Resolved
The Board agreed the following: Methodology to be amended to refer to the Gunnersbury Park Regeneration Board rather ... view the full minutes text for item 17.
Gunnersbury Park Joint Advisory Panel agreed this item on Monday 5 January 2009. Below is the council's own wording, with the papers it was decided on.
Resolved
The Board agreed the following: Methodology to be amended to refer to the Gunnersbury Park Regeneration Board rather ... view the full minutes text for item 17.
Gunnersbury Park Regeneration Board Board Paper 5 January 2009
------------------------------------------------------------------------------------------------------------
Proposed Methodology for Options Appraisal
Summary and Recommendations This report sets out a detailed methodology for the Options Appraisal to be undertaken by Jura Consultants including the critical role the board will play in progressing the Options Appraisal. Board members should note the report and in particular the following recommendations:
It is proposed that the Regeneration board undertake the decision-making role of ‘stakeholder workshop’ inviting other key stakeholders if appropriate.
It is proposed that the stakeholder workshop agree a shortlist of options at an additional meeting of the board (either Thursday 22 or 29 January.)
It is proposed that the stakeholder workshop agree the ranking of options and confirm the preferred option on Thursday 26 February or a special meeting of the board on 5 March.
It is recommended that a programme of public consultation is initiated after the second stakeholder workshop 26 February or 5 March.
The completion of this report may require a recommendation to be made at the Board meeting of 2 April to the two Executive bodies of each Council depending on what actions are being proposed in order to progress this project further.
1. Background 1.1 The Conservation Management Plan (CMP) completed earlier this year confirmed the significance of Gunnersbury and identified the issues facing the estate. It is clear that intervention is required to prevent the continued decline in value of the estate. But the CMP does not indicate what that intervention might be.
1.2A development programme is required for the estate which identifies both a clear masterplan and a number of objectives designed to achieve it. This masterplan will form the basis for discussions with possible future partnerships and applications to Heritage Lottery Fund (HLF) and other grant awarding bodies. The masterplan will be arrived at through an Options Appraisal which reflects the guidance of HM Treasury Green Book.
1.3An Options Appraisal is the process of defining objectives, examining options, and weighing up the costs, benefits, risks and uncertainties of those options to determine the best solution for a project.
Reports: Gunnersbury proposed method for ops apprais 1.4 The Green Book is a Government best practice guide aiming to make the appraisal process more consistent and transparent.
1.5Jura consultants have been appointed to undertake the options appraisal for Gunnersbury Park Estate. They are specialist consultants in the cultural heritage sector with a track record in bringing Heritage assets back into use, frequently co-coordinating applications to the HLF.
1.6The project needs to balance the economics required to make the estate sustainable against the fact that the estate is a significant heritage asset easily damaged by inappropriate development. Jura have recognized this by teaming up with LDN Architects a firm with appropriate, accredited conservation expertise and experience, and Montagu Evans a property management consultant.
1.7A methodology has been developed for undertaking the appraisal. An initial phase will establish basic evidence and confirm objectives. A second phase will develop a series of options which can be ranked against agreed criteria. The final phase will clearly communicate conclusions and recommendations including a preferred option with a detailed analysis and masterplan.
2. Initial Phase 2.1 The preliminary step will involve research to set out the scope of the project and the reasons for intervention. Although much of this is covered by the CMP Jura need to thoroughly understand the current situation and the results of not intervening before moving to intervention options and their associated costs and benefits.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Gunnersbury proposed method for ops appraisReport | 35 KB | DownloadRead as text |
PDF |
Proposed Methodology for Options Appraisal and Proposed Programme for Options AppraisalReport | 70 KB | Download |
Follow Gunnersbury Park Joint Advisory Panel at Hounslow and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 7 Jul 2017 | Heritage Progress ReportThe submitted report was noted. | Noted | Open |
| 7 Jul 2017 | Sports Progress ReportResolved : The submitted report was noted. | Noted | Open |
| 28 Apr 2017 | Dates of future meetingsIt was agreed to move the July 21 date forward to 7 July 2017. James Wisdom submitted apologies for the new date and ... | Agreed | Open |
| 18 Nov 2016 | Presentation on Sports HubIt was agreed that revised images would be circulated the following week to members of the Panel, as well as to other... | Agreed | Open |
| 21 Oct 2016 | Update on Park Events Licence ProposalIt was agreed to arrange an additional meeting with appropriate officers attending to discuss the licensing policy. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.