That the Cabinet agreed the recommendations of the report as follows: The Cabinet noted the progress of the work undertaken for the 2013-2015 schools expansion programme. The Cabinet agreed to the process of consultation by publishing Statutory Notices to expand Wellington Primary School from 2 forms of entry to 4 forms of entry in September 2017. The Cabinet agreed to the proposed 2016-2020 School Expansion delivery programme identified in section 5 of the report. The Cabinet noted the potential costs associated with the provision of places for the 2016-2020 schools expansion programme. The Cabinet noted that a more detailed report will be presented to Cabinet on 13 October 2014 on the projected need for SEN places and any required expansion to existing SEN Schools. That the Cabinet agreed the recommendations of the report as follows: The Cabinet noted the progress of the work undertaken for the 2013-2015 schools expansion programme. The Cabinet agreed to the process of consultation by publishing Statutory Notices to expand Wellington Primary School from 2 forms of entry to 4 forms of entry in September 2017. The Cabinet agreed to the proposed 2016-2020 School Expansion delivery programme identified in section 5 of the report. The Cabinet noted the potential costs associated with the provision of places for the 2016-2020 schools expansion ... view the full minutes text for item 18.
Word for word from the decision Hounslow published for this meeting.Source: democraticservices.hounslow.gov.uk
Contains Confidential Yes - Appendix 6 or Exempt Information Information is exempt under Schedule 12A of the Local Government Act 1972 as it includes the financial or business affairs of the authority and in all the circumstances of the case, the public interest in maintaining the exemption outweighs the public interest in disclosing the information.
Title CA446
Schools Expansion Programme 2016-2020
Member Reporting Councillor Tom Bruce, Lead Member for Education and Children’s Services Contact Details Sheena Poley, Head of Place Planning and Admissions [email protected] Tel: 020 8583 2640 For Consideration By Cabinet Date to be Considered 9 September 2014
Implementation Date if 1 April 2016 Not Called In Affected Wards ALL Keywords/Index Schools, School Organisation, Expansion, Wellington, Secondary Schools, Primary Schools, School expansion programme 2016-2020 Hounslow Town, SEN
1. Details of Recommendations
Cabinet is asked to:
1. Note the progress of the work undertaken for the 2013-2015 schools expansion programme
2. Agree to the process of consultation by publishing Statutory Notices to expand Wellington Primary School from 2 forms of entry to 4 forms of entry in September 2017.
3. Agree the proposed 2016-2020 School Expansion delivery programme identified in section 5.
4. Note the potential costs associated with the provision of places for the 2016- 2020 schools expansion programme. 5. Note that a more detailed report will be presented to Cabinet on 14 th October 2014 on the projected need for SEN places and any required expansion to existing SEN Schools.
If the recommendations are adopted, how will residents benefit? Benefits to residents and reasons why they will Dates by which they can benefit, link to Values expect to notice a difference Provision of high quality school places in areas of September 2016 greatest demand Local schools and places for local children
2. Report Summary
This report provides Cabinet with an update on the progress of the 2013-2105 school expansion programme and presents the school place need for 2016-20.
The report proposes several scenarios to address the secondary need and to secure funding to deliver the capital programme required to meet the projected place need beyond 2015-16 and up to 2020.
As part of the 2016-2020 delivery programme the Cabinet is asked to consider whether to proceed with proposals for expanding Wellington Primary School by September 2017, through publication of appropriate statutory notices. Any decision to issue statutory notices should take account of the views that have been expressed during the earlier informal consultation process, detailed in appendix 5.
3. Context for School Place Planning in Hounslow
3.1Since 2000 there has been an increase in the local birth rate. This along with patterns of migration and a rise in the number of families occupying new housing in Hounslow has contributed to a significant increase in the population. In its analysis report, ‘Do the Maths 2014’, released recently by London Councils, it reveals and details the current and future huge pressure for, and shortage of, school places in London. Within that context the report highlights that Hounslow: Is the 7th highest London borough for pupil growth overall between 2012- 2017. Is one of 5 London Boroughs with the highest percentage of growth, at 24.4% in the primary phase between 2012-2017. Has a secondary phase growing by 6.6% between 2012-2017
3.2Rising construction costs, a shortage of land and the Heathrow flight path, add to the costs of both building new schools and expanding existing ones in Hounslow.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Delivery Plan Monitoring - Q4 2025/26Resolved : Cabinet agreed to: 1. Note progress to date with the programmes within the People Portfolio as set out in ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.