London Borough of Hounslow
Cabinet, Tuesday 1 April 2014 at 7.00pm

CA 427 - Outcomes of the Consultation on the expansion of Primary and SEN Places for September 2015

Agreed Executive 2 papers

Cabinet agreed this item on Tuesday 1 April 2014. Below is the council's own wording, with the papers it was decided on.

Item147

Resolved

That the Cabinet agreed the recommendations of the report as follows: 1. The Cabinet approved the expansion of five Primary schools and the establishment of five SEN Centres listed below from September 2014/15, subject to planning consent being obtained by July 2014. Beavers Primary School St Mary’s RC Primary School, Isleworth St Paul’s CE Primary School Hounslow Heath Infant School (SEN Centre) Hounslow Heath Junior School Hounslow Heath Junior School (SEN Centre) Feltham Hill Infant School (SEN Centre) Strand on the Green Infants and Strand on the Green Junior School (SEN Centre). 2. The Cabinet approved the allocation of funding for these projects identified in the School Expansion Programme 2013-15 (paragraph 17) and gave approval to invite and accept tenders for feasibility studies, investigations and construction works, all in compliance with the Council’s Tenders and Contract Regulations and EU law. 3. The Cabinet delegated authority to the Director for Children’s and Adults’ Services in consultation with the Lead Member for Education and HR to accept tenders for each scheme subject to all the tender returns not exceeding the total budget. 4. The Cabinet delegated authority to the Director for Children’s and Adults’ Services in consultation with the Lead Member to modify by way of changing, adding or removing from the list of schemes if necessary but remaining within the original financial constraints of the £26.071m detailed within the report. That the Cabinet agreed the recommendations of the report as follows: 1. The Cabinet approved the expansion of five Primary schools and the establishment of five SEN Centres listed below from September 2014/15, subject to planning consent being obtained by July 2014. Beavers Primary School St Mary’s RC Primary School, Isleworth St Paul’s CE Primary School Hounslow Heath Infant School (SEN Centre) Hounslow Heath Junior School Hounslow Heath Junior School (SEN Centre) Feltham Hill Infant School (SEN Centre) Strand on the Green Infants and Strand on the Green Junior School (SEN Centre). 2. The Cabinet approved the allocation of funding for these projects identified in the School Expansion Programme 2013-15 (paragraph 17) and gave approval to invite and accept tenders for feasibility studies, investigations and construction works, all in compliance with the Council’s Tenders and Contract Regulations and EU law. 3. The Cabinet delegated authority to the Director for Children’s and Adults’ Services in consultation with the Lead Member for Education and HR to accept tenders for each scheme subject to all the tender returns not exceeding the total budget. 4. The Cabinet delegated authority to the Director for Children’s and Adults’ Services in consultation with the Lead Member to modify by way of changing, adding or removing from the list of schemes if necessary but remaining within the original financial constraints of the £26.071m detailed within the report.
Word for word from the decision Hounslow published for this meeting. Source: democraticservices.hounslow.gov.uk

Follow this further

Built from Hounslow's papers

What the report saysPro

Report to Cabinet

Report for: ACTION

Contains Confidential No or Exempt Information No

Title CA427

Outcomes of the Consultations on the expansion of Primary and SEN places September 2015 Member Deciding Councillor Tom Bruce, Lead Member for Education and HR Contact Details Sheena Poley, Head of Place Planning and Admissions [email protected] Tel: 020 8583 2640 For Consideration By Cabinet Date to be Considered 1 April 2014 Implementation Date if 11 April 2014 Not Called In Affected Wards All Wards Keywords/Index Consultation, School organisation, school expansion, Beavers School, St Mary’s RC Isleworth, Hounslow Heath Infants, Hounslow Heath Juniors, Feltham Hill Infants, Strand on the Green Infants and Strand on the Green Juniors.

1. Details of Recommendations

1.1Approve the expansion of five Primary schools and the establishment of five SEN Centres listed below from September 2014/15, subject to planning consent being obtained by July 2014.

• Beavers Primary School • St Mary’s RC Primary, RC • St Paul’s CE Primary School • Hounslow Heath Infant School • Hounslow Heath Infant School (SEN Centre) • Hounslow Heath Junior School • Hounslow Heath Junior School (SEN Centre) • Feltham Hill Infant School (SEN Centre) • Strand on the Green Infants and Strand on the Green Junior School (SEN Centre)

1.2To approve the allocation of funding for these projects identified in the School Expansion Programme 2013-15 (paragraph 17), and seek approval to invite and accept tenders for feasibility studies, investigations and construction works, all in compliance with the council’s Tenders and Contract Regulations and EU law.

1.3Delegate Authority to the Director for Children’s and Adults Services in consultation with the Lead Member for Education and HR to accept tenders for each scheme subject to all the tender returns not exceeding the total budget.

1.4Delegate Authority to the Director for Children’s and Adults Services in consultation with the Lead Member to modify by way of changing, adding or removing from the list of schemes if necessary but remaining within the original financial constraints of the £26.071m detailed within this report.

If the recommendations are adopted, how will residents benefit? ‘Getting it Right – Going the extra mile’- parents can Additional places will be expect a fair and equitable provision which responds provided to meet demand to their needs for September 2015

2. Report Summary

The local authority is responding to it statutory duty to provide sufficient schools places to meet need. This paper presents the outcomes of statutory notices on proposals to expand, with effect from September 2015/16 Reception entry, 5 of the borough’s infant, junior and primary schools to meet the growing demand for primary school places across Hounslow and establish four SEN centres in Primary Schools.

The Cabinet gave approval at their meeting on 3 December 2013 to delegate the decision to expand the schools to the Lead Member for Education and HR, if there were no significant objections.

3. Reason for Decision and Options Considered

3.1Members are aware of the increasing birth rate in the borough and the resulting increased demand for Primary and SEN school places. As part of the Council’s response to this, public consultation was undertaken on the expansion of five schools and establishment of an SEN centre in 4 primary schools (listed below) between 9 September and 18 October 2013.

3.2The outcomes of these consultations were reported to Cabinet in December 2013. At that meeting approval was given to proceed to the next stage of the process, which involves statutory notices being published formally proposing the expansion and inviting representations from anyone with an interest.

3.3The regulations governing the expansion of schools state that Statutory Notices are required for the increase in capacity of a school by both:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CA 427: Outcomes of the Consultation on the expansion of Primary and SEN Places for September 2015Report 152 KB DownloadRead as text
PDF
Cabinet report CA427 Appendix A: 2011-16 Bulge Class CostingsAppendix 79 KB Download

At this meeting

Whole meeting

On this subject at Hounslow

Search all
  1. CA 427 - Outcomes of the Consultation on the expansion of Primary and SEN Places for September 2015This decision
  2. CA 449- Outcomes of the Statutory Consultation to Expand Marjory Kinnon and Oaklands SchoolsNoted
  3. CA 455 - Outcomes of the formal consultation to expand Wellington Primary School for September 2017Agreed
  4. CA 465 - Outcomes of the informal consultations to expand Marjory Kinnon and Oaklands Special SchoolsAgreed

More from Hounslow Cabinet

All decisions
MeetingDecisionOutcome
14 Jul 2026 Budget Outturn 2025-2026Resolved : Cabinet agreed to the following: General Fund 1. Approve the General Fund net revenue o verspend of £1.6m ... Agreed Open
14 Jul 2026 Delivery Plan Monitoring - Q4 2025/26Resolved : Cabinet agreed to: 1. Note progress to date with the programmes within the People Portfolio as set out in ... Agreed Open
14 Jul 2026 Quarterly Performance Reporting 2025-2026 (Q4)Resolved : Cabinet noted the corporate performance report for Quarter 4 (January to March 2026) detailed in Appendix ... Noted Open
14 Jul 2026 Procurement Plan - July 2026Resolved : Cabinet approved the following: 1. Specialist Support and Therapies services: a) Approve commencement of p... Approved Open
14 Jul 2026 Updated West London Waste Plan - Regulation 19 Consultation and Submission to Secretary of State for ExaminationResolved : Cabinet recommended to Borough Council: 1. To approve the ‘Regulation 19’ publication of the Proposed Subm... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies