Resolved
RESOLVED – the allocation of funding be endorsed.
Scrutiny Commission decided this item on Wednesday 28 March 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – the allocation of funding be endorsed.
1.1To request Scrutiny Commission endorses the allocation of funding from the Developing Communities Fund to the Burbage project.
2.1That Scrutiny Commission endorses the funding allocations identified in section 4 of the report through the Developing Communities Fund subject to condition outlined in 4.6
3. BACKGROUND TO THE REPORT
3.1The implementation of the Developing Communities Fund was agreed at Council, 21 March 2017. The fund was introduced to:- support parishes and communities wanting to deliver locally important and ambitious schemes; build on the success of the Parish and Community Initiative Fund; and provide support for larger projects in areas where there is (or is anticipated to be) considerable population / employment growth.
The Director (Environment and Planning) has delegated authority to implement the fund in consultation with the Executive Lead for Rural Communities and the Executive Lead for Town Centres.
3.2All parishes were written to and expressions of interest submitted in December 2016. From these, seven schemes were identified as potentially suitable for funding and were invited to submit an application for funding by 1 June 2017.
3.3Governance arrangements are that:- each project will be assessed by two assessors from the Project Team, with further support from Finance, Legal, Planning and Nigel Butler; Project Board considers assessors recommendations and confirms which grants should be recommended to SLT for approval;
06/16 Project Board membership is Councillor Ladkin, Councillor Morell, Rob Parkinson and Caroline Roffey; Scrutiny Commission are consulted on the recommended grants; and SLT agree funding amounts.
3.4Project Team assessors were identified for each scheme and a full assessment has now been completed for: Burbage Parish Council: Extension to the Millennium Hall and Building the Pavilion (Assessors: Simon Jones and Malcolm Evans)
4.0OVERVIEW OF PROJECT
4.1Burbage Parish Council has been considering extending the Millennium Hall for many years following a consultation carried out during 2012. Burbage Parish Council employed a company called “Focus Consultants” to work with them to provide evidence to inform the parish council if it was financially viable for them to extend and refurbish the existing hall. The Consultants provided an analysis document which has confirmed the potential demand for the extension of the Millennium Hall and the additional activities that could be delivered.
The building is currently used for numerous activities and our rooms are occupied to almost full capacity. The rooms within the building are used by all ages, for fitness, crafts, social gatherings, adult learning classes, volunteer and authority organised holiday clubs. It is also used as a polling Station, for party bookings, dog training and at the moment sports changing facilities and toilets are included on site.
Population growth within the village continues at a pace therefore there is an increasing demand for more facilities.
4.2To deliver this enhanced provision an extension to the Millennium Hall will necessitate the need to re-model the interior of the existing building and to provide an additional separate facility for called “The Pavilion”. The Pavilion is a necessity to ensure the continued use of sporting activities in the village to allow the creation of new activities to take place on the Britannia Road Recreation Ground which adjoins the Millennium Hall.
4.3Project Costs: The overall project budget is £978,375.
£426,368 Public Works Board loan £58,907 Existing developer contributions £143,100 Parish Council funds
£628,375 Sub contribution total via Burbage Parish Council
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Developing Communities Fund: Burbage Parish CouncilReport | 5 pages | DownloadRead as text |
Follow Scrutiny Commission at Hinckley and Bosworth and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Oct 2026 | Scrutiny Commission Work ProgrammeRESOLVED – (i) The additional review item into the adoption of public open space associated with housing developments... | Approved | Open |
| 22 Oct 2026 | Review of the council's constitutionRESOLVED - Council be recommended to approve the constitutional amendments as set out within the report. | Approved | Open |
| 22 Oct 2026 | Budget planRESOLVED - members noted the Budget Plan for 2027/2028. | Noted | Open |
| 22 Oct 2026 | Homelessness and rough sleeping strategy / local plan to end homelessness 2026-2029RESOLVED – The Scrutiny Commission: (i) Noted the progress made in developing the Homelessness and Rough Sleeping Str... | Noted | Open |
| 22 Oct 2026 | Rough Sleeping programme allocation 2026/27RESOLVED – The Scrutiny Commission recommended to Council that it approves acceptance of the £100,524 allocation, est... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.