Award of contract for the design and build of a new playground in St Pauls Recreation Ground
AgreedExecutive1 paper
Executive Member Delegated Decision agreed this item on Thursday 20 January 2011. Below is the council's own wording, with the papers it was decided on.
The Lead Executive Member agreed the recommendations in the report as follows: That following a competitive tender the contract for the design and build of a new playground in St Paul’s Recreation Ground is awarded to Proludic . The total contract is £157,999. That in addition to the contract sum an allowance of £15,000 is made to cover fees and contingency events. That due to the nature of the project and the fact that it will cross financial years, the balance of any sum unspent for this financial year is set aside in an earmarked reserve from which the remaining costs can be met in 2011/12.
Word for word from the decision Hounslow published for this meeting.Source: democraticservices.hounslow.gov.uk
1.1Officers recommend that following a competitive tender the contract for the design and build of a new playground in St. Pauls Recreation Ground is awarded to Proludic. The total contract sum is £157,999.
1.2In addition to the contract sum officers are also recommending that an allowance of £15,000 is made to cover fees and contingency events.
1.3Due to the nature of the project and the fact that it will cross financial years we recommend that the balance of any sum unspent for this financial year is set aside in an earmarked reserve from which the remaining costs can be met in 2011/12.
Background
2.1On the 14th July 2009 the Executive agreed to prioritise the growth allocated to leisure to improve the parks and open spaces. St. Pauls Recreation Ground was one of the main parks identified and this project will significantly enhance the play provision within the area for local people to enjoy. 2.2 Very few of our existing playgrounds offer disability access and most have very poor play value. In general equipment is not integrated into the natural landscape and consideration has generally not been given for the need for seating or shade.
2.3This project is to renovate the old playground and to design and build/install a new playground ground that aims to achieve a RoSPA (Royal Society for Prevention of Accidents) 5 star design award for design and accessibility in its place.
2.4The new playground will cater for children of the age range of 0-13 years of age and is landscaped and laid out in a way that integrates the play area into the park. The playground will be expanded to encompass a larger area and therefore allow greater use.
3. DISCUSSION
3.1Five companies were invited to tender for the above works for a fixed price contract of £158,000. The tender period closed on the 15th October 2010 and five tenders were received by the closing date.
3.2The tenders were evaluated by a small panel of officers against the following quality criteria and weighting. A maximum of 100 points were available.
Award Criteria Weighting The price and overall benefit of the contract to the 10 Council Evaluations of the layout plan/proposed design of 70 the playground and the proposed playground equipment.
A self assessment against the RoSPA 5 star design Criteria must be completed and attached with the tender, to assist the panel evaluation criteria.
The Contractors Proposals submission considering 20 building work specifications, play equipment specifications, method statements, etc.
Total Evaluation 100
3.3The panel awarded Proludic a score of 60 points. This was significantly higher than the other tenders received. The other scores are detailed below for information. A more detailed breakdown of the scores is provided in Appendix A. Company A 54 points Company C 51 points Company D 50 points Company E 42 points
3.4Discussion with our planning team suggests that Proludic’s design will not require planning permission.
3.5The Director of Finance has agreed that this work can be met from this year’s revenue budget.
4. COMMENTS OF THE DIRECTOR OF FINANCE
4.1This programme of works will cross over two financial years then it is therefore proposed that the balance of the sum approved that is unspent in this financial year will be set aside an earmarked reserve from which the remaining approved costs can be met in 2011/12. If this is not possible, then the unspent costs will need to be met from the budget approved for 2011-12.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Rainbow Project - Additional FundingThe Leader of the Council approved the provision on an additional £100,000 from HRA reserves to the Rainbow project, ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.