Cabinet, Tuesday 15 November 2016 at 7.00pm

REG 442 - Hogarth's House Mulberry Project - Updates and Approvals

Noted Executive 3 papers

Cabinet noted this item on Tuesday 15 November 2016. Below is the council's own wording, with the papers it was decided on.

Item56

Resolved

A) That Cabinet noted the September 2016 submission of a Round 2 Heritage Lottery Fund bid for the building of a learning centre and associated improvements to the garden at Hogarth’s House – a decision is expected at the end of November 2016. B) That Cabinet agreed the recommendations of the report as follows: 1. Cabinet approved the underwriting of the fund-raising strategy for the Hogarth’s House Mulberry Project capital works 2016-19 in the sum of £360,000, in support of a grant application for £1.35 million Heritage Grant from the Heritage Lottery Fund (HLF), as HLF needs this commitment in order to decide on the Grant. 2. Cabinet agreed the implementation of future governance arrangements for Hogarth’s House – reported in REG 296 September 2015- for the period following November 2018 (the date of the end of the Carillion contract) on behalf of the Council, by authorising the Executive Director for Regeneration, Economic Development and Environment (the ‘Director’), in consultation with the Cabinet Member for Public Health and Leisure, to complete the Articles of Association and all necessary documentation for transfer of management to a repurposed Hogarth’s House Trust. 3. Cabinet agreed to set core support grant for Hogarth’s House Trust from 2018-19, based on the cost of Carillion’s management of the facility and a 25% cost reduction from December 2018. A) That Cabinet noted the September 2016 submission of a Round 2 Heritage Lottery Fund bid for the building of a learning centre and associated improvements to the garden at Hogarth’s House – a decision is expected at the end of November 2016. B) That Cabinet agreed the recommendations of the report as follows: 1. Cabinet approved the underwriting of the fund-raising strategy for the Hogarth’s House Mulberry Project capital works 2016-19 in the sum of £360,000, in support of a grant application for £1.35 million Heritage Grant from the Heritage Lottery Fund (HLF), as HLF needs this commitment in order to decide on the Grant. 2. Cabinet agreed the implementation of future governance arrangements for Hogarth’s House – reported in REG 296 September 2015- for the period following November 2018 (the date of the end of the Carillion contract) on behalf of the Council, by authorising the Executive Director for Regeneration, Economic Development and Environment (the ‘Director’), in consultation with the Cabinet Member for Public Health and Leisure, to complete the Articles of Association and all necessary documentation for transfer of management to a repurposed Hogarth’s House Trust. 3. Cabinet agreed to set core support grant for Hogarth’s House Trust from 2018-19, based on the cost of Carillion’s management of the facility and a 25% cost reduction from December 2018.
Word for word from the decision Hounslow published for this meeting. Source: democraticservices.hounslow.gov.uk

Follow this further

Built from Hounslow's papers

What the report saysPro

Report to Cabinet, 8 pages

Report for: ACTION

Contains Confidential No or Exempt Information

Title Hogarth’s House Mulberry Project – Updates and Approvals Member Reporting Councillor Corinna Smart – Portfolio Holder Contact Details David Stockdale – Heritage Services & Major Projects Manager – 0208 583 3823 – [email protected]

Imran Choudhury- Director of Public Health-0208 583 [email protected]

For Consideration By Cabinet Date to be Considered 15.11.2016 Implementation Date if 28.11.2016 Not Called In Affected Wards (All) Chiswick Riverside Keywords/Index Hogarth’s House, Regeneration, Governance, Heritage Lottery Fund

1. Details of Recommendations

The Cabinet is asked to note the September 2016 submission of a Round 2 Heritage Lottery Fund bid for the building of a learning centre and associated improvements to the garden at Hogarth’s House – decision at end of November 2016, and to agree the following

1. Approve the underwriting of the fund-raising strategy for the Hogarth’s House Mulberry Project capital works 2016-19 in the sum of £360,000, in support of a grant application for £ 1.35 million Heritage Grant from the Heritage Lottery Fund (HLF), as HLF needs this commitment in order to decide on the Grant.

2. Agree the implementation of future governance arrangements for Hogarth’s House – reported in REG 296 September 2015 - for the period following November 2018 (date of end of Carillion contract) on behalf of the Council, by authorising the Executive Director for Regeneration, Economic Development and Environment (the ‘Director’) in consultation with the Lead Member for Leisure to complete the Articles of Association and all necessary documentation for transfer of management to a repurposed Hogarth’s House Trust. 3. Set core support grant for Hogarth’s House Trust from 2018-19, based on the cost of Carillion’s management of the facility and a 25 % cost reduction from December 2018.

If the recommendations are adopted, how will residents benefit? Benefits to residents and reasons why they will Dates by which they can benefit, link to Values expect to notice a difference

Innovating – Learning from experience Improved facilities, access The HLF “Hogarth’s House Mulberry Project” will and services at Hogarth’s change how this service is delivered, improving House by 2019-20. facilities and visitor access to the House & providing a valuable resource for local schools.

Spending wisely – every penny counts

Transferring operations of the House to Hogarth’s 2018-19 House Trust to deliver improved management and increase eligibility for raising external funds.

Supporting the Trust with a core service grant to 2019-23 make the House sustainable and reduce operational costs within 5 years.

2. Report Summary

1. This report deals with the proposed development of Hogarth’s House historic house to include a new learning centre and refurbished gardens.

2. A Round 2 submission has been made to the Heritage Lottery Fund for £ 1.35 million, and they require the Council to underwrite the charitable and private fund-raising element (£ 360,000) for capital works prior to any decision being made.

3. These recommendations are being made because the House requires improvement to its inadequate facilities and because it needs a sustainable management model, as proposed by the commissioned Business Plan (Appendix B, available for reference as an electronic file only ). This Business Plan is a requirement of the HLF bid process and the commissioning was approved by Cabinet in September 2015, REG 296.

3. Reason for Decision and Options Considered

3.1Background 3.1 Hogarth’s House (building and garden) the former country home of the English artist William Hogarth is held by Hogarth’s House Trust (registered charity no 1010069) for which the Council is currently the sole trustee. The property is held for the general purposes of the charity – primarily, ‘to hold the house and associated lands for the inhabitants of the county of Middlesex’.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Strategy and Tracker for Project Fundraising 2 0Appendix A 2 pages Download
PDF
ELECTRONIC Appendix B Mulberry Garden Project Business Plan Final ReportAppendix 91 pages Download
PDF
REG 442: Hogarth's House Mulberry Project: Updates and ApprovalsReport 8 pages DownloadRead as text

More from Hounslow Cabinet

All decisions
MeetingDecisionOutcome
14 Jul 2026 Budget Outturn 2025-2026Resolved : Cabinet agreed to the following: General Fund 1. Approve the General Fund net revenue o verspend of £1.6m ... Agreed Open
14 Jul 2026 Delivery Plan Monitoring - Q4 2025/26Resolved : Cabinet agreed to: 1. Note progress to date with the programmes within the People Portfolio as set out in ... Agreed Open
14 Jul 2026 Quarterly Performance Reporting 2025-2026 (Q4)Resolved : Cabinet noted the corporate performance report for Quarter 4 (January to March 2026) detailed in Appendix ... Noted Open
14 Jul 2026 Procurement Plan - July 2026Resolved : Cabinet approved the following: 1. Specialist Support and Therapies services: a) Approve commencement of p... Approved Open
14 Jul 2026 Updated West London Waste Plan - Regulation 19 Consultation and Submission to Secretary of State for ExaminationResolved : Cabinet recommended to Borough Council: 1. To approve the ‘Regulation 19’ publication of the Proposed Subm... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies