Procurement of Integrated Transport Information System for West London Alliance (WLA) Transport Efficiency Project (ENV155)

Noted Executive 1 paper

Cabinet noted this item on Tuesday 7 February 2012. Below is the council's own wording, with the papers it was decided on.

Item132

Resolved

1) The Cabinet noted one amendment to the report – in the Executive Summary paragraph 2 – amend reference to ¼ share to 1/5 as there are 5 boroughs involved. 2) The Cabinet agreed the recommendations of the report as follows: The Cabinet approved the tender process for the managed service provision of an Integrated Transport Information System (ITIS) for the West London Alliance (WLA) Regional Transport Bureau, as part of the WLA Alliance Transport Efficiency Programme. The Cabinet noted that this tender envisages that IT IS will be hosted by the chosen contractor remotely from Hounslow and will be provided on a managed service basis to ensure maximum flexibility to meet future changes in the Bureau’s service delivery requirements. 1) The Cabinet noted one amendment to the report – in the Executive Summary paragraph 2 – amend reference to ¼ share to 1/5 as there are 5 boroughs involved. 2) The Cabinet agreed the recommendations of the report as follows: The Cabinet approved the tender process for the managed service provision of an Integrated Transport Information System (ITIS) for the West London Alliance (WLA) Regional Transport Bureau, as part of the WLA Alliance Transport Efficiency Programme. The Cabinet noted that this tender envisages that IT IS will be hosted by the chosen contractor remotely from Hounslow and will be provided on a managed service basis to ensure maximum flexibility to meet future changes in the Bureau’s service delivery requirements.
Word for word from the decision Hounslow published for this meeting. Source: democraticservices.hounslow.gov.uk

Follow this further

Built from Hounslow's papers

What the report saysPro

Report to Cabinet

Recommendations

1.1To approve the tender process for the managed service provision of an Integrated Transport Information System (ITIS) for the West London Alliance (WLA) Regional Transport Bureau, as part of the WLA Alliance Transport Efficiency Programme

1.2To note that this tender envisages that ITIS will be hosted by the chosen contractor remotely from Hounslow and will be provided on a managed service basis to ensure maximum flexibility to meet future changes in the Bureau's service delivery requirements.

Summary

This report seeks agreement to start the tender process for a Managed Service provision of an Integrated Transport Information System for the West London Alliance Regional Transport Bureau (on behalf of five boroughs) that is to be established in the Hounslow Civic Centre in 2012. The system will enable the optimal selection of resources to carry out transport tasks, plan and cost journeys and, crucially, will enable optimisation of journeys amongst the multiple possible permutations of routes, resources and destinations across the participating Boroughs in the Programme). Provision of this system is critical to the successful operation of the Bureau and the provision of efficient and effective passenger transport services for vulnerable children and adults.

The contract value for provision of the Integrated Transport Information System is not expected to exceed £300k over three years. The value of the contract for Hounslow is estimated to be £75k (1/4 share) over three years. All of the participating Boroughs, including Hounslow, will be charged for a proportion of this cost according to their use of the Bureau's services. The value of the contract for Hounslow is estimated to be £75k (1/4 share) over three years. 2.0 BACKGROUND AND MAIN REPORT ETC

2.1The WLA Transport Efficiency Programme is a wide-ranging collaborative programme operating across five Boroughs (Hounslow, Ealing, Barnet and Brent plus Harrow, who have recently joined) and includes a number of work- streams that involve procurement activity in one form or another. Through the Programme Board it has been agreed that the lead for these procurement activities will be shared by various Boroughs and, specifically, it has been agreed that Hounslow will provide the lead Procurement/Legal input for the procurement of an ‘Integrated Transport Information System’ Managed Service contract for Passenger Transport that will be used by the WLA Regional Transport Bureau in the delivery of passenger transport services for the participating 4 Boroughs.

2.2The current annual spend on transport services across the four participating Boroughs is in excess of £20million. The WLA Transport Efficiency Programme is expected to deliver £8.4M savings over 4 years and, of this, it is anticipated that £2.4M savings will be delivered through the operation of the Bureau and will be enabled by implementation of the Integrated Transport Information System. Of this £2.4M, it is estimated that savings for Hounslow will be £547K.

2.3The objective of the initial phase of the Programme is to establish a collaborative Regional Transport Bureau to achieve:

• Maximum savings through collaborative working and centralised transport scheduling, call handling, procurement, integration of passenger transport services and concessionary travel services, wherever possible, and creation of a common framework for third party transport providers.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Procurement of Integrated Transport Information System for West London Alliance (WLA) Transport Efficiency Project (ENV155)Report 83 KB DownloadRead as text

At this meeting

Whole meeting
119Apologies for absence, declarations of interest or any other communications from MembersDecided 120Minutes of the meeting held on 17 January 2012Agreed 121Youth Services in Hounslow - A Scrutiny Review of Partnership Arrangements for the Voluntary and Community Sector - Final ReportAgreed 122Hounslow Town Centre Masterplan and Supplementary Planning Document (ENV 139)Agreed 123Street Trading Review - Hounslow Town Centre (ENV 160)Agreed 124Boston Manor House - options appraisal (ENV 121)Agreed 125Supplementary documents for Boston Manor reportNoted 126New Waterman's Marina Feasibility (ENV 131)Agreed 127Adult Day Opportunities Review (CS 310)Agreed 128Housing Revenue Account (HRA) Budget 2012/13, 3 Year Housing Capital Programme 2012/13-2014/15(CS 353)Noted 128aAddendum - revised report. Title: Housing Revenue Account (HRA) Budget 2012/13,3 Year Housing Capital Programme 2012/13-2014/15Noted 129Hounslow Local Safeguarding Children Board Annual Report (CSLL 216)Noted 130Armed Forces Community Covenant (CS 366)Approved 131Responding to the Importance of Music, a National Plan for Music Education (CSLL 238)Agreed
132Procurement of Integrated Transport Information System for West London Alliance (WLA) Transport Efficiency Project (ENV155)This decision
133West London Alliance Mobility Assessment Framework (ENV 156)Agreed 134NHS Monies for Social Care (CS365)Agreed 135Business Waiver to Continue Connexions Contract with Prospects Services Limited (CSLL 232)Noted 135aAddendum to Business Waiver report - Revised Equalities Impact AssessmentNoted 136Monthly Revenue Financial Monitoring - 30th November 2011 (CR11)Noted 137Urgent BusinessDecided 138Exclusion of Press and PublicDecided 139Compulsory Purchase Order : 18 Wellesley Road, Chiswick (CS 363)Private 140Lampton Park Conference Centre - Award of Catering Contract (ENV 134)Private 141New Waterman's Marina Feasibility (ENV 131) - Confidential appendixPrivate 142Any other items which the Chair considers urgent and are exempt from publicationDecided

More from Hounslow Cabinet

All decisions
MeetingDecisionOutcome
14 Jul 2026 Budget Outturn 2025-2026Resolved : Cabinet agreed to the following: General Fund 1. Approve the General Fund net revenue o verspend of £1.6m ... Agreed Open
14 Jul 2026 Delivery Plan Monitoring - Q4 2025/26Resolved : Cabinet agreed to: 1. Note progress to date with the programmes within the People Portfolio as set out in ... Agreed Open
14 Jul 2026 Quarterly Performance Reporting 2025-2026 (Q4)Resolved : Cabinet noted the corporate performance report for Quarter 4 (January to March 2026) detailed in Appendix ... Noted Open
14 Jul 2026 Procurement Plan - July 2026Resolved : Cabinet approved the following: 1. Specialist Support and Therapies services: a) Approve commencement of p... Approved Open
14 Jul 2026 Updated West London Waste Plan - Regulation 19 Consultation and Submission to Secretary of State for ExaminationResolved : Cabinet recommended to Borough Council: 1. To approve the ‘Regulation 19’ publication of the Proposed Subm... Approved Open