OutcomeApprovedConvert two tennis courts to three padel courts per site
Money£950,000Total project cost, funded from general fund capital unallocated budget
What happens nextCompletion expected December 2026Construction planned September to November 2026
Who it affectsHanworth and Isleworth Leisure Centres usersTwo existing underused tennis courts at each site to be converted
What was decided
Cabinet approved delivery of the project to convert two underused tennis courts into three padel courts at both Hanworth and Isleworth Leisure Centres, with canopies for year-round play. Report 6.1
Cabinet approved a £950,000 project budget from the general fund capital programme unallocated budget, and an initial £90,000 drawdown for design and planning. Report 6.1, 6.2
Cabinet delegated authority to officers to approve further budget drawdowns, to commence procurement and award contracts, and to vary the service agreements with Lampton Leisure. Report 6.2, 6.6, 7.4
Why
The investment is expected to generate £1.44 million of additional income over four years, reducing the net cost of operating the council's leisure centres and supporting long-term financial sustainability. Report P22, 10.1
The project repurposes existing hardstanding rather than building on undeveloped land, while expanding opportunities for physical activity, social interaction and inclusion across age groups and abilities. Report 9.1, 8.1, 8.2
Option B, the full conversion at both sites, was assessed as offering the greatest revenue potential and consistent year-round availability compared with doing nothing, a phased pilot or a private partnership. Report P5, P7, P9, P10
What happens next
Planning and design will run from February to May 2026, followed by procurement in June to July 2026, mobilisation in August 2026, construction from September to November 2026, and commissioning and launch in December 2026. Report P46, P47, P48, P49, P50
Further budget drawdowns will require approval of an Outline and Full Business Case, and an Equality Impact Assessment will be completed at the Full Business Case stage. Report 6.2, 8.4
The contract with Lampton Leisure will be varied to reflect the financial implications of the investment, including income sharing and operational responsibilities. Report 6.6, 7.4
The money
£950,000 Total estimated capital cost for six padel courts, including a 10% contingency, funded from the General Fund Capital Programme unallocated budget Report 6.1
£90,000 Initial drawdown for the next phase of design and planning work Report 6.2
£1.44 million Projected additional income over four years from memberships, pay-as-you-go bookings and coaching Report P22, 10.1
£215,000 Projected income in Year 1 Report P22
£518,000 Projected income in Year 4 Report P22
£7,000 Routine maintenance cost in Year 1, rising with inflation Report 6.4
£47,500 Minimum Revenue Provision per year under the Treasury Management Strategy Report 6.4
Options considered
Rejected: Option A: Do Nothing, retain existing tennis courts. No capital investment required, but misses opportunity to provide padel courts and generate additional income Report P2, P3
Chosen: Option B: Convert two tennis courts to three padel courts at each site, with canopies for year-round play (recommended). Highest capital investment but offers the greatest revenue potential and consistent availability Report P4, P5, P10
Rejected: Option C: Phased pilot of two padel courts at one site before full rollout. Lowers financial risk and allows early learning but delays full benefits; later expansion may cost more and face market saturation Report P6, P7
Rejected: Option D: Partnership delivery with a private operator under a revenue-share model. Quicker delivery and lower capital outlay, but limits council control over pricing, programming and service quality, reduces income share, and limits integration with Lampton Leisure services Report P8, P9
Implications
Financial: The investment is expected to generate £1.44 million of additional income over four years, reducing the net cost of operating the council's leisure centres. Report P22, 10.1
Financial: Minimum Revenue Provision of £47,500 per year will be required under the council's Treasury Management Strategy, with useful life of the courts set at 20 years. Report 6.4
Legal: Works will be procured through a compliant framework agreement in line with the council's Constitution and Contract Procedure Rules, with further legal advice on subsidy to follow as the project progresses. Report 7.2, 7.3, 7.4, 7.5
Equalities: Inclusive design will include step-free access, adaptable equipment and clear wayfinding to comply with the Equality Act 2010, with concessions and pay-as-you-go options to maintain affordability. Report 8.2
Equalities: Outreach will target women, ethnic minorities and those experiencing social isolation, and an Equality Impact Assessment will be completed at Full Business Case stage. Report 8.3, 8.4
Climate: The scheme reuses existing hardstanding, avoiding new build on undeveloped land, and will install energy-efficient LED lighting with smart controls and Sustainable Urban Drainage Systems compliant drainage. Report 9.1, 9.2
Risk: Identified risks include insufficient income, planning permission delays, procurement and tendering delays, limited court availability due to high demand, increased footfall and congestion, and booking system integration issues. Report P13, P14, P16, P17, P18, P19
Other: The finished courts will be managed by Lampton Leisure Ltd, a company wholly owned by the council. Report 7.3
Who and where
Users of Hanworth and Isleworth Leisure Centres, including existing tennis court users Report 6.1, P5
Lampton Leisure Ltd, which will manage the new courts under a varied service agreement Report 7.3, 6.6
Residents from lower-income households, older adults, people with disabilities, women, ethnic minorities and people experiencing social isolation, who are identified for targeted outreach Report 8.2, 8.3
Contractors and suppliers participating in the procurement of design and construction works Report 7.2, P47
Timeline
February to May 2026: Planning and design, including planning application and market engagement of contractors Report P46
June to July 2026: Procurement via approved framework, evaluation and contract award Report P47
August 2026: Mobilisation, contractor onboarding and site preparation Report P48
September to November 2026: Construction, including groundworks, padel court and canopy installation, and commissioning of lighting and access Report P49
December 2026: Commissioning and launch, including safety checks, staff training and community engagement Report P50
Plain English for the jargon
MRP: Minimum Revenue Provision, the charge to council revenue accounts to reflect the cost of capital expenditure funded by borrowing or credit arrangements
SuDS: Sustainable Urban Drainage Systems, drainage standards designed to manage surface water and reduce flood risk
EQIA: Equality Impact Assessment, an assessment of how a proposal may affect people with protected characteristics
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7
Resolved
· Cabinet approved delivery of the project to convert two existing underused tennis courts into three padel courts at both Hanworth and Isleworth Leisure Centres. · Cabinet approved the allocation of a project budget of £950,000 to be funded from the general fund capital programme unallocated budget for the delivery of the padel courts project. · Cabinet approved the drawdown of £90k from the project budget for the next phase of work, including design and planning. · Cabinet delegated authority to Executive Director of Finances and Resources to approve drawdown of the remaining project budget, subject to approval of an Outline and Full Business Case. · Cabinet delegated authority to the Acting Director of Environmental Services to authorise the commencement of procurement for and award of relevant services and works contracts required for the project. Cabinet delegated authority to the Director of ICP and Commissioning to Instruct the legal contract variations to the service agreements with Lampton Leisure, to take account of additional investment in leisure facilities and increased income.
Word for word from the decision Hounslow published for this meeting.Source: democraticservices.hounslow.gov.uk
Report Title New padel courts at Isleworth and Hanworth Leisure Centres
Member Reporting Councillor Salman Shaheen, Portfolio holder for Culture, Leisure and Public Spaces
Contact Details Melanie Fontinelle, Acting Director of Environmental Services [email protected] Martin Waddington, Director of the Integrated Care Partner (ICP) and Commissioning [email protected]
For Consideration By Cabinet
Date to be Considered 20 January 2026
Deadline for call-in 28 January 2026
Implementation Date 2 February 2026 (if not Called In)
Affected Wards Hanworth Park and Isleworth
Approved by
Official 1. Recommendations
Cabinet is asked to:
1. Approve delivery of the project to convert two existing underused tennis courts into three padel courts at both Hanworth and Isleworth Leisure Centres.
2. Approve the allocation of a project budget of £950,000 to be funded from the general fund capital programme unallocated budget for the delivery of the padel courts project.
3. Approve the drawdown of £90k from the project budget for the next phase of work, including design and planning.
4. Delegate authority to Executive Director of Finances and Resources to approve drawdown of the remaining project budget, subject to approval of an Outline and Full Business Case.
5. Delegate authority to the Acting Director of Environmental Services to authorise the commencement of procurement for and award of relevant services and works contracts required for the project.
6. Delegate authority to the Director of ICP and Commissioning to Instruct the legal contract variations to the service agreements with Lampton Leisure, to take account of additional investment in leisure facilities and increased income.
2. Report Summary
2.1This proposal seeks approval to progress a project converting two underused tennis courts into three padel courts at both Hanworth and Isleworth Leisure Centres. Padel is a rapidly growing sport that offers an accessible, social, and inclusive activity for residents of all ages. The project will revitalise underutilised assets, diversify the borough’s leisure offer, and support health and wellbeing priorities.
2.2The estimated capital cost for delivery is £950,000. The projected additional income across the two leisure centres is £1.4 million over four years, this is through existing members upgrading, new memberships and those playing on a pay as you go basis. The additional income is projected to increase incrementally from £215,000 in Year 1 to £518,000 by Year 4, which will reduce the net cost of operating the Council’s leisure centres and improve long-term financial sustainability.
2.3The initiative aligns with Hounslow’s Corporate Plan, Playing Pitch Strategy, and Lampton Leisure’s objectives to deliver high-quality, sustainable facilities that meet evolving community needs.
Official 3. Background and links to Corporate Priorities
3.1The Council is committed to improving health, wellbeing, and social inclusion through accessible and high-quality leisure provision. Current usage data shows a significant decline in tennis participation, with court occupancy falling by 27% compared to pre-pandemic levels. This underutilisation presents an opportunity to repurpose existing assets to meet changing community needs and preferences.
3.2Padel is one of the fastest-growing sports in the UK, recognised for its accessibility, sociable nature, and appeal across all age groups. Introducing padel courts at Hanworth and Isleworth Leisure Centres will diversify the borough’s leisure offer, attract new user groups, and maximise the value of existing infrastructure. This initiative supports the Council’s ambition to create vibrant, inclusive spaces that encourage active lifestyles and reduce health inequalities.
3.3The project directly aligns with Hounslow’s Corporate Plan priorities, including:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Delivery Plan Monitoring - Q4 2025/26Resolved : Cabinet agreed to: 1. Note progress to date with the programmes within the People Portfolio as set out in ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.