Cabinet, Tuesday 19 January 2016 at 7.00pm

REG88 - Marjory Kinnon School School Expansion Update

Agreed Executive 1 paper

Cabinet agreed this item on Tuesday 19 January 2016. Below is the council's own wording, with the papers it was decided on.

Item121

Resolved

That Cabinet agreed the recommendations of the report as follows: 1. Cabinet noted the progress of the proposals to expand Marjory Kinnon School. 2. Cabinet authorised the Executive Director, Regeneration, Economic Development and Environment (‘Director’), or such officers as may be authorised to act on his behalf, to take all necessary actions to progress the procurement and letting of the contracts; to accept and award the construction phase works and other associated costs, professional fees and surveys, subject to the project remaining within budget forecast costs. That Cabinet agreed the recommendations of the report as follows: 1. Cabinet noted the progress of the proposals to expand Marjory Kinnon School. 2. Cabinet authorised the Executive Director, Regeneration, Economic Development and Environment (‘Director’), or such officers as may be authorised to act on his behalf, to take all necessary actions to progress the procurement and letting of the contracts; to accept and award the construction phase works and other associated costs, professional fees and surveys, subject to the project remaining within budget forecast costs.
Word for word from the decision Hounslow published for this meeting. Source: democraticservices.hounslow.gov.uk

Follow this further

Built from Hounslow's papers

What the report saysPro

Report to Cabinet

Reason for decision

3.1CA449 reported to Cabinet on the outcome of the formal consultation to expand Marjory Kinnon School. On 17 March 2015 Cabinet approved the expansion of Marjory Kinnon School, subject to planning consent being obtained.

3.2The Local Authority has a statutory duty to provide education for SEN children through the specialist support and teaching that they require to fulfil their potential and be kept safe.

3.3The proposal to expand Marjory Kinnon Special School is to construct a dedicated Primary and Secondary SEN School on recreational green space south on the existing Marjory Kinnon School. The school will expand places from 165 to accommodate 288 pupils.

3.4This project will involve the demolition of the existing Marjory Kinnon School building upon completion and occupation of the new facility.

3.5Discussions have commenced with Bedfont Primary School who share the western boundary of the site with Marjory Kinnon School. Issues to be considered include a permanent pupil access point onto the playing field, as well as a temporary solution to the use of the field during the period of construction.

3.6A planning application is being prepared and will issued shortly.

3.7An OJEU contract notice has been placed in the Official Journal of the European Union (OJEU). A Pre-Qualification Questionnaire is being provided to prospective bidders who express an interest. Subsequently, a shortlist of contractors will be selected to participate in a competitive tender process.

3.8A master programme has been developed and the aim is to complete the construction of the new school at Marjory Kinnon by December 2017. This is a tight programme and there is little scope for slippage of individual activities without impacting on the overall delivery date.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
REG88: Marjory Kinnon School School Expansion UpdateReport 77 KB DownloadRead as text

More from Hounslow Cabinet

All decisions
MeetingDecisionOutcome
14 Jul 2026 Budget Outturn 2025-2026Resolved : Cabinet agreed to the following: General Fund 1. Approve the General Fund net revenue o verspend of £1.6m ... Agreed Open
14 Jul 2026 Delivery Plan Monitoring - Q4 2025/26Resolved : Cabinet agreed to: 1. Note progress to date with the programmes within the People Portfolio as set out in ... Agreed Open
14 Jul 2026 Quarterly Performance Reporting 2025-2026 (Q4)Resolved : Cabinet noted the corporate performance report for Quarter 4 (January to March 2026) detailed in Appendix ... Noted Open
14 Jul 2026 Procurement Plan - July 2026Resolved : Cabinet approved the following: 1. Specialist Support and Therapies services: a) Approve commencement of p... Approved Open
14 Jul 2026 Updated West London Waste Plan - Regulation 19 Consultation and Submission to Secretary of State for ExaminationResolved : Cabinet recommended to Borough Council: 1. To approve the ‘Regulation 19’ publication of the Proposed Subm... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies