The Cabinet agreed the recommendations of the report as follows: The Cabinet authorised the Director of Environment to prepare and submit a planning application for a new Marina development adjoining Waterman’s Park based on option 2 as detailed in the report. The Cabinet authorised the Director of Environment to open negotiations with the Port of London Authority (PLA) with a view to forming a development partnership to develop the new marina and to report back on the outcome. The Cabinet recommended to the Leader of the Council the use of the Leader’s Performance Fund to finance the negotiation of the development agreement as set out in the report. The Cabinet agreed the recommendations of the report as follows: The Cabinet authorised the Director of Environment to prepare and submit a planning application for a new Marina development adjoining Waterman’s Park based on option 2 as detailed in the report. The Cabinet authorised the Director of Environment to open negotiations with the Port of London Authority (PLA) with a view to forming a development partnership to develop the new marina and to report back on the outcome. The Cabinet recommended to the Leader of the Council the use of the Leader’s Performance Fund to finance the negotiation of the development agreement as set out in the report.
Word for word from the decision Hounslow published for this meeting.Source: democraticservices.hounslow.gov.uk
This report sets out the results of the viability study in relation to the provision of a new Marina adjoining Waterman’s park in Brentford. The report asks Cabinet to consider and agree the way forward.
Background
2.1At the meeting on 9th November 2010 Cabinet agreed that a viability study be undertaken into the possibility of creating a new Marina adjoining Waterman’s park.
2.2Accordingly, consultants Frankham’s were appointed to prepare possible schemes for a Marina and to discuss those with various agencies involved including the PLA, the Environment Agency with the Council’s planning department. These options would then be tested by Frankhams for financial viability.
-1- 3.0 Viability Report
3.1The outcome of those investigations and discussions and options appraisals are contained in the confidential report (appendix A). The two options outlined in the report are in effect the minimum and maximum potential development that would produce a positive return. Clearly option 2 is potentially the most viable and if Members wish to pursue the proposal to develop a new Marina then it is recommended that this option form the basis of a planning application and subsequent development.
3.2Clearly there is considerable amount of work to be done to turn that option into an acceptable development and further discussions will be needed with all the agencies concerned in the normal way as part of submitting a planning application for the development.
3.3Therefore, if Members wish to pursue this option then the next step would be to instruct Frankhams to prepare a detailed planning application in the usual way. If this was unsuccessful then development could not proceed but if it were successful then legal action would be necessary to remove all the current unlicensed boats from the site to enable construction work to commence.
3.4Whether or not any of the current unlicensed occupiers then return as a proper licensed occupier will have to be determined nearer the time.
4.0Development Partnership
4.1As can be seen from the attached report the PLA is responsible for issuing licences for such developments and is in the process of changing how it issues such licences and the anticipated outcome of those changes has been taken into account in the report.
4.2The proposed changes lend themselves to a position where the Council and the PLA could join together in a partnership to deliver a new development subject to the outcome receipt of planning consent.
4.3The PLA have indicated that in principle they would be very interested in entering into a partnership with the Council as they see the resolution of the long-standing problems at Waterman’s Park to be a key priority for them and it was also fit in with their new approach.
4.4Such a partnership would have distinct advantages for the Council as well, as any development can’t be done without the agreement or support of the PLA. Furthermore, a partnership would reduce the financial risk to the Council.
4.5As can be seen from the report, financial viability looks very robust and could potentially deliver to the Council a significant return whilst
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Delivery Plan Monitoring - Q4 2025/26Resolved : Cabinet agreed to: 1. Note progress to date with the programmes within the People Portfolio as set out in ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.