AI summaryHounslow's Audit and Governance Committee noted three external audit progress reports from Forvis Mazars LLP on the 2024/25 Statement of Accounts, Pension Fund Accounts, and Value for Money work.
Written from the decision and the officer reportPDF Pro
OutcomeNoted
MoneyNot stated
What happens nextNot stated
Who it affectsCouncil accounts and pension fundCovers the 2024/25 financial year for both the Council and Pension Fund.
What was decided
The committee noted the Audit Progress Report on the Council's Statement of Accounts 2024/25, submitted by Forvis Mazars LLP. Report 13.1
The committee noted the Audit Progress Report of the Council's Pension Fund Accounts 2024/25, submitted by Forvis Mazars LLP. Report 13.2
The committee noted the Value for Money Progress Report 2024/25, submitted by Forvis Mazars LLP. Report 13.3
Why
The report updates the committee on the status of the external audit of the Council's Statement of Accounts for the 2024/25 financial year. Report 11.1
The Accounts and Audit (Amendment) Regulations 2024, laid before Parliament on 9 September 2024 and in force from 30 September 2024, set the statutory deadlines for the audit. Report 7.1
What happens next
The Monitoring Officer expects that extension of time for publishing approved accounts will help the Council meet its statutory duties under the Audit and Accounts Regulations 2015 (as amended) in future years. Report 12.1
Implications
Equalities: The committee is not being asked to make any decisions with implications for equalities, community cohesion or public health. Report 8.1
Climate: There are no direct implications in the report relating to the Climate Emergency Action Plan. Report 9.1
Other: Financial implications are discussed throughout the report. Report 6.1
Other: No further implications arise from the report. Report 10.1
Who and where
London Borough of Hounslow, in respect of its 2024/25 Statement of Accounts and Pension Fund Accounts Report 13.1, 13.2, 13.3
Timeline
9 September 2024: Statutory Instrument 2024/907 laid before Parliament. Report 7.1
30 September 2024: Statutory Instrument 2024/907 came into force. Report 7.1
31 March 2025: Year-end covered by the three noted audit progress reports. Report 13.1, 13.2, 13.3
Plain English for the jargon
Forvis Mazars LLP: The Council's external auditors, who submitted the three progress reports.
Statutory Instrument 2024/907: The Accounts and Audit (Amendment) Regulations 2024, which gave effect to the backstop audit deadlines.
Backstop deadlines: Statutory deadlines set by the amendment regulations for completing local authority audits.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7
Resolved
That the Audit & Governance Committee noted the following reports, submitted by the Council’s external auditors, Forvis Mazars LLP: 1. Audit Progress Report on the Council’s Statement of Accounts 2024/25 (Appendix A ); 2. Audit Progress Report of the Council’s Pension Fund Accounts 2024/25 (Appendix B ); 3. Value for Money progress Report 2024/25 (Appendix C).
Word for word from the decision Hounslow published for this meeting.Source: democraticservices.hounslow.gov.uk
Report for: ACTION Contains Confidential or N Exempt Information Cabinet Key Decision N
Report Title External Audit Progress Update 2024/25 Accounts
Member Reporting Leader of the Council and Cabinet Member for Strategy, Resources and External Affairs
Contact Details Jake Bacchus Executive Director of Finance and Resources [email protected]
For Consideration By Audit and Governance Committee
Date to be Considered 3 February 2026
Deadline for call-in Not applicable as not an Executive decision
Implementation Date Not applicable (if not called in) Affected Wards All Wards
Approved by
1. Details of Recommendations
The Audit and Governance Committee is asked to note the following reports, submitted by the Council’s external auditors, Forvis Mazars LLP:
1. Audit Progress Report on the Council’s Statement of Accounts 2024/25 (Appendix A);
2. Audit Progress Report of the Council’s Pension Fund Accounts 2024/25 (Appendix B);
3. Value for Money progress Report 2024/25 (Appendix C). 2. Report Summary
2.1This report deals with the process for undertaking the external audit of the Statement of Accounts 2024/25.
2.2It asks that the Committee note the Audit Progress Report for the audit of the 2024/25 Statement of Accounts as submitted by Forvis Mazars LLP, the council’s external auditors. The document sets out the proposed disclaimed opinion which follows from the backstop arrangements introduced by the Accounts and Audit (Amendment) Regulations 2024.
2.3This recommendation is being made because part of the Committee’s remit is to oversee the external audit of the Statement of Accounts and provide appropriate challenge and support to the process.
2.4The Value for Money report is presented in draft for Audit and Governance Committee to review. The report is underpinned by National Audit Office guidance.
2.5All appendices are progress updates and final versions will be presented at Audit and Governance Committee when the audit is complete.
3. Background and links to Corporate Priorities
3.1The Council is required to prepare annual accounts in accordance with the Accounts and Audit Regulations issued by the Government. It is part of the role of the Audit and Governance Committee to ensure they have appropriate assurances over the robustness and accuracy of the Statement of Accounts.
4. Proposal and Rationale
Audit Completion Report (Main Accounts and Pension Fund)
4.1The Council’s 2024/25 draft Statement of Accounts were published within the statutory deadline on 30 June 2025. Residents were able to exercise their rights to publicly inspect the accounts and ask questions of the auditor under Regulation 14(1) of the Accounts and Audit Regulations 2015. This is a fixed period of time, which in the case of the 2024/25 Statement of Accounts was the 30 days from 2 July 2025 to 13 August 2025. There were no objections to the draft accounts.
4.2Since then, Forvis Mazars have performed their audit of the accounts in accordance with the Accounts and Audit (Amendment) Regulations 2024. The report is noted at Appendix A and gives a progress update with an expected disclaimed opinion. This disclaimed opinion has arisen from the backstopped opinion given on the 2023/24 accounts. The Council will continue to work with Forvis Mazars to build back assurance on the accounts within the timeframes set out in the regulations. 4.3. There are a range of material changes to the draft accounts that are outlined in Appendix A. These changes will be made in the final audited accounts. The Council recognises improvements needed in the reconciliation of its Fixed Assets Register and is currently in talks with its external valuer on the valuation estimations of Western International Market. It should be noted that these changes are not expected to impact the Council’s “bottom line” but instead would be taken through the Movement in Reserves Account and into unusable reserves.
4.4Forvis Mazars will continue to finalise their work and will report progress at the next Audit and Governance Committee meeting.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.