CR129 - Monthly Financial Monitoring (2014/15 - Period 4)

Agreed Executive 5 papers

Cabinet agreed this item on Tuesday 9 September 2014. Below is the council's own wording, with the papers it was decided on.

Item24

Resolved

That the Cabinet agreed the recommendations of the report as follows: 1) The Cabinet noted the following: 1. Projected revenue outturn for the General Fund. 2. Projected revenue outturn for the Housing Revenue Account (HRA). 3. A detailed mitigation report on each of the service areas shown to have projected overspend of £100,000 or more will be provided with the October Monthly Financial Monitoring report and details on all known pressures on the revenue budget will be presented in the Medium Term Financial Strategy. 4. Performance against the key corporate financial indicators and summary of debts approved for write off. 5. Treasury Management performance for the period to 31 July 2014. 6. The following approved projects to be funded from the Chief Executive’s Performance Improvement Fund:- · £108,600 to establish four posts in Legal Services. · £100,000 Waterman’s Park – Feasibility study of licensed moorings development. · £192,557 to fund increased capacity to support Members and electoral registrations. · £200,000 Western International Market and Environs – Property Development Opportunities. 2) The Cabinet approved the following recommendations:- 7. Approved the additions and amendments to the Annual Procurement Plan (as detailed in Appendix C of the report). 8. Approved the budget virements highlighted below:- a) Budget realignment in Children’s Services to reflect more up to date information. b) Budget adjustments to reflect the second wave of Hounslow Homes staff transferring to Corporate Resources and Chief Executive’s (CED) Departments. c) Budget transfer in Regeneration, Economic Development and Environment to reflect the appointment of a Director of Public Health. This has resulted in the creation of a Public Health and Leisure division. That the Cabinet agreed the recommendations of the report as follows: 1) The Cabinet noted the following: 1. Projected revenue outturn for the General Fund. 2. Projected revenue outturn for the Housing Revenue Account (HRA). 3. A detailed mitigation report on each of the service areas shown to have projected overspend of £100,000 or more will be provided with the October Monthly Financial Monitoring report and details on all known pressures on the revenue budget will be presented in the Medium Term Financial Strategy. 4. Performance against the key corporate financial indicators and summary of debts approved for write off. 5. Treasury Management performance for the period to 31 July 2014. 6. The following approved projects to be funded from the Chief Executive’s Performance Improvement Fund:- · £108,600 to establish four posts in Legal Services. · £100,000 Waterman’s Park – Feasibility study of licensed moorings development. · £192,557 to ... view the full minutes text for item 24.
Word for word from the decision Hounslow published for this meeting. Source: democraticservices.hounslow.gov.uk

Follow this further

Built from Hounslow's papers

What the report saysPro

Report to Cabinet, 9 pages

Report for: ACTION

Contains Confidential Yes, Appendix E. Under exempt category 3 - Information or Exempt Information relating to the financial or business affairs of any particular person (including the authority holding that information).

Title CR129 - Monthly Financial Monitoring Report Member Reporting Councillor Theo Dennison, Cabinet Member for Finance and Citizen Engagement Contact Details Name: Clive Palfreyman, AD Strategic Finance Telephone: 020 8583 6682 Email: [email protected] For Consideration By Cabinet Date to be Considered 9 September 2014 Implementation Date if 16 September 2014 Not Called In Affected Wards All Keywords/Index Financial Monitoring, Period 4

1 Details of Recommendations Cabinet members are asked to note the following:-

1. Projected revenue outturn for the General Fund. 2. Projected revenue outturn for the Housing Revenue Account (HRA) 3. A detailed mitigation report on each of the service areas shown to have a projected overspend of £100,000 or more will be provided with the October Monthly Financial Monitoring report and details on all known pressures on the revenue budget will be presented in the Medium Term Financial Strategy. 4. Performance against the key corporate financial indicators and summary of debts approved for write off. 5. Treasury Management performance for the period to 31 July 2014. 6. The following approved projects to be funded from the Chief Executive’s Performance Improvement Fund:- £108,600 to establish four posts in Legal Services £100,000 Waterman’s Park - Feasibility study of licensed moorings development £192,557 to fund increased capacity to support Members and electoral registrations £200,000 Western International Market & Environs - Property Development Opportunities

Cabinet members are asked to approve the following recommendations:- 7. To approve the additions and amendments to the Annual Procurement Plan (as detailed in Appendix C). 8. To approve the budget virements highlighted below:- a. Budget realignment in Children’s services to reflect more up to date information. b. Budget adjustments to reflect the second wave of Hounslow Homes staff transferring to Corporate Resources and CED. c. Budget transfer in Regeneration, Economic Development and Environment to reflect the appointment of a Director of Public Health. This has resulted in the creation of a Public Health and Leisure division.

If the recommendations are adopted, how will residents benefit? Benefits to residents and reasons why they will Dates by which they can expect to benefit, link to Values notice a difference The Council will manage its cost pressures to ensure - that costs are managed within the approved budget.

2 Report Summary This report presents a projected general fund revenue outturn for 2014/15 of £186.7m which represents a £4.9m over spend against revised budget on departmental revenue spend and a £0.5m under spend against revised budget on corporate budgets, giving a total net projected overspend of £4.4m.

This report also presents a projected surplus of £2.0m for the 2014/15 HRA. This represents an underspend of £0.2m against the revised HRA budget.

The report provides an update on the Council’s performance against the key corporate financial indicators and a summary of the write offs approved in this period.

3 Reason for Decision and Options Considered 3.1 Members are asked to approve a number of recommendations in this report. The reasons for these decisions are highlighted below.

3.2Decision 1 - Additions and amendments to the Annual Procurement Plan - this will enable the Council to deliver the services as outlined in Appendix C.

3.3Decision 2 - Approval of budget virements highlighted in Section 5.19 – 5.23. These are required in order to ensure that budgets are aligned to management responsibilities for effective control and management.

4 Key Implications 4.1 There are no key implications to be considered.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Department Outturn P4Appendix A 5 pages Download
PDF
Key Corporate Financial IndicatorsAppendix B 1 pages Download
PDF
Procurement Plan UpdatesAppendix C 5 pages Download
PDF
Treasury Managment UpdateAppendix D 4 pages Download
PDF
CR129: Monthly Financial Monitoring (2014/15: Period 4)Report 9 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Hounslow

Search all
  1. CR129 - Monthly Financial Monitoring (2014/15 - Period 4)This decision
  2. Monthly Revenue Financial Monitoring -Decided
  3. CEX 166 - Monthly Financial MonitoringAgreed
  4. CEX 148 - Monthly Financial MonitoringAgreed
  5. CEX 140 - Monthly Financial Monitoring ReportAgreed
  6. CEX 136 - Monthly Financial Monitoring ReportDecided

More from Hounslow Cabinet

All decisions
MeetingDecisionOutcome
14 Jul 2026 Budget Outturn 2025-2026Resolved : Cabinet agreed to the following: General Fund 1. Approve the General Fund net revenue o verspend of £1.6m ... Agreed Open
14 Jul 2026 Delivery Plan Monitoring - Q4 2025/26Resolved : Cabinet agreed to: 1. Note progress to date with the programmes within the People Portfolio as set out in ... Agreed Open
14 Jul 2026 Quarterly Performance Reporting 2025-2026 (Q4)Resolved : Cabinet noted the corporate performance report for Quarter 4 (January to March 2026) detailed in Appendix ... Noted Open
14 Jul 2026 Procurement Plan - July 2026Resolved : Cabinet approved the following: 1. Specialist Support and Therapies services: a) Approve commencement of p... Approved Open
14 Jul 2026 Updated West London Waste Plan - Regulation 19 Consultation and Submission to Secretary of State for ExaminationResolved : Cabinet recommended to Borough Council: 1. To approve the ‘Regulation 19’ publication of the Proposed Subm... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies