AI summaryHounslow Cabinet approves Golden Mile Investment Framework and £1,115,000 to start Phase 1 feasibility work, with delegated procurement authority up to £1m.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedPhase 1 Delivery Action Plan funded, procurement delegated
Money£1,115,000£950k capital, £50k S106, £115k CEZ grant
What happens nextPhase 1 feasibility studiesEach project needs separate business case
Who it affectsGolden Mile corridor, HounslowStrategic regeneration framework area
What was decided
Cabinet approved the Golden Mile Investment Framework as Appendix 1, setting a strategic basis for future investment and planning decisions. Report 13.1
Cabinet approved £1,115,000 of funding for the Phase 1 Delivery Action Plan and delegated authority to the Director for Regeneration and Economic Growth for procurement and contractual decisions under £1m. Report 12.1
Why
The framework is intended to provide a coordinated strategic approach to attract investment along the Golden Mile and direct it to community benefit, supported by longstanding partnership work with the GLA and TfL. Report 7.2, 10.1
Approving the framework signals strategic intent without committing the Council to specific projects or financial contributions; each intervention will still need its own business case, financial appraisal and delegated decision. Report 6.3, 6.6
What happens next
Phase 1 projects will move into feasibility, with full business cases and separate approvals required before delivery. Further Equality Impact Assessments and health assessments will be undertaken as projects progress. Report 6.3, 8.3
Officers will prioritise external grant funding over Council capital and explore UKSPF, CIL and S106 sources to reduce further capital investment. Report 6.4
The money
£1,115,000 Total funding for Phase 1 Delivery Action Plan projects
£950,000 Allocation from Area Regeneration budget, treated as capital expenditure Report 6.2, 12.1
£50,000 Section 106 funding supplementing the allocation Report 12.1
£115,000 CEZ grant funding supplementing the allocation Report 12.1
Options considered
Chosen: Approve the Golden Mile Investment Framework and £1,115,000 funding with delegated procurement authority under £1m. Provides a coordinated framework to attract investment; framework approval does not bind the Council to specific projects Report 6.6
Implications
Financial: Risks include funding dependency on external sources, potential cost overruns, and capital being written off as revenue if projects are not delivered. Report 6.5, P6, P7, P8
Legal: The framework is non-statutory but may be a material consideration in planning. Future delivery must comply with procurement, land transaction, subsidy control, and governance rules. Report 7.1, 7.2
Equalities: EDI principles are embedded in the framework; further Equality Impact Assessments will be required as individual projects progress. Report 8.1, 8.3
Climate: Net Zero and sustainability principles are to be embedded in design and feasibility, including green infrastructure, SuDS, active travel and District Heat Network opportunities. Report 9.2, 9.3
Risk: Reliance on external funding may affect delivery timelines and scope; alternative funding sources such as UKSPF, CIL and S106 will be explored. Report 6.4, 6.5
Who and where
Communities and businesses along the Golden Mile corridor in Hounslow Report 8.1, 10.1
Underrepresented groups targeted by inclusive economic growth, training and creative enterprise actions Report 8.1
The Council as landowner or asset holder on sites within the Golden Mile Report 9.4, 10.1
Timeline
Cabinet 17 June 2025: Earlier Cabinet approval of £950,000 East Area Regeneration capital funding now being allocated to Phase 1 projects Report 12.1
Phase 1 period (feasibility): Feasibility studies for Phase 1 strategic priority projects, with business case development to follow Report 6.3, 11.1
Plain English for the jargon
GMIF: Golden Mile Investment Framework, the strategic document approved as Appendix 1
CEZ: Cleaner Energy Zone, referenced as a source of £115,000 grant funding
UKSPF: UK Shared Prosperity Fund, an external funding source officers may seek
CIL: Community Infrastructure Levy, an external funding source officers may seek
SuDS: Sustainable Drainage System, to be promoted in Phase 1 design work
EqIA: Equality Impact Assessment, to be carried out as individual projects progress
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6
Resolved
· Cabinet approved the Golden Mile Investment Framework (GMIF) – Appendix 1 of the submitted report. · Cabinet approved the allocation of £1,115,000 funding to support the implementation of the Delivery Action Plan for Phase 1 strategic priority projects as set out in Exempt Appendix 3 of the submitted report. Cabinet granted delegated authority to the Director for Regeneration and Economic Growth to approve all procurement and contractual decisions related to this programme under £1m, in compliance with the Contract Procedure Rules.
Word for word from the decision Hounslow published for this meeting.Source: democraticservices.hounslow.gov.uk
Contains Y – Exempt Confidential or information in Exempt Information Appendix 3 - LGA 1972 Sch 12A para 3 applies
Cabinet Key Y Decision
Report Title Golden Mile Investment Framework
Deputy Leader of the Council and Portfolio holder for Member Reporting Assets, Regeneration and Development Councillor Tom Bruce Peter O’Brien Contact Details Director of Regeneration and Economic Growth
For Consideration By Cabinet
Date to be Considered 20 January 2026
Deadline for call-in 28 January 2026
Implementation Date 29 January 2026 (if not Called In)
Brentford East, Brentford West, Chiswick Gunnersbury, Affected Wards Chiswick Riverside, Osterley and Spring Grove
Peter O’Brien, Director of Regeneration and Economic Approved by Growth 1. Recommendations
Cabinet is asked to:
1. Approve the Golden Mile Investment Framework (GMIF) – Appendix 1.
2. Approve the allocation of £1,115,000 funding to support the implementation of the Delivery Action Plan for Phase 1 strategic priority projects as set out in Exempt Appendix 3.
3. Grant delegated authority to the Director for Regeneration and Economic Growth to approve all procurement and contractual decisions related to this programme under £1m, in compliance with the Contract Procedure Rules.
2. Report Summary
2.1This report presents the Golden Mile Investment Framework (GMIF) as the strategic case for investment, setting out a coordinated vision and delivery approach for the Golden Mile, one of London and the UK’s most significant growth and regeneration areas. The GMIF aligns with the Council’s priorities, the London Growth Plan, and national policy, supported by a robust evidence base.
2.2Following Cabinet approval of the Business Case for Growth in 2024, the Golden Mile (Great West Corridor) was identified as a key regeneration opportunity to transform not only Brentford, Syon Lane, Boston Manor, Chiswick, but the wider borough, as well as West London.
2.3As the borough’s largest economic growth area, this report unveils a 15-year vision with a clear roadmap for place-shaping and social and economic transformation. The GMIF provides strategic priorities for public and private investment, with Phase 1 (0–5 years) outlining projects and programmes to stimulate investment from partners, government, and the private sector.
2.4The GMIF identifies key strategic ambitions for the Golden Mile:
1. Become the leading Creative-Tech Innovation District and build the ecosystem across key growth sectors of digital media and production and advanced technologies.
2. Be an exemplar centre of Knowledge Excellence, Skills and Partnerships in AI, Aviation, Biomedical sciences.
3. Elevate the Golden Mile as a London destination for thriving culture, leisure, immersive experiences and sport.
4. Transform the A4 corridor from motorways to avenue like streets with green neighbourhoods to support existing and future communities to live, learn and create. 5. Regenerate the River Brent Corridor as a vital place for nature, well-being and as part of the new West London Regional Park.
6. Deliver and connect the new West London Orbital (WLO) Railway line to the wider London sub regional, Southeast and national rail network via HS2 and the Heathrow economic zone alongside enhanced transport connectivity.
2.5The scale and ambition of the regeneration will deliver renewed and inclusive growth, not only at a regional scale but at a national and international level. As the Council does not own many assets within the Golden Mile beyond the public realm, highways, parks and Brentford Fountain Leisure Centre, strong partnership working is essential for the Council to optimise its role as the key enabler and convenor.
2.6The Golden Mile has the potential to deliver both physical and social economic transformation by 2041:
• Delivery of 7,500 new homes ranging to 14,000 to meet the borough’s housing requirements.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Delivery Plan Monitoring - Q4 2025/26Resolved : Cabinet agreed to: 1. Note progress to date with the programmes within the People Portfolio as set out in ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.