Resolved
That the Audit & Governance Committee noted the amended Corporate Risk Register at Appendix 1.
Audit and Governance Committee noted this item on Thursday 13 March 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Audit & Governance Committee noted the amended Corporate Risk Register at Appendix 1.
Corporate Risk Register Quarterly Update Q3 - Risk Update New RiskID Risk description Cause and consequence Mitigations CLT Risk Owner Has the nature of the risk (the cause and/ or Effectiveness of existing mitigations/ current Further action - any new mitigations/ controls Impact Likelihood Q3 2024/25 Direction of What has caused the risk (may be multiple)? consequence) changed? controls Residual Risk Score Travel What are the potential consequences of the risk? (from previous Q)
RHES0001 Failure to deliver Recovery and growth will require significant Implementation of the Opportunity Hounslow Business Case Assistant Chief Updated wider context it sits within - very Added in focus on partnership working to unlock Partnership working; Business Case for Growth Significant Possible 12 Medium 0 regeneration and growth regeneration, providing greater business for Growth. Additional officer capacity to promote Executive difficult delivery environment and maximise limited resources strategy context High ambitions opportunities; increased numbers of good jobs and regeneration ambitions. Progressing work on Local Plan to Communities & homes; improvements to residents’ employment ensure we have an up to date development plan that Strategy (interim) prospects; and improvements to the environment and enables regeneration, sustainable development and growth. public realm. Failure to deliver these ambitions Production of masterplans, SPDs, guidance that enables hamstrings sustainable growth and limits our regeneration, development and growth. Focus on ambitions for the Borough as set out in the partnership working with private and public sector. Opportunity Hounslow Business Case for Growth, but is constrained by a very difficult delivery environment, limited liquidity of key partners and limited resources meaning partnership working is key.
RHES0002 Failure to meet landlord New Legislation is in place in respect of Building Safety Robust compliance monitoring arrangements in place for all Director of No material change to the corporate level risk. No material change to the corporate level risk. Recruitment and retention of compliance staff Significant Possible 12 Medium 0 health and safety and Fire Safety providing new responsibilities, risks and Council properties that are regularly reported and reviewed. Communities The BSR requested the additional 2 cases (as This risk continues to be managed, with monthly remains challenging, with an industry shortage of High requirements (maintenance) obligations to the London Borough of Hounslow, Plans have been developed for implementing the new (interim) anticipated) and these have been submitted. performance reviews and close liaison with skills, leading to competitive salaries. for Council housing tenants / Members, Colleagues and Residents. This Legislation requirements of the Building Safety, and Fire Safety Bills, Additional questions have been received from Housing Tenancy Management colleagues. Continue to manage risk and maintain robust properties consists: (1) The Fire Safety Act 2021; (2) The Building and programmes of activity are currently underway to effect the BSR (w/c 3/2/25). monitoring arrangements. Safety Act 2022 and (3) The Fire Safety (England) those plans. The BSR has advised that further cases will be Regulations 2022. requested in Q3 / Q4. Preparation work for this has commenced.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Corporate Risk Register Update_FinalReport | 5 pages | DownloadRead as text |
PDF |
Risk ManagementReport | 5 pages | Download |
Follow Audit and Governance Committee at Hounslow and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Sep 2026 | Apologies for absence, declarations of interest or any other communication from MembersThere were no apologies for absence, declarations of interest or other communications. | Decided | Open |
| 8 Sep 2026 | Minutes of the meeting held on 3 February 2026The minutes of the meeting held on 3 February 2026 were agreed as an accurate record. | Agreed | Open |
| 8 Sep 2026 | Matters arising from the minutesThere were no matters arising from the minutes. | Decided | Open |
| 8 Sep 2026 | Quarterly Monitoring of Corporate Risk Register (Q1, 2026-27)Please see the report by Sarah Filby, Director Strategy, Performance & Commissioning (agenda item 4) The report was p... | Decided | Open |
| 8 Sep 2026 | Treasury Management Annual Report 2025/26Please see the report by Jake Bacchus, Executive Director of Finance and Resources (agenda item 5) The report was pre... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.