That the Cabinet agreed the recommendations of the report as follows: 1. The Cabinet approved the Schools (Maintenance) Capital Programme 2014-15 as outlined in Appendix A of the report. 2. The Cabinet agreed to include all procurement projects linked to this report as Appendix A of the Council’s Annual Procurement Plan (where decisions are delegated to the Director of the Service Area). 3. The Cabinet agreed to delegate to the Chief Officer to modify the schemes and budgets if necessary following site investigations. If projects are changed, the overall budget will not be exceeded. That the Cabinet agreed the recommendations of the report as follows: 1. The Cabinet approved the Schools (Maintenance) Capital Programme 2014-15 as outlined in Appendix A of the report. 2. The Cabinet agreed to include all procurement projects linked to this report as Appendix A of the Council’s Annual Procurement Plan (where decisions are delegated to the Director of the Service Area). 3. The Cabinet agreed to delegate to the Chief Officer to modify the schemes and budgets if necessary following site investigations. If projects are changed, the overall budget will not be exceeded.
Word for word from the decision Hounslow published for this meeting.Source: democraticservices.hounslow.gov.uk
Contains Confidential No or Exempt Information Title Schools (Maintenance) Capital Programme 2014-15 Member Reporting Cllr Tom Bruce Cabinet Member Education & Human Resources Contact Details Bob Seera Head of Property Development [email protected] Ext 2547 For Consideration By Cabinet Date to be Considered 1 April 2014 Implementation Date if Not Called In Affected Wards All Keywords/Index
1. Details of Recommendations
The Cabinet is asked to agree the following:
1.1To approve the Schools (Maintenance) Capital Programme 2014-15 as outlined in Appendix A. 1.2 To include all procurement projects linked to this report as Appendix A of the Council Annual Procurement Plan( where decisions are delegated to the Director of the Service Area). 1.3 Delegate authority to the Chief Officer to modify the schemes and budgets if necessary following site investigations. If projects are changed, the overall budget will not be exceeded.
If the recommendations are adopted, how will residents benefit?
Maintenance of existing school portfolio ensures 2015-16 schools are fit for purpose and enables brighter futures for the Borough’s children and young people. 2. Report Summary
1. This report seeks Member approval of the Schools (Maintenance) Capital Programme 2014-15 as outlined in Appendix A. 2. It recommends that all projects listed in Appendix A are approved and placed on the Council Annual Procurement Plan as Appendix A items, granting delegated authority to the Director of Regeneration, Economic Development and Environment. 3. These recommendations are being made because the existing school portfolio requires regular maintenance to ensure it is fit for purpose. 4. There is no call on Council resources as the programme is funded from DfE funding. 5. All projects will be delivered at Local Authority maintained schools only as Academies and Free Schools are not eligible for this funding.
3. Reason for Decision and Options Considered
3.1The proposed projects are all necessary priority works identified from the school condition surveys. The surveys are currently being updated therefore this programme seeks to complete outstanding items from the existing information. 3.2 The programme also seeks to retain a significant contingency that enable any high priority urgency items to be undertaken prior to the release of the DfE Capital Maintenance Funding 2015-16. 3.3 Funding has been allocated based on the most appropriate schools building priorities.
4. Key Implications
4.1Projects have not yet been commissioned and the individual project scope is yet to be determined. Targets and measures will be established on a project by project basis in conjunction with relevant stakeholders, in particular the schools.
5. Financial Details
5.1The projects identified by officers will be funded from the 2014-15 capital maintenance funding allocated from the DfE. Any overspend will be met from the contingency sum. There is no call on council resources for these projects. 5.2 The DfE maintenance capital grant funding allocated to the London Borough of Hounslow for 2014-15 is £2,498,174. 5.3 The DfE allocation is calculated using the number of Local Authority (LA) maintained schools within the Borough, excluding all Academies and Free Schools. Therefore, all proposed projects will be delivered at LA maintained schools only. 5.4 Following Member approval, schools will be notified of the project allocations. It should be noted that the costs identified for each project are indicative only. As with any list of projects across a wide portfolio of properties it may be necessary to modify the list of schemes as each project is progressed due to unknown site factors.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Delivery Plan Monitoring - Q4 2025/26Resolved : Cabinet agreed to: 1. Note progress to date with the programmes within the People Portfolio as set out in ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.