CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
London Borough of Hounslow
Cabinet, Tuesday 19 January 2016 at 7.00pm

CEX081 - Monthly Financial Monitoring

Agreed Executive 1 paper

Cabinet agreed this item on Tuesday 19 January 2016. Below is the council's own wording, with the papers it was decided on.

Item122

Resolved

That Cabinet agreed the recommendations of the report as follows: 1. Cabinet noted the following: Finance · £370,000 to be allocated from the Chief Executive’s Performance Improvement Fund to fund the costs of professional fees relating to the relocation of the Civic Centre. · £67,000 to be allocated from the savings investment fund for the IT set up costs of the Citizen Access Portal, to deliver savings in 2016/17. · £49,000 to be allocated from the savings investment fund for delivery of savings in leisure. Procurement · Approved exemptions to the procurement regulations (waivers) as set out in Appendix VI of the report. 2. Cabinet approved the following recommendation: Procurement · The additions to the Annual Procurement Plan (detailed in Appendix V of the report). That Cabinet agreed the recommendations of the report as follows: 1. Cabinet noted the following: Finance · £370,000 to be allocated from the Chief Executive’s Performance Improvement Fund to fund the costs of professional fees relating to the relocation of the Civic Centre. · £67,000 to be allocated from the savings investment fund for the IT set up costs of the Citizen Access Portal, to deliver savings in 2016/17. · £49,000 to be allocated from the savings investment fund for delivery of savings in leisure. Procurement · Approved exemptions to the procurement regulations (waivers) as set out in Appendix VI of the report. 2. Cabinet approved the following recommendation: Procurement · The additions to the Annual Procurement Plan (detailed in Appendix V of the report).
Word for word from the decision Hounslow published for this meeting. Source: democraticservices.hounslow.gov.uk

Follow this further

Built from Hounslow's papers

What the report saysPro

Report to Cabinet

Report for: INFORMATION

Contains Confidential No or Exempt Information Title CEX081 - Monthly Financial Monitoring Report Member Reporting Councillor Theo Dennison, Cabinet Member for Finance and Citizen Engagement Councillor Corinna Smart, Cabinet Member for Corporate Performance and Customer Care Contact Details Name: Clive Palfreyman, Director, Finance and Corporate Services Telephone: 020 8583 6682 Email: [email protected] For Consideration By Cabinet Date to be Considered 20 January 2016 Implementation Date if 1 February 2016 Not Called In Affected Wards All Keywords/Index Financial Monitoring, Period 8, Procurement, APP, Waivers

1 DETAILS OF RECOMMENDATIONS

1.1Cabinet members are asked to note the following:-

Finance • £370,000 to be allocated from the Chief Executive’s Performance Improvement Fund to fund the costs of professional fees relating to the relocation of the Civic Centre • £67,000 to be allocated from the savings investment fund for the IT setup costs of the Citizen Access Portal to deliver savings in 2016/17 • £49,000 to be allocated from the savings investment fund for delivery of savings in corporate property • £24,000 to be allocated from the savings investment fund for delivery of savings in leisure

Procurement • Approved exemptions to the procurement regulations (waivers) as set out in Appendix VI

1.2Cabinet members are asked to approve the following recommendation:-

Procurement • The additions to the Annual Procurement Plan (detailed in Appendix V). If the recommendations are adopted, how will residents benefit? Benefits to residents and reasons why they will Dates by which they can expect to benefit, link to Values notice a difference The Council will manage its cost pressures to ensure - that costs are managed within the approved budget.

1 REPORT SUMMARY 2.1 This report presents the following; • Projected General Fund revenue outturn for 2015/16 of £185m which represents an overspend against revised budget on departmental revenue spend. This variance ranges from £6.3m to £9.0m depending on the successful implementation of mitigation strategies. There is a projected £5.1m underspend against revised budget on corporate budgets which will reduce the overspend range between £1.2m to £3.9m. • Projected revenue outturn for Housing Revenue Account (HRA) with deficit of £16.4m and an underspend of £0.45m against 2015/16 budget. • An update on the Council’s performance against the key corporate financial indicators. • Summary of write offs awaiting approval • Annual Procurement Plan with additions • Waivers granted in the period between September 2015-December 2015

3 KEY IMPLICATIONS 3.1 There are no key implications in this report

4 FINANCIAL DETAILS Financial Impact on the Budget 4.1 There are no decisions proposed in this report that have an impact on the overall Council’s revenue budget. An update on the Council’s financial performance is provided below.

General Fund 4.2 The table below provides a summary of each Directorate’s performance against the Council’s approved 2015/16 Revenue Budget and is based on department’s projections of their anticipated outturn for the year.

4.3The projected revenue outturn anticipates a significant overspend on departmental revenue spend and a £5.1m underspend on corporate budgets. Further detail is provided in Appendix I.

4.4Mitigation reports have been prepared for each service area overspending by more than £100k. These mitigation plans are included at Appendix II

4.5Where mitigation plans are robust, these have built into current projected figures. If all mitigation plans are successfully implemented the variance would change as shown (a) (b) (c) (d) (e) (f) (g) (h) (c)-(b) (d)-(e) (d)-(g) Department Variance Original Revised Projected Mitigation Adjusted Variance Reported last Movement Budget Budget Outturn proposals Variance period £m £m £m £m £m £m £m £m Chief Executive 64.5 64.1 64.8 0.7 0.4 0.3 0.0 0.7

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CEX081: Monthly Financial MonitoringReport 846 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Hounslow

Search all
  1. CEX081 - Monthly Financial MonitoringThis decision
  2. CEX 166 - Monthly Financial MonitoringAgreed
  3. CEX 148 - Monthly Financial MonitoringAgreed
  4. CEX 140 - Monthly Financial Monitoring ReportAgreed
  5. CEX 136 - Monthly Financial Monitoring ReportDecided
  6. CEX126 Monthly Financial MonitoringNoted

More from Hounslow Cabinet

All decisions
MeetingDecisionOutcome
14 Jul 2026 Budget Outturn 2025-2026Resolved : Cabinet agreed to the following: General Fund 1. Approve the General Fund net revenue o verspend of £1.6m ... Agreed Open
14 Jul 2026 Delivery Plan Monitoring - Q4 2025/26Resolved : Cabinet agreed to: 1. Note progress to date with the programmes within the People Portfolio as set out in ... Agreed Open
14 Jul 2026 Quarterly Performance Reporting 2025-2026 (Q4)Resolved : Cabinet noted the corporate performance report for Quarter 4 (January to March 2026) detailed in Appendix ... Noted Open
14 Jul 2026 Procurement Plan - July 2026Resolved : Cabinet approved the following: 1. Specialist Support and Therapies services: a) Approve commencement of p... Approved Open
14 Jul 2026 Updated West London Waste Plan - Regulation 19 Consultation and Submission to Secretary of State for ExaminationResolved : Cabinet recommended to Borough Council: 1. To approve the ‘Regulation 19’ publication of the Proposed Subm... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies