Legacy Plan (2026 - 2028) and Refreshed Corporate Plan (2023-2028)

Approved Executive 4 papers

AI summaryHigh Peak Borough Council Cabinet recommends Full Council approves a Legacy Plan for 2026 to 2028 and adopts a refreshed Corporate Plan covering 2023 to 2028, to guide work until the new unitary structure starts on 1 April 2028.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedApprove Legacy Plan, adopt refreshed Corporate Plan, note Priority Actions
MoneyNo new sums approvedFunded from existing revenue, capital and reserves
What happens nextFull Council to considerAt its next meeting, then implement
Who it affectsCouncil staff and servicesUntil transition to new unitary council on 1 April 2028

What was decided

Cabinet agreed to recommend that Full Council approves the Legacy Plan 2026 to 2028, attached at Appendix A, which sets out priorities for work up to the new unitary structure. Report 2.1, 3.1

Cabinet agreed to recommend that Full Council adopts the refreshed Corporate Plan 2023 to 2028, attached at Appendix B, which updates the vision, aims, objectives and priority actions. Report 2.2, 3.5, 13.3, 13.4

Cabinet noted the Priority Actions by Portfolio Holder set out in Appendix C. Report 2.3, 3.6

Why

The plans focus the Council's work on the transition into a new unitary structure on 1 April 2028, after which the current Council will cease to exist. Report 3.1, 7.1

A review of the 43 Priority Actions from the Corporate Plan 2023 to 2027 has identified what can be achieved, accelerated, discontinued or added before reorganisation. Report 3.2, 8.1, P46

A Section 24 Direction from Government is expected to restrict the decisions the Council can make without the agreement of the emerging successor Council, so priorities need to be set now. Report 6.5, 9.2, 9.3

What happens next

Full Council will be asked to approve the Legacy Plan and adopt the refreshed Corporate Plan at its next meeting. Report 2.1, 2.2

A programme of resident and stakeholder engagement will follow approval, including through the website, exhibitions and community partners, and will be used to develop six Locality Plans. Report 6.8, P32, P33, 7.3, 10.8

Heads of Service will produce service plans to deliver the 25 objectives, progress will be monitored through the Performance Management Framework, and Overview and Scrutiny work programmes will be refreshed to focus on delivery. Report 13.6, 13.9, 13.11, 6.9

Options considered

  • Rejected: No alternative options. The report states there are no options to consider. Report 5.1, P18

Implications

  • Financial: Most Legacy Plan actions will be funded from existing revenue budgets, capital programme provisions and earmarked reserves. A small number of capital projects are at design stage where costs are not yet certain and may need further provision. Report 6.4, P27
  • Legal: A Section 24 Direction is expected to require written consent from the successor council for land or asset disposals over £100,000, capital contracts over £1,000,000 and non-capital contracts over £100,000 in whole life costs. Report 6.5, 9.2, 9.3
  • Staffing: There are significant workforce implications from the transition into the new unitary structures. Retention of staff through the transition is expected to be a significant challenge and an approach to deal with it has already been developed. Report 6.2, P21, P22, P23
  • Equalities: The report has been prepared in line with the Council's Diversity and Equality Policies. A full equality impact assessment will be undertaken alongside the refresh of the Corporate Plan. Report 6.3, P25
  • Climate: Delivery of the Climate Change Strategy and Action Plan is a commitment in the Legacy Plan and refreshed Corporate Plan, with focus on built Council assets and the vehicle fleet. Report 6.6
  • Other: Biodiversity Net Gain obligations under the Environment Act 2021 will continue to be met through the planning process, and the Council will support partners to generate BNG units on Council land. Report 6.7, P86
  • Other: Improved Community Safety is a priority outcome, and supporting the police in the prevention and detection of crime is one of the Council's influencing priorities. Report 6.1

Who and where

  • Council staff, including those in a shared workforce with High Peak Borough Council, who will transfer to new unitary councils Report 6.2, P21, P22
  • Residents, community partners and stakeholders who will be engaged on the Legacy Plan and Locality Plans Report 6.8, P32, P33, P34
  • Town and parish councils, who will be engaged in Locality Plans and neighbourhood governance arrangements Report 10.9, 10.13
  • Local businesses, including smaller enterprises affected by Biodiversity Net Gain requirements Report P86, P112
  • Private sector landlords and tenants, through a new Private Sector Housing Strategy and action on damp, mould and the Renter's Rights Act 2025 Report P75, P76

Timeline

  • December 2025: Communications Strategy and Cultural Strategy approved Report P57, P77
  • February 2026: Medium Term Financial Plan approved Report P27
  • 25th March 2026: Resources Overview and Scrutiny Panel considered the Legacy Plan Report 6.8, 12.1
  • 2026: Private Sector Housing Strategy to be developed Report P75
  • Later in 2026: Transfer of Local Land Charges function to HM Land Registry expected to go live Report P63
  • 1st April 2028: Transition into the new unitary structure Report 3.1, 3.5

Plain English for the jargon

  • LGR: Local Government Reorganisation, the process of restructuring councils into new unitary authorities
  • Section 24 Direction: A legal direction expected from Government after the Structural Changes Order, restricting the decisions the existing council can make without the agreement of the successor council
  • BNG: Biodiversity Net Gain, a requirement under the Environment Act 2021 that development must deliver measurable gains for biodiversity
  • PSDS: Public Sector Decarbonisation Scheme, a government grant programme for reducing carbon emissions from public sector buildings
  • ANPR: Automatic Number Plate Recognition, a camera-based system used in car parking enforcement
  • VCSE: Voluntary, Community and Social Enterprise organisations
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item52

Resolved

DECISION: 1. That Cabinet recommends that Full Council: 1.1 Approves the Legacy Plan as attached at Appendix A 1.2 Adopts the refreshed Corporate Plan 2023-2028 as attached at Appendix B 2. That Cabinet notes: 2.1 The Priority Actions by Portfolio Holder as detailed in Appendix C.
Word for word from the decision High Peak published for this meeting. Source: democracy.highpeak.gov.uk

Follow this further

Built from High Peak's papers

What the report saysPro

Report to Cabinet

Recommendations

Cabinet recommends that Full Council:

2.1Approves the Legacy Plan as attached at Appendix A

2.2Adopts the refreshed Corporate Plan 2023-2028 as attached at Appendix B

Cabinet notes:

2.3The Priority Actions by Portfolio Holder as detailed in Appendix C 3. Executive Summary

3.1The Legacy Plan 2026-2028 (attached at Appendix A) sets out the Council’s priorities for the work to be undertaken during the transition into the new unitary structure on 1st April 2028.

3.2The focus for the development of the Legacy Plan has been the delivery of the priorities set out in the Council’s Corporate Plan 2023-2027. The Priority Actions, agreed in 2023 (Annex 1 of the Legacy Plan), have been delivered through the Council’s Transformation Programme. There has been a comprehensive review of the progress with the delivery of the programme to inform the development of the Legacy Plan.

3.3The Legacy Plan has four themes:

• Growth • Service Improvement and Preparation for LGR • Efficiency • Locality

3.4The detailed Delivery Plan (Annex 2 of the Legacy Plan) sets out the following:

• Description of each Legacy Project • Summary of expected outcome by 31st March 2028 (narrative provided in the Plan) • Responsible Portfolio Holder • Responsible Executive Director • Lead Head of Service • Project reference

3.5A refreshed Corporate Plan 2023-2028 (attached at Appendix B) has been developed to reflect the commitments in the Legacy Plan. This sets out the ambitions and priorities of the Council up to 31st March 2028 when the authority will make the transition in to a new unitary structure.

3.6The refreshed Corporate Plan includes a reset of the Priority Actions that reflect the commitments in the Legacy Plan. Details of the Priority Actions by Portfolio Holder are set out in Appendix C.

4. How this report links to Corporate Priorities

4.1The Legacy Plan seeks to ensure that the priorities set out in the Corporate Plan 2023-2027 are achieved.

4.2Following development of the Legacy Plan the Corporate Plan has been refreshed to provide the focus for delivery of priorities through to 31st March 2028. 5. Alternative Options

5.1There are no options to consider.

6. Implications

6.1Community Safety - (Crime and Disorder Act 1998) Improved Community Safety is one of the Council’s priority outcomes. Supporting the police in the prevention and detection of crime is one of the influencing priorities.

6.2Workforce The Corporate Plan will provide the direction for the workforce by setting service objectives and priorities. These will inform the development of individual Service Plans which will form the basis of the employee appraisal scheme

There are significant workforce implications associated with the transition into the new unitary structures. This is more complex due to the shared workforce with High Peak Borough Council.

The LGR transition work will ensure that the transfer of staff to the new unitary councils is progressed effectively.

The retention of staff throughout the LGR transition period is expected to be a significant challenge and will need to be mitigated. An approach for dealing with this issue has already been developed

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix AAppendix A 623 KB Download
PDF
Appendix BAppendix B 1.2 MB Download
PDF
Appendix CAppendix C 116 KB Download
PDF
Legacy Plan (2026: 2028) and Refreshed Corporate Plan (2023-2028)Report 172 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 14 attended
MG
Councillor Mike GledhillChair, present
DP
Councillor Darren PriceVice-Chair, present
CA
Councillor Charlotte AtkinsCommittee Member, present
BC
Councillor Bill CawleyCommittee Member, present
DP
Councillor Dave ProudloveCommittee Member, present
MS
Councillor Matt SwindlehurstCommittee Member, present
CW
Councillor Chris WoodCommittee Member, apologies
NY
Councillor Nigel YatesCommittee Member, present
MD
Member Diary SMDCOfficer, expected
AS
Andrew StokesOfficer, expected
MO
Martin OwenOfficer, expected
AE
Anna EastgateOfficer, expected

All 14 on the meeting page

On this subject at High Peak

Search all
  1. Legacy Plan (2026 - 2028) and Refreshed Corporate Plan (2023-2028)This decision
  2. Cabinet - Legacy Plan (2026 – 2028) and Refreshed Corporate Plan (2023-2028)Approved
  3. Legacy Plan (2026 - 2028) and Refreshed Borough Plan (2023-2028)Approved
  4. Legacy PlanDecided

More from High Peak Cabinet

All decisions
MeetingDecisionOutcome
11 Aug 2026 Forward PlanDECISION: That the be approved for publication. Approved Open
11 Aug 2026 Climate and Nature Delivery Plan Update - Performance Report October 25 to April 26DECISION: That Cabinet approved the performance report set out in Appendix A. Approved Open
11 Aug 2026 Fourth Quarter - Finance, Procurement & Performance ReportsDECISION: 1. That the Fourth Quarter 2025/26 financial, procurement and performance position detailed in Appendices A... Noted Open
11 Aug 2026 Partial Review Staffordshire Moorlands Local PlanDECISION: 1. That the Staffordshire Moorlands Local Plan Partial Review be approved (attached at Appendix A) for a 6-... Approved Open
11 Aug 2026 Adoption of Market Guidance (Development Management)DECISION: That the Guidance attached at Appendix 1 of the report be approved for use by the Council’s Development Man... Approved Open