Resolved
RESOLVED – a supplementary budget of up to £50,000 to fund the Stamp Duty Land Tax for the Hinckley Squash and Rack Club development be approved.
Executive approved this item on Wednesday 4 March 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – a supplementary budget of up to £50,000 to fund the Stamp Duty Land Tax for the Hinckley Squash and Rack Club development be approved.
1.1To obtain formal approval of a supplementary budget required to fund the Stamp Duty Land Tax associated with build of the new squash facility for Hinckley Squash and Racket Club as endorsed by Council on 1st July 2014 (Agenda item 11).
2.1That Executive approves a supplementary budget of up to £50,000 to fund the Stamp Duty Land Tax (SDLT) due with regards to the Hinckley Squash and Racket Club development.
3. BACKGROUND TO THE REPORT
3.1Following Council approval on 1st July 2014, Hinckley and Bosworth Borough Council will fund the land acquisition and construction costs of a new squash facility for Hinckley Squash and Rackets Club (HSRC). The cost of this scheme will be financed by the Compulsory Purchase Order (CPO) payments due to HSRC for moving from their current site as well as £110,000 of HSRC’s own cash. In both cases, the funds have been passed to Hinckley and Bosworth Borough Council to expend and therefore the scheme is included as fully funded in the Programme.
3.2The contracts for the transaction (Heads of Terms) were signed by all parties on 14th November 2014. The scheme has a 40 week build programme and is expected to be completed by summer 2015. On completion the Council will grant a 125 year peppercorn lease to the HSRC, after which the land and building will be transferred to HSRC for a nominal sum.
3.3The arrangement for build and subsequent lease of the new development will mean that the lease to be granted to Hinckley Squash and Racket Club (HS&RC) will be liable for Stamp Duty Land Tax (SDLT). As part of the Heads of Terms, Hinckley and Bosworth Borough Council agreed to fund these costs up to a maximum of £50,000. These costs would be met from the VAT that was saved as a result of Hinckley and Bosworth Borough Council spending Compulsory Purchase Order (CPO) monies on behalf of HS&RC.
3.4The point above was endorsed by Council in the report dated 1st July 2014 with the intention that a supplementary budget would be sought once the agreements were signed.
3.5On this basis, it is requested that a supplementary budget of up to £50,000 be approved to fund the cost of the SDLT upon grant of lease. Currently, and based on build cost, this liability is estimated to be £39,465.
4. FINANCIAL IMPLICATIONS [KP]
4.1The supplementary budget will be financed from the General Fund, through the mechanisms of the VAT reclaim (Revenue Contributions to Capital Outlay).
4.2All supplementary budgets between £25,001 - £50,000 must be approved by Executive as outlined in Financial Procedure Rules. 5. LEGAL IMPLICATIONS [EH]
5.1The legal liability with HMRC for payment of the SDLT will rest with HS&RC however the council is contractually obliged, under the agreement for lease, to cover the SDLT as set out in the body of the report. This is in addition to the SDLT payment due on the purchase of the freehold of the site.
6. CORPORATE PLAN IMPLICATIONS
6.1This scheme supports the Corporate Plan objective for regenerating the economy and improving physical activity of residents in the Borough.
7.1Not applicable
8.1It is the Council’s policy to proactively identify and manage significant risks which may prevent delivery of business objectives.
8.2It is not possible to eliminate or manage all risks all of the time and risks will remain which have not been identified. However, it is the officer’s opinion based on the information available, that the significant risks associated with this decision / project have been identified, assessed and that controls are in place to manage them effectively.
8.3The following significant risks associated with this report / decisions were identified from this assessment:
Management of significant (Net Red) Risks Risk Description Mitigating actions Owner None
9. KNOWING YOUR COMMUNITY – EQUALITY AND RURAL IMPLICATIONS
9.1This scheme will assist in ensuring services are accessible to the general public.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Squash Club SDLT supplementary budgetSupplementary | 2 pages | DownloadRead as text |
Follow Executive at Hinckley and Bosworth and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Sep 2026 | Future Ready Council StrategyRESOLVED – The Executive: (i) Endorsed the 2026–2028, attached as Appendix A. (ii) Supported the development of a del... | Decided | Open |
| 23 Sep 2026 | Housing Services - Landlord Property Safety and ComplianceRESOLVED – The Executive: (i) approved the Landlord Property Safety and Compliance Policy 2026. (ii) Noted the streng... | Approved | Open |
| 23 Sep 2026 | Cyber Security StrategyRESOLVED - (i) Members approved the strategy. (ii) The positive work undertaken by the ICT Service to date was noted. | Approved | Open |
| 29 Jul 2026 | Tenant satisfaction measures and tenant engagement updateRESOLVED – The Executive: (i) Noted the tenant engagement activity undertaken during 2025/26; (ii) Acknowledged the i... | Noted | Open |
| 29 Jul 2026 | Fraud StrategyRESOLVED – The Executive: (i) Considered and approved the Fraud Management Strategy & Action Plan; (ii) Noted that of... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.