Resolved
RESOLVED – The use of the DCF reserve of £120,000 to allocate to the Market Bosworth road improvement scheme be approved, along with creation of related expenditure budgets.
Council approved this item on Tuesday 3 October 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – The use of the DCF reserve of £120,000 to allocate to the Market Bosworth road improvement scheme be approved, along with creation of related expenditure budgets.
1.1To seek Council approval to allocate the balance of the Developing Communities Fund (DCF) to a project in Market Bosworth that will improve road safety, enhance tourism opportunities and support local businesses.
2.1That Council approves:
Use of the Developing Communities Fund reserve of £120,000 to be allocated to the Market Bosworth road improvement scheme, as detailed in sections 4 and 6 of this report;
Setting up of expenditure budgets to use the remaining DCF reserve on the Market Bosworth road improvement scheme, as detailed in sections 4 and 6 of this report.
3. Background to the report
3.1The implementation of the Developing Communities Fund was agreed at Council, 21 March 2017 and reviewed for DCFII on 27 November 2018. The fund was introduced to:
support parishes and communities wanting to deliver locally important and ambitious schemes build on the success of the Parish and Community Initiative Fund provide support for larger projects in areas where there is (or is anticipated to be) considerable population / employment growth.
3.212 schemes located in rural areas were supported and have been delivered.
3.3One of the 12 schemes was Market Bosworth Town Square Redevelopment.
DCF 1 Phase 1 was approved for expenditure of up to £27,600 for the development of the feasibility of the scheme for the redevelopment the town square including public consultation.
The consultation was very positively received with 85% of the public supportive of the plans.
Subsequently, DCF 2 Phase II was approved which saw the further development of the scheme to enable it to be ready for any external funding opportunities that may present themselves. The term ‘shovel ready project’ is sometimes used.
Phase II requires funding of £63,135 as a 69% contribution towards the identified costs of £91,500. The Parish Council aligned £28,365 within their budget to support phase 2 (31%).
3.4The original proposed scheme broadly consists of the introduction of a one- way system, 20mph speed limit, changes to parking arrangements and a range of hard and soft landscaping changes to create a safer and more attractive village centre.
3.5As the Highways Authority, Leicestershire County Council (LCC) led on this work.
3.6A programme of works was provided by the County Council outlining when each task associated with phase 2 would be completed. The programme was due to commence early 2020, however due to the COVID-19 outbreak and subsequent “lockdowns” initiated by Central Government throughout 2020 and 2021, it was not possible to start these works until June 2021.
3.7The overall refined estimated costs incorporating all the works ranged from £2M to more than £4M. This considered the supply of materials, labour and a large sum allocated towards contingency and inflationary costs.
4. Proposal and funding request
4.1Clearly the overall cost estimate to deliver the overarching public realm scheme and associated highway improvements is not insignificant and as such it is likely to be highly challenging in being able to achieve a successful bid outcome for the full funding ask.
4.2Following a series of clarification meetings with LCC, HBBC and Market Bosworth Parish Council representatives the County Council advised that the associated highway improvements could be delivered as a holistic highway improvement scheme. In doing so the parish councils safety objectives could still be met, but minus the aspirational public realm landscaping materials. Doing so would not dilute the overarching public realm scheme concept and in essence would future proof its implementation when wider funding becomes available.
4.3The proposal consists of 3 elements:
A) Rectory Lane/Sutton Lane – Change of Junction Priority
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
DCF appendixAppendix | 3 pages | Download |
PDF |
Developing Communities Fund: Market BosworthReport | 5 pages | DownloadRead as text |
Follow Council at Hinckley and Bosworth and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 27 Oct 2026 | Minutes of the previous meetingRESOLVED – the minutes of the meeting held on 29 September be approved. | Approved | Open |
| 27 Oct 2026 | Review of the council's constitutionRESOLVED – the changes to the constitution be approved. | Approved | Open |
| 27 Oct 2026 | Community Governance Review - Witherley - final recommendationsRESOLVED – (i) The current parish of Witherley and Witherley Parish Council be abolished; (ii) Fenny Drayton parish a... | Decided | Open |
| 29 Sep 2026 | Minutes of the previous meetingsRESOLVED – the minutes of the meetings held on 23 July and 4 August 2026 be confirmed as a correct record. | Decided | Open |
| 29 Sep 2026 | Local authority housing fund - round 4RESOLVED – (i) Participation in the local authority housing fund round 4, including the acquisition of six residentia... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.