: Officers relied on Planning Practice Guidance to grant lawful development certificates under amended descriptions without requiring the applicant's agreement, although this is described as advisable rather than mandatory. Report P34, P35, P36, P45, P46, P47
  • Risk: On Brown Edge Road, the county councillor raised concerns that development on a sloping site with known clay soils and ground movement could pose risks to infrastructure, including the nearby railway, without updated technical evidence. Report P12, P13, P14, P15, P16
  • Other: Members were asked to determine the Brown Edge Road application without an updated Flood Risk Assessment, revised hydraulic modelling or a comprehensive slope stability assessment. Report P14
  • Other: The county councillor noted the Brown Edge Road site is unallocated, delivers limited public benefit and provides no affordable housing. Report P22

Who and where

  • The applicant and residents near Land off Brown Edge Road, Buxton (application HPK/2024/0496) Report P4, P13, P22
  • The applicant for Land South of The Heath, Glossop (application HPK/2025/0427) Report P25
  • The applicant and landowner at Hargate Equestrian Centre, Charlesworth (applications HPK/2025/0337 and HPK/2025/0339) Report P27, P38
  • The applicant and parties involved in the Milltown Way application (HPK/2025/0461), pending determination of NMA/2025/0031 Report P50, P51, P52
  • Network Rail, as a consultee on the Brown Edge Road application, with no updated comments before members Report P16

Timeline

  • 23rd February 2026: Date of the Development Control Committee update sheet Report P1, P2
  • When the NMA/2025/0031 decision is issued: Decision notice for HPK/2025/0461 at Milltown Way can then be issued Report P52

Plain English for the jargon

  • Lawful development certificate: A certificate issued by a local planning authority confirming that a proposed or existing use of land or operational development is lawful.
  • NMA (Non-Material Amendment): A minor change to an existing planning permission that does not materially alter it; here, used to introduce phasing to the Milltown Way consent HPK/2022/0317.
  • B8 storage use: A use class covering storage and distribution, including open air storage.
  • Nutrient neutrality: A requirement to ensure a development does not add to nutrient loads (such as nitrates or phosphates) affecting protected habitats.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item26/95

Resolved

That the update sheet be noted.
Word for word from the decision High Peak published for this meeting. Source: democracy.highpeak.gov.uk

Follow this further

Built from High Peak's papers

What the report saysPro

Report to Development Control Committee

23rd February 2026

HPBC DEVELOPMENT CONTROL COMMITTEE

UPDATES REPORT

HPK/2024/0496 – Land off Brown Edge Road, Buxton

Point of Clarification

Paragraph 7.7 of the report sets out the relevant part of LP Policy H1 that relates specifically to proposed housing development situated outside of the built-up area boundary. In order to comply with it a proposed development must not only comply with the 4 bullet points listed but also with the other policies in the local plan,

For the avoidance of doubt, the words “in principle” should follow the word countryside in the first sentence. The application is assessed against the Local Plan as a whole, as well as other material considerations which includes the Framework.

Updates

Comments from County Councillor Smith:

When determining this application, I believe the key question before us is a simple one: do we currently have enough reliable evidence to be confident that this development can proceed safely and sustainably?

In my view, that threshold has not yet been met.

This is a challenging site. The land slopes significantly toward the railway boundary, and historic assessments have already identified drainage and ground condition constraints. Earlier work concluded that conventional soakaway drainage was unlikely to be effective due to clay soils, meaning development would depend upon engineered drainage solutions and careful long-term management.

Having visited the site on several occasions, it becomes immediately apparent how substantial the level changes are. This is particularly evident when standing at the end of Brown Edge Close and looking across the site toward the railway, where the extent of the drop and the likely scale of earthworks required to facilitate development can be clearly appreciated. In my view, this reinforces that the proposal cannot reasonably be regarded as minor in physical impact, despite the relatively small number of dwellings proposed.

Members should also be aware that visible signs of movement can already be observed within boundary walls along properties on Brown Edge Road. While no technical conclusions are drawn from these observations alone, they reinforce the importance of securing comprehensive and up-to-date land stability evidence before development proceeds on this sloping site. However, Members are being asked to make a decision without an updated Flood Risk Assessment, without revised hydraulic modelling, and without a comprehensive slope stability assessment. Given the known interaction between water management and ground stability on steep sites, that absence of updated technical work is difficult to overlook.

British Geological Survey mapping identifies susceptibility to ground movement where subsurface water increases. That does not automatically prevent development, but it does place a responsibility on decision-makers to ensure risks are fully understood before permission is granted. Comparable nearby developments required detailed investigation before approval, and it is reasonable to expect the same level of evidence here.

The proximity of the railway adds an additional layer of sensitivity. Previous applications prompted detailed engagement from Network Rail regarding drainage control and land stability. Members do not currently have updated comments before them. I would simply caution that lack of a response should not be interpreted as confirmation that no issues exist, particularly where infrastructure safety may be affected.

Turning to ecology, I am conscious that additional wildlife evidence has been submitted after initial consultee responses were provided. Protected species legislation requires us to proceed on the basis of sound ecological information. Where credible evidence suggests bat activity and wider habitat use, it is important that the authority is satisfied all relevant information has been properly assessed before determination.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Update SheetReport 89 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

13 of 23 attended
RM
Councillor Robert McKeownChair, present
SE
Councillor Simon EvansVice-Chair, present
AB
Councillor Alan BarrowCommittee Member, present
CF
Councillor Charlotte FarrellCommittee Member, present
SG
Councillor Stewart GardnerCommittee Member, present
LG
Councillor Linda GroobyCommittee Member, apologies, sent representative
AH
Councillor Adrian HopkinsonCommittee Member, present
IH
Councillor Ian HuddlestoneCommittee Member, present
DL
Councillor David LomaxCommittee Member, apologies
PR
Councillor Peter RobertsCommittee Member, apologies, sent representative
GS
Councillor Gillian ScottCommittee Member, present
JT
Councillor Jean ToddCommittee Member, present

All 23 on the meeting page

On this subject at High Peak

Search all
  1. Update SheetThis decision
  2. Update SheetNoted
  3. Update SheetNoted
  4. Update SheetNoted
  5. Update SheetNoted
  6. Update SheetNoted

More from High Peak Development Control Committee

All decisions
MeetingDecisionOutcome
10 Aug 2026 Minutes of the previous meetingThat the minutes of the meeting held on 13 July 2026 be approved as a correct record. Approved Open
10 Aug 2026 Update SheetThat the update sheet be noted. Noted Open
10 Aug 2026 Planning ApplicationsThat the report be noted. Noted Open
10 Aug 2026 HPK/2026/0134 - The Natural Baths, The Crescent, BuxtonThat the application be approved as set out in the report, subject to the amended condition from DCC Archaeology as s... Approved Open
10 Aug 2026 HPK/2026/0184 - Buxton Opera House, Water Street, Buxton, DerbyshireThat Listed Building Consent be granted as set out in the report: 2. That in the event of any changes being needed to... Approved Open