Child and Adolescent Mental Health Services (CAMHs) Tier 2 - Contract Award

Approved Executive 1 paper

AI summaryCabinet approved a direct award to West London NHS Trust to run Child and Adolescent Mental Health Services Tier 2 in Hounslow from 1 April 2026 for three years, with a possible two-year extension, at £618,354 a year.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedWest London NHS Trust to deliver CAMHs Tier 2
Money£618,354 per year, £3,091,770 totalThree year term plus optional two year extension
What happens nextContract starts 1 April 2026Commissioning team to manage the contract
Who it affectsChildren and young people in HounslowTwo service elements: Early Intervention and SISP

What was decided

Cabinet approved the direct award of a CAMHs contract to West London NHS Trust for 1 April 2026 to 31 March 2029, with an optional two-year extension to 31 March 2031. Report 6.1

The contract will be awarded under Direct Award C of the Health Care Services Provider Selection Regime 2023, with a transparency notice to follow. Report 7.2

Why

The existing provider is delivering the contract to a satisfactory standard and the new contract is not materially different, so the Provider Selection Regime permits a direct award. Report 7.2

West London NHS Trust has agreed that inflationary increases will not apply during the initial three-year term, producing estimated avoided inflationary costs of £41,716, rising to a maximum of £71,078 if the extension is used. Report 6.2, 11.1, 13.2

The service aligns with the council's Corporate Plan, Equality, Diversity and Inclusion Strategy, Children and Young People's Plan and Health and Wellbeing Strategy 2023-26, all of which prioritise early mental health support for children and young people. Report 8.1, P12, P13, P14, P15

What happens next

The council's Commissioning Team will take on implementation and ongoing contract management, and will work with service leads to develop a workplan and Key Performance Indicators for an annual performance report. Report 12.1, 12.2

A transparency notice of the award will be published to comply with the Provider Selection Regime, and negotiations to maintain current values will begin in year three. Report 11.1

The money

  • £618,354 Annual contract value Report 6.1
  • 3,091,770 Total potential lifetime contract value over five years
  • £496,666 Annual budget for the Early Intervention Team element Report 6.1
  • £121,688 Annual budget for the Specialist Intensive Support Programme element Report 6.1
  • £41,716 Estimated avoided inflationary cost over the initial three-year term Report 6.2, 13.2, P6
  • £71,078 Maximum avoided inflationary cost if the two-year extension is exercised Report 6.2, 13.2, P7
  • £625k General funded budget available from 2026/27, made up of £504k Children's Commissioning and £121k Children's Social Care Report 13.1

Options considered

  • Chosen: Direct award of a three-year contract with optional two-year extension to West London NHS Trust under Provider Selection Regime Direct Award C. Existing provider is performing satisfactorily, new contract is not materially different, and the trust has agreed no inflationary uplifts during the initial term Report 7.2, 11.1

Implications

  • Financial: No inflationary increase will apply during the initial three-year term, avoiding an estimated £41,716 of inflationary cost and up to £71,078 over the full five-year term. Report 6.2, 11.1, 13.2
  • Legal: The award uses Direct Award C of the Health Care Services Provider Selection Regime 2023 and requires publication of an award notice for transparency. Report 7.1, 7.2
  • Equalities: The service supports council equality priorities around mental health support for people with disabilities and for LGBT+ young people. Report P12, 8.1
  • Climate: The contract will include the council's net zero and climate change clauses, and West London NHS Trust has a Sustainable Travel Plan 2025-28 to cut environmental and air pollution impact. Report 9.1, 9.2
  • Risk: A break clause applies at the end of year three, and the Chief Financial Officer flags that effective contract management will be needed to keep costs within budget and maintain quality. Report 13.2, 13.3
  • Other: Commissioning and oversight will need to reflect the North West London Integrated Care System's Mental Health Strategy and alignment with the THRIVE Framework. Report 10.1, P21

Who and where

  • Children and young people in Hounslow using CAMHs Tier 2 services Report 6.1, 8.1
  • West London NHS Trust as the contracted provider Report 9.2
  • London Borough of Hounslow Commissioning Team, which will manage the contract Report 12.1
  • Hounslow's Youth Counselling Service partner mentioned in the Children and Young People's Plan Report P14

Timeline

  • 1 April 2026: Contract start date for the initial three-year term
  • 31 March 2029: End of the initial three-year contract term
  • 31 March 2031: Latest possible end date if the two-year extension is exercised
  • Year 3 of the contract: Negotiations begin with the provider to maintain current annual values where possible Report 11.1

Plain English for the jargon

  • CAMHs Tier 2: Targeted Child and Adolescent Mental Health Services, sitting between universal support and specialist Tier 3 services
  • EIT: Early Intervention Team, the part of the service with an annual budget of £496,666
  • SISP: Specialist Intensive Support Programme, the part of the service with an annual budget of £121,688
  • Provider Selection Regime: The Health Care Services Provider Selection Regime 2023, the rules governing procurement of certain health services by the council
  • Direct Award C: A route under the Provider Selection Regime that allows award to an existing provider where performance is satisfactory and the new contract is not materially different
  • THRIVE Framework: A model for organising mental health services around the needs of children and young people, referenced in the North West London Mental Health Strategy
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8

Resolved

Resolved : · Cabinet approved the direct award of a contract to West London NHS Trust for the delivery of a Child and Adolescent Mental Health Service, for the period 1st April 2026 to 31st March 2029, with an optional 2-year extension to 31st March 2031, at an annual contract value of £618,354 and a total potential lifetime value of 3,091,770.
Word for word from the decision Hounslow published for this meeting. Source: democraticservices.hounslow.gov.uk

Follow this further

Built from Hounslow's papers

What the report saysPro

Report to Cabinet, 8 pages

Report for: ACTION

Contains Confidential N or Exempt Information

Cabinet Key Decision Y

Award of Contract to West London NHS Trust for Child and Report Title Adolescent Mental Health Services

Councillor Samia Chaudhary, Portfolio holder for Education, Member Reporting Children, Skills & Employment

Will Parsons, Contact Details [email protected]

For Consideration By Cabinet

Date to be Considered Tuesday, 10th February 2026

Deadline for call-in Wednesday, 18th February 2026

Implementation Date Thursday, 19th February 2026 (if not Called In) (actual implementation expected 1st April 2026)

Affected Wards (All Wards); Martin Waddington, Director ICP and Commissioning Approved by [email protected] 1. Recommendations

Cabinet is asked to:

1. Approve the direct award of a contract to West London NHS Trust for the delivery of a Child and Adolescent Mental Health Service, for the period 1st April 2026 to 31st March 2029, with an optional 2-year extension to 31st March 2031, at an annual contract value of £618,354 and a total potential lifetime value of 3,091,770.

2. Report Summary

a. This report summarises the direct award of a contract to West London NHS Trust from 1st April 2026 for Child and Adolescent Mental Health Services, also referred to as Tier 2 CAMHS services.

b. These services provide an early intervention offer for Hounslow’s Children and Young People (CYP) to support them with their mental health and aims to prevent escalations of mental health related issues into high-cost hospital services such as Accident and Emergency (A&E) and or crisis support.

c. In addition to this, these services also provide expert recommendations from psychologists which support the care proceedings process whilst also undertaking direct work with families that have had children taken into the care system.

d. The direct award of this contract will enable continuation of service provision and is compliant with relevant Procurement Regulations, specifically, Direct Award C of the Provider Selection Regime, ‘where an existing provider is satisfying its contract and the new contract will not be materially different from the current contract’.

3. Background and links to Corporate Priorities

3.1This service aligns with the London Borough of Hounslow’s (LBH) Corporate Plan 2022-2026 and the Children and Young People’s Plan, to improve mental health services for the children in Hounslow through joint work with our partners across our Integrated Care System. The Corporate Plan notes, under the heading, Healthier Hounslow:

• Intervene early to support children’s mental wellbeing and prevent crisis.

3.2In addition to this, the Children and Young People’s Plan notes that we will help young people develop mental wellbeing through:

• Providing group interventions in school to help children develop coping mechanisms for dealing with stress and anxiety. • Working with Hounslow’s Youth Counselling Service to ensure that one to one self-referred counselling is available and accessible to young people.

• Offer universal wellbeing support through mental health support teams in schools.

4 Proposal and Rationale

4.1The recommendation to commission directly from West London NHS Trust enables continuity and consistency in early mental health provision for children and young people (CYP) in Hounslow. This includes support for vulnerable looked-after children, young offenders, and families requiring specialist intensive help. Without these services, mental health issues amongst Children and Young People may escalate to crisis levels, potentially leading to hospital admissions or the need for higher-threshold services. Additionally, without an early intervention offer, there is an increased risk of needs escalating and the requirement for costly social care placements being needed to support children.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Child and Adolescent Mental Health Services (CAMHs) Tier 2: Contract AwardReport 8 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Hounslow

Search all
  1. Child and Adolescent Mental Health Services (CAMHs) Tier 2 - Contract AwardThis decision
  2. Update on Child and Adolescent Mental Health Services (CAMHS) - Review 2009-10Noted
  3. Child & Adolescent Mental Health Services - Review ReportAgreed

More from Hounslow Cabinet

All decisions
MeetingDecisionOutcome
14 Jul 2026 Budget Outturn 2025-2026Resolved : Cabinet agreed to the following: General Fund 1. Approve the General Fund net revenue o verspend of £1.6m ... Agreed Open
14 Jul 2026 Delivery Plan Monitoring - Q4 2025/26Resolved : Cabinet agreed to: 1. Note progress to date with the programmes within the People Portfolio as set out in ... Agreed Open
14 Jul 2026 Quarterly Performance Reporting 2025-2026 (Q4)Resolved : Cabinet noted the corporate performance report for Quarter 4 (January to March 2026) detailed in Appendix ... Noted Open
14 Jul 2026 Procurement Plan - July 2026Resolved : Cabinet approved the following: 1. Specialist Support and Therapies services: a) Approve commencement of p... Approved Open
14 Jul 2026 Updated West London Waste Plan - Regulation 19 Consultation and Submission to Secretary of State for ExaminationResolved : Cabinet recommended to Borough Council: 1. To approve the ‘Regulation 19’ publication of the Proposed Subm... Approved Open