Project Progress Report - Heritage Lottery Project - Update

Agreed Committee 1 paper

Gunnersbury Park Joint Advisory Panel agreed this item on Friday 18 July 2014. Below is the council's own wording, with the papers it was decided on.

Item4

Resolved

The following actions were agreed by the Panel: Members congratulated both authorities for swift action in dealing with the Traveller incursion. Members proposed that officers ask the Safer Community Teams in both authorities to be involved in considering the security of the park to avoid problems for the future. It was agreed that the regular project update to the Panel should include an item on security to each meeting. Members asked officers to consider levying a small charge for future events with funds raised going to the park. Members wished to have the following agenda items with reports for the October meeting: · The Mela · Sports in the Park · Events and where income generated has been attributed. Members also asked for feedback on action taken in respect of the incident on 27 June of broken glass deliberately perpetrated in the children’s playground.
Word for word from the decision Hounslow published for this meeting. Source: democraticservices.hounslow.gov.uk

Follow this further

Built from Hounslow's papers

What the report saysPro

Report to Gunnersbury Park Joint Advisory Panel, 6 pages

GUNNERSBURY PARK REGENERATION PROJECT

GUNNERSBURY PARK London

Project Progress Report Gunnersbury Park Joint Advisory Panel

18 July 2014

1 Project Progress report to Gunnersbury Park Joint Advisory Panel 18th July 2014

1.0HLF Applications

1.1Parks for People Grant (PfP) On 26 June 2014 HLF awarded us a grant of up to £4,671,000.00 (four million six hundred and seventy one thousand pounds), 57% of the total eligible project cost of £8,207,009.00 towards works proposed to conserve and enhance the heritage parkland, to improve the parks facilities and to provide a wider range of activities, events and opportunities for learning.

HLF will monitor progress against the following outputs:

1. Restore the historic parkland setting of the two mansions, planting and tree work 2. Relocate the pitch and putt course to open up the historic parkland 3. Restore the Orangery for use as an events venue 4. Recreate the west section of the Horseshoe Pond 5. Repair the round pond and bring back public boating activities 6. Re-build the cafe and create stronger links with park and museum and restore views 7. Restore the park’s listed structures and remove them from the at Risk Register 8. Create a community kitchen garden with learning and volunteering opportunities 9. Create new footpath links to improve circulation around the park 10. Develop existing and new habitats to increase the wildlife value of the park 11. Improve the park’s entrance areas, signage and interpretation 12. Delivery of Activity Plan 13. Appointments: Head Gardener (1FTE) - for 5 years Outreach Officer (1 FTE) - for 4 yrs Learning Officer (0.5 FTE)- for 5 yrs Horticultural Apprentices - 3nr for 12 months each

1.2Heritage Grant (HG) Awards will be decided 22 July 2014. This project encompasses the refurbishment of the large mansion and the museum.

1.3Permission to start A joint meeting will be arranged end July for PfP and HG, if successful to agree:

construction programme by considering the duration and sequence of component activities management for the construction phase Review and determine procurement strategy Review and update risk register

1.4Development Phase The total cost of the Development Phase (up to submission of the bids to HLF) for both projects was completed within budget with a slight underspend achieved due to efficiencies in running the two bids together. The final PfP claim was submitted 20 June 2014. The HG final claim is planned for 11 July 2014

2 2.0 Work stream updates

2.1Governance and Development Trust This work stream has appointed external consultants to provide expert advice on the legal and financial implications for the most advantageous governance model. It considers the council’s overarching requirement to retain strategic control of operations whilst meeting the requirements of the HLF and taking VAT risks into account.

The proposal is for: A Community Interest Company (CIC) limited by guarantee. o A recommendation will be made to both Cabinets in October for a CIC to manage and Operate Gunnersbury.

A separate Charitable Trust for raising funds will be created that will be able to pass these funds to CIC. advice has been obtained on the most efficient way to transfer these funds o An appointment will be made at each borough council in September to the charitable trust.

A review of the current management of the site is underway to explore the best option for the transition period between starting the HLF project and the hand over to the CIC

2.2Procurement Strategy for Construction Contractor The project team carried out a procurement workshop on the 2nd of July to agree on a procurement strategy for the project including both PfP and HG.

The team agreed that a two stage procurement strategy using a traditional form of contract was the preferred route. The discussions centred upon protecting the client’s commercial position, maintaining the qualitative aspirations of the project and carrying out sufficient opening-up and investigative works to inform the design.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Project Progress Report: Heritage Lottery Project: UpdateReport 6 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Hounslow

Search all
  1. Project Progress Report - Heritage Lottery Project - UpdateThis decision
  2. Progress Report on the Lottery ProjectNoted
  3. Heritage Lottery Fund (HLF) Capital Project Progress UpdateAgreed
  4. Project Progress UpdateNoted

More from Hounslow Gunnersbury Park Joint Advisory Panel

All decisions
MeetingDecisionOutcome
7 Jul 2017 Heritage Progress ReportThe submitted report was noted. Noted Open
7 Jul 2017 Sports Progress ReportResolved : The submitted report was noted. Noted Open
28 Apr 2017 Dates of future meetingsIt was agreed to move the July 21 date forward to 7 July 2017. James Wisdom submitted apologies for the new date and ... Agreed Open
18 Nov 2016 Presentation on Sports HubIt was agreed that revised images would be circulated the following week to members of the Panel, as well as to other... Agreed Open
21 Oct 2016 Update on Park Events Licence ProposalIt was agreed to arrange an additional meeting with appropriate officers attending to discuss the licensing policy. Agreed Open