Resolved : · Cabinet noted the findings of the options appraisal report in the exempt Appendix 1 of the submitted report to identify an alternative delivery mechanism for the Charlton House and Albany House Estate redevelopment. · Cabinet approved the preferred option identified in the submitted report (Option 2), involving the appointment of development management advisors and multi-disciplinary design team via a direct call off procurement framework; to refine the scheme within the existing planning consent. · Cabinet approved utilisation of the budget, as outlined in exempt Appendix 2 of the submitted report, from the HRA Council House building capital programme contingency budget for procurement of development management advisors and multi-disciplinary design team and to refine the scheme within confines of the existing planning consent. · Cabinet delegated authority to the Director of Regeneration and Economic Growth to approve and award procured contracts for development management advisors and multi-disciplinary design team and enter into any necessary associated legal documentation. · Cabinet noted that a report would be brought to Cabinet to present the outcome of the redesign work with a revised cost estimate for the complete construction works and retender process.
Word for word from the decision Hounslow published for this meeting.Source: democraticservices.hounslow.gov.uk
Contains Confidential Y (Exempt or Exempt Information information in Appendices 1 and 2)
Cabinet Key Decision Y
Charlton House and Albany House Estate Regeneration Report Title Delivery Plan
Cllr Tom Bruce Member Reporting Deputy Leader of the Council and Portfolio holder for Assets, Regeneration and Development
Peter O’Brien Contact Details Director of Regeneration and Economic Growth [email protected]
For Consideration By Cabinet
Date to be Considered Tuesday 13th May 2025
Deadline for call-in Wednesday 21st May 2025
Implementation Date Thursday 22nd May 2025 (if not Called In)
Affected Wards Brentford West
Peter O’Brien Approved by Director of Regeneration and Economic Growth 1. Recommendations
Cabinet is asked to:
1.1Note the findings of the options appraisal report in confidential Appendix 1 to identify an alternative delivery mechanism for the Charlton House and Albany House Estate redevelopment.
1.2Approve the preferred option identified in the report (option 2), involving the appointment of development management advisors and multi-disciplinary design team via a direct call off procurement framework; to refine the scheme within the existing planning consent.
1.3Subject to approval of Recommendation 1.2, to approve utilisation of the budget, outlined in confidential Appendix 2, from the HRA Council House building capital programme contingency budget for procurement of development management advisors and multi-disciplinary design team and to refine the scheme within confines of the existing planning consent.
1.4Delegate authority to the Director of Regeneration and Economic Growth to approve and award procured contracts for development management advisors and multi-disciplinary design team and enter into any necessary associated legal documentation.
1.5Note that a report will be brought to Cabinet to present the outcome of the redesign work with a revised cost estimate for the complete construction works and retender process.
2. Report Summary
2.1Council’s Housing Estate Regeneration Programme, which includes Charlton House and Albany House Estate (CHAH), was approved by Cabinet in January 2020. CHAH residents supported the estate’s regeneration, voting overwhelmingly in favour of the estate’s redevelopment in the February 2021 resident’s ballot.
2.2Detailed planning permission was granted for the scheme in August 2022 for the demolition of the building on site and the provision of mixed-use development consisting of residential and commercial units.
2.3In January 2023 Cabinet approved an indicative budget for the scheme in the Housing Revenue Account (HRA) Business Plan and the Council Housing Delivery Plan 2022-26.
2.4A contractor was appointed following the first stage of a two-stage tender process; entering into a Pre-Construction Services Agreement (PCSA) with the Council in November 2023. The PCSA involved collaboration with the Council’s project team to develop a final design and price to deliver the construction of the development.
2.5The contractor was required to submit an 80% cost certainty report, as part of the PCSA programme, that would be used to approve the construction budget at Cabinet.
2.6Since the appointment of the PCSA additional funding has been secured for the scheme from both the GLA and the Ministry of Housing, Communities & Local Government (MHCLG), lessening the burden on the HRA.
2.7The 80% report cost certainty report from the PSCA contractor confirmed that the contractor’s construction cost proposal would significantly exceed the project budget allocated within the 2023 HRA Business Plan. Coupled with increased costs of borrowing to fund schemes since 2023 proceeding with the project as currently designed is no longer affordable to the HRA.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Delivery Plan Monitoring - Q4 2025/26Resolved : Cabinet agreed to: 1. Note progress to date with the programmes within the People Portfolio as set out in ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.