London Borough of Hounslow
Cabinet, Monday 16 March 2026 at 7.00pm

Charlton House and Albany Estate Regeneration Delivery Plan

Approved Executive 2 papers

AI summaryHounslow Cabinet approves direct delivery of 182 council homes at Charlton and Albany Estate, with delegated authority to award the main contractor contract within the approved budget.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApproved182 council rent homes plus ground floor commercial space
MoneyBudget in Confidential Appendix 1Specific construction cost not disclosed in open papers
What happens nextTender evaluation to April 2026Start on site targeted for September 2026
Who it affectsEstate residents and waiting listOver 4,400 households on the council waiting list

What was decided

Cabinet approved direct delivery of 182 council rent homes plus ground floor commercial space at the Charlton and Albany Estate. Report P2, 2.3

Cabinet approved a total scheme construction budget and added scheme budgets from 2026/27 onwards to the HRA Council House Building capital programme, with figures set out in Confidential Appendix 1. Report P2, 6.1, 13.1

Cabinet delegated authority to the Director of Regeneration and Economic Growth to award the main contractor and any required professional advisor contracts, provided the successful bid does not exceed the construction cost element within the approved budget; bids over budget will return to Cabinet. Report P3

Why

The Council wants to keep full control over design, tenure mix, sustainability standards and long term asset management, and to secure all 182 homes as genuinely affordable council rent. Report P22, P23, 2.3

Estate residents voted 87.1% in favour of regeneration on an 81.4% turnout in a ballot held in February 2021, providing a strong mandate for a council led model. Report 3.2

Direct delivery allows the Council to use secured Greater London Authority and London Economic Regeneration Fund grant funding that is contingent on construction starting by September 2026. Report 2.3, 3.10, 7.4

What happens next

Complete tender evaluation between March and April 2026, with the tender return date of 9 March 2026 already set. Report P59, 2.6

Secure a decision on the Section 73 Minor Material Amendment planning application between April and June 2026. Report P60, 3.9

Appoint the main contractor in June 2026 and start on site by September 2026, otherwise risk losing GLA grant funding. Report P61, P62, 7.4, P38

The money

  • £3m HRA savings programme HRA savings required in 2026/27 and 2027/28 to support the borrowing headroom for this scheme Report P69
  • £1 per week Rent convergence increase planned for 2027/28 Report P68
  • £2 per week Rent convergence increase planned for 2028/29 Report P68

Options considered

  • Chosen: Direct delivery by the Council (recommended). Retains control over design, tenure and long term asset management; secures 100% affordable council rent homes; leverages GLA and LERF grant funding. Report 4.2, P22, P23
  • Rejected: Disposal of the site to a private developer on the open market. Would generate a capital receipt but the Council would lose control over design, tenure and long term ownership, and affordable housing would depend on planning policy compliance only. Report P25, P26, P27
  • Rejected: Disposal of the site to a Registered Provider. May secure nomination rights but identifying and appointing a suitable provider would extend the programme and the Council would lose direct control of delivery. Report P28, P29, P30
  • Rejected: Joint venture with a private developer or Registered Provider. Would share financial risk but require market engagement, potentially a revised planning application, and the proportion of affordable homes would depend on negotiated viability. Report P31, P32, P33

Implications

  • Financial: GLA and LERF grant funding is conditional on construction starting by September 2026; any delay risks forfeiting the funding and the viability of the project. Report 3.10, 7.4, P38
  • Financial: The 2026 HRA Business Plan includes additional borrowing headroom that depends on rent increases of CPI plus 1% from September, rent convergence, delivery of the £3m HRA savings programme, and securing expected GLA grant. Report 13.4, P67, P68, P69, P70
  • Legal: The Council used Compulsory Purchase powers under section 226 of the Town and Country Planning Act 1990, with home loss and disturbance payments made under section 203 of the Housing and Planning Act 2016; the redevelopment relies on the power to build new houses under section 9(1) of the Housing Act 1985. Report 7.1, 7.2
  • Legal: Procurement of professional services and the main contractor must comply with the Procurement Act 2023 and the Council's Contract Procedure Rules. Report 7.3
  • Equalities: An equalities impact assessment completed in February 2023 found the new neighbourhood would provide good living conditions, improved retail spaces, and public realm improvements that could reduce stigma and postcode discrimination. Report 8.2, 8.3
  • Climate: The development is expected to exceed Building Regulations Part L and supports the Council's Climate Emergency Action Plan; a carbon offset is included in the Unilateral Undertaking carried forward into the Section 73 amendment. Report 9.1, 9.2
  • Risk: Key risks include insufficient tender returns, tender prices exceeding the approved budget, loss of GLA grant funding if construction is delayed beyond September 2026, and rejection of the Section 73 application. Report P36, P37, P38, P39

Who and where

  • Current and former residents of Charlton House and Albany Estate, who have been rehoused to enable demolition Report 2.1, 3.3, 7.1
  • Households on the council housing waiting list, with over 4,400 households waiting as of July 2025 Report 3.1
  • Future tenants of the 182 new council rent homes, with over 30% of homes being 3 bedroom or larger Report 2.3, 3.8
  • Existing and incoming ground floor commercial tenants Report 8.2
  • Surrounding neighbourhood residents who will use the new public realm and over 2,500m² of green space Report 3.8, 8.3

Timeline

  • January 2020: Cabinet approved the Housing Estate Regeneration Programme including CHAH Report 2.1, 3.2
  • February 2021: Estate ballot held, with 87.1% in favour on an 81.4% turnout Report 3.2
  • August 2022: Detailed planning permission granted for the redevelopment Report 2.1, 3.2
  • February 2023: Cabinet approved the Compulsory Purchase Order and Delivery Plan Report 3.3
  • October 2023: Cabinet approved budget for the Pre Construction Service Agreement contractor, consultants and demolition contractor Report 3.4
  • May 2025: Demolition of existing buildings commenced
  • May 2025: Cabinet approved appointment of a new professional team to refine the design Report 3.6
  • October 2025: Cabinet approved initiation of the procurement process for a main contractor Report 3.10
  • January 2026: Section 73 Minor Material Amendment planning application submitted Report 3.9
  • By March 2026: Completion of demolition of existing buildings
  • 9 March 2026: Tender return date for the main contractor procurement
  • March to April 2026: Completion of tender returns and evaluation Report P59, 2.6
  • April to June 2026: Expected approval of the Section 73 planning application Report P60
  • June 2026: Expected appointment of the main contractor (subject to planning) Report P61
  • September 2026: Targeted start on site to retain GLA grant funding Report P62, 7.4

Plain English for the jargon

  • HRA: Housing Revenue Account, the ringfenced account that funds council housing in England
  • CPO: Compulsory Purchase Order, used by the Council to acquire the land needed for redevelopment
  • GLA: Greater London Authority, which is providing grant funding for the scheme
  • LERF: London Economic Regeneration Fund, the second external grant source for the scheme
  • Section 73 application: A planning application to make minor material amendments to an existing planning permission
  • PCSA: Pre Construction Service Agreement, an early contractor engagement arrangement terminated after RIBA Stage 4 design
  • RIBA Stage 4: Technical Design stage in the Royal Institute of British Architects work plan
  • RP: Registered Provider, a social housing landlord
  • JV: Joint Venture, a partnership delivery model
  • UU: Unilateral Undertaking, a planning obligation agreement containing the carbon offset
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12

Resolved

Resolved : · Cabinet approved direct delivery of the scheme at Charlton and Albany House to provide 182 homes for Council rent, plus ground floor commercial space. · Cabinet approved a total scheme budget for the construction phase of the scheme and the addition of the scheme budgets from 2026/27 onwards to the HRA Council House Building capital programme with the budget and financing set out in Confidential Appendix 1 of the submitted report. Provided that the successful bid did not exceed the construction costs element within the budget envelope approved by Cabinet, Cabinet delegated authority to the Director of Regeneration and Economic Growth to approve and award contracts for a main contractor, and any other professional advisors as and when required, and enter into any necessary associated legal documentation; and Cabinet noted that, should the bid exceed the construction costs element within the budget envelope, this matter would be reported to Cabinet.
Word for word from the decision Hounslow published for this meeting. Source: democraticservices.hounslow.gov.uk

Follow this further

Built from Hounslow's papers

What the report saysPro

Report to Cabinet, 14 pages

Recommendations

Cabinet is asked to:

1. Approve direct delivery of the scheme at Charlton and Albany House to provide 182 homes for Council rent, plus ground floor commercial space. 2. Approve a total scheme budget for the construction phase of the scheme and the addition of the scheme budgets from 2026/27 onwards to the HRA Council House Building capital programme with the budget and financing set out in Confidential Appendix 1.

3. Provided that the successful bid does not exceed the construction costs element within the budget envelope approved by Cabinet, delegate authority to the Director of Regeneration and Economic Growth to approve and award contracts for a main contractor, and any other professional advisors as and when required and enter into any necessary associated legal documentation; and note that if the bid exceeds the construction costs element within the budget envelope, this matter will be reported to Cabinet. 2. Report Summary

2.1The Charlton House and Albany House (CHAH) redevelopment is a flagship regeneration project for the London Borough of Hounslow. The Council’s Housing Estate Regeneration Programme, which includes CHAH, was approved by Cabinet in January 2020. CHAH residents supported the estate’s regeneration, voting overwhelmingly in favour of the estate’s redevelopment in the February 2021 resident’s ballot. Detailed planning permission was granted for the scheme in August 2022 for the demolition of the existing buildings and the provision of a mixed-use development consisting of residential and commercial units. The new development forms part of the Council’s commitment to deliver 1,000 new council homes. The scheme replaces outdated and non- compliant housing stock with high-quality, energy-efficient homes for social rent, alongside retail units and green space that support a vibrant, inclusive neighbourhood. This project is aligned with the Council’s Corporate Plan 2022– 2026, delivering against multiple strategic outcomes including a liveable Hounslow.

2.2This report outlines the available delivery options for the CHAH redevelopment and presents the corresponding recommendations. It summarises the progression of the project through key stages including design refinement, cost assessment, feasibility work, planning amendments, and confirmation of resident support each undertaken to ensure the scheme remains achievable within the parameters of the 2026 HRA Business Plan. Cabinet is asked to consider the options appraisal and background commercial details provided in Confidential Appendix 1.

2.3The preferred option is for the Council to directly deliver the estate regeneration. This approach secures full control over all aspects of the scheme, guarantees that all 182 new homes will be genuinely affordable Council housing, and enables the Council to optimise the use of secured external funding streams, including grants from the Greater London Authority (GLA) and the London Economic Regeneration Fund (LERF).

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Charlton House and Albany Estate Regeneration Delivery Plan: Appendix 2Appendix 1 pages Download
PDF
Charlton House and Albany Estate Regeneration Delivery PlanReport 14 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Hounslow

Search all
  1. Charlton House and Albany Estate Regeneration Delivery PlanThis decision
  2. Charlton House and Albany House Estate Regeneration Delivery PlanNoted
  3. Charlton House, Albany Rd, BrentfordApproved
  4. Charlton House and Albany House - Osier Court stock transferApproved
  5. Regeneration of Charlton House and Albany House - Approval to make Compulsory Purchase Order and Delivery PlanApproved
  6. Charlton House, Albany House & Osier Court, Albany Road, BrentfordRefused

More from Hounslow Cabinet

All decisions
MeetingDecisionOutcome
14 Jul 2026 Budget Outturn 2025-2026Resolved : Cabinet agreed to the following: General Fund 1. Approve the General Fund net revenue o verspend of £1.6m ... Agreed Open
14 Jul 2026 Delivery Plan Monitoring - Q4 2025/26Resolved : Cabinet agreed to: 1. Note progress to date with the programmes within the People Portfolio as set out in ... Agreed Open
14 Jul 2026 Quarterly Performance Reporting 2025-2026 (Q4)Resolved : Cabinet noted the corporate performance report for Quarter 4 (January to March 2026) detailed in Appendix ... Noted Open
14 Jul 2026 Procurement Plan - July 2026Resolved : Cabinet approved the following: 1. Specialist Support and Therapies services: a) Approve commencement of p... Approved Open